10 C.F.R. § 603.560

Current through September 30, 2024
Section 603.560 - Estimate of project expenditures
(a) To use a fixed-support TIA, rather than an expenditure-based TIA, the contracting officer must have confidence in the estimate of the expenditures required to achieve well-defined outcomes. Therefore, the contracting officer must work carefully with program officials to select outcomes that, when the recipient achieves them, are reliable indicators of the amount of effort the recipient expended. However, the estimate of the required expenditures need not be a precise dollar amount, as illustrated by the example in paragraph (b) of this section, if:
(1) The recipient is contributing a substantial share of the costs of achieving the outcomes, which must meet the criteria in § 603.305(a) ; and
(2) The contracting officer is confident that the costs of achieving the outcomes will be at least a minimum amount that can be specified and the recipient is willing to accept the possibility that its cost sharing percentage ultimately will be higher if the costs exceed that minimum amount.
(b) To illustrate the approach, consider a project for which the contracting officer is confident that the recipient will have to expend at least $800,000 to achieve the specified outcomes. The contracting officer must determine, in conjunction with program officials, the minimum level of recipient cost sharing required to demonstrate the recipient's commitment to the success of the project. For purposes of this illustration, let that minimum recipient cost sharing be 60% of the total project costs. In that case, the Federal share should be no more than 40% and the contracting officer could set a fixed level of Federal support at $320,000 (40% of $800,000). With that fixed level of Federal support, the recipient would be responsible for the balance of the costs needed to complete the project.
(c) Note, however, that the level of recipient cost sharing negotiated should be based solely on the level needed to demonstrate the recipient's commitment. The contracting officer may not use a shortage of Federal Government funding for the program as a reason to try to persuade a recipient to accept a fixed-support TIA, rather than an expenditure-based instrument, or to accept responsibility for a greater share of the total project costs than it otherwise is willing to offer. If there is insufficient funding to provide an appropriate Federal Government share for the entire project, the contracting officer should re-scope the effort covered by the agreement to match the available funding.

10 C.F.R. §603.560