Cal. Code Regs. Tit. 27, div. 1, 1, ch. 3, art. 1, tbl. 1

Current through Register 2024 Notice Reg. No. 50, December 13, 2024
Table 1 - Summary of Chapter 3, Article 1, Environmental Permit Timelines

TABLE 1

SUMMARY OF CHAPTER 3, ARTICLE 1,

ENVIRONMENTAL PERMIT TIMELINES

Note: This table provides general summary information only; see appropriate section of the text for regulatory language and conditions of applicability.
DEPARTMENTPERMIT/AUTHORIZATIONSECTIONTIME TO PROCESS PERMITS
Department of Toxic Substances ControlHazardous Waste Facility Permit (responsible agency for land disposal facility project)10300(b)1 Year
Department of Toxic Substances ControlHazardous Waste Facility Permit (responsible agency for non-land disposal facility project)10300(c)180 Days
Department of Toxic Substances ControlLead agency for development project requiring EIR10300(d), (e)1.5 Years
Department of Toxic Substances ControlLead agency for development project requiring NEG DEC10300(f), (g)195 Days
Department of Toxic Substances ControlHazardous Waste Hauler Registration10300(h)14 Days
Department of Toxic Substances ControlVariances10300(i), (j)180 Days
Department of Pesticide RegulationQualified Applicator Certificate10301(a)100 Days
Department of Pesticide RegulationAgricultural Pest Control Adviser License10301(b)100 Days
Department of Pesticide RegulationAgricultural Pest Control Adviser License Renewal10301(c)60 Days
Department of Pesticide RegulationQualified Applicator License10301(d)90 Days
Department of Pesticide RegulationDesignated Agent License10301(e)90 Days
Department of Pesticide RegulationDesignated Agent License Renewal10301(f)30 Days
Department of Pesticide RegulationPest Control Pilots License10301(g)30 Days
Department of Pesticide RegulationPest Control Pilots License Renewal10301(h)30 Days
Department of Pesticide RegulationAccreditation of Continued Education Instruction10301(i)30 Days
Department of Pesticide RegulationCertificate of Registration for Economic Poisons for New Active Ingredient10301(j)150 Days
Department of Pesticide RegulationCertificate of Registration for Economic Poisons for New Product10301(k)90 Days
Department of Pesticide RegulationCertificate of Registration for Economic Poisons for Renewal10301(l)60 Days
State Water Resources Control Board & Regional Water Quality Control BoardsWaste Discharge Requirements10302(b)120 Days
State Water Resources Control Board & Regional Water Quality Control BoardsGeneral Industrial Storm Water Permit10302(c)7 Days
State Water Resources Control Board & Regional Water Quality Control BoardsWastewater Treatment Plant Operators Certificate of Competence10302(d)30 Days
California Integrated Waste Management BoardFull Solid Waste Facilities Permit10303(a)120 Days
California Integrated Waste Management BoardStandardized Solid Waste Facilities Permit10303(b)75 Days
California Integrated Waste Management BoardRegistration Solid Waste Facilities Permit10303(c)30 Days
California Integrated Waste Management BoardWaste Tire Facility Permit10303(d)180 Days 1 Year (If lead agency.)
California Integrated Waste Management BoardUsed Oil Collection Center Certifications10303(e)45 Days
California Integrated Waste Management BoardUsed Oil Recycling Incentive Payment Registrations10303(f)45 Days
Air Resources BoardEmergency Variance for Sulfur in Gasoline or Diesel10304(b)(1)10 Days
Air Resources BoardApproval of Independent Testers10304(b)(2)90 Days
Air Resources BoardAll Other Permits10304(a)90 Days