Current through October 31, 2024
Section 830.203 - Unreviewed safety question process(a) The contractor responsible for a Hazard Category 1, 2, or 3 DOE nuclear facility must establish, implement, and take actions consistent with a DOE-approved USQ procedure that meets the requirements of this section.(b) The contractor responsible for a new Hazard Category 1, 2, or 3 DOE nuclear facility must submit for DOE approval a procedure for its USQ process on a schedule that allows DOE approval in a safety evaluation report issued pursuant to § 830. 207(a) of this part.(c) The contractor responsible for a Hazard Category 1, 2, or 3 DOE nuclear facility must implement the DOE-approved USQ procedure in situations where there is a:(1) Temporary or permanent change in the facility as described in the existing documented safety analysis;(2) Temporary or permanent change in the procedures as described in the existing documented safety analysis;(3) Test or experiment not described in the existing documented safety analysis; or(4) Potential inadequacy of the documented safety analysis because the analysis potentially may not be bounding or may be otherwise inadequate.(d) A contractor responsible for a Hazard Category 1, 2, or 3 DOE nuclear facility must obtain DOE approval prior to taking any action determined to involve a USQ.(e) The contractor responsible for a Hazard Category 1, 2, or 3 DOE nuclear facility must annually provide to DOE a summary of the USQ determinations performed since the prior submittal.(f) If a contractor responsible for a Hazard Category 1, 2, or 3 DOE nuclear facility discovers or is made aware of a potential inadequacy of the documented safety analysis, it must:(1) Take action, as appropriate, to place or maintain the facility in a safe condition until an evaluation of the safety of the situation is completed;(2) Notify DOE of the situation;(3) Perform a USQ determination and notify DOE promptly of the results; and(4) Submit the evaluation of the safety of the situation to DOE prior to removing any operational restrictions initiated to meet paragraph (f)(1) of this section.