Cal. Code Regs. tit. 22 § 60320.328

Current through Register 2024 Notice Reg. No. 49, December 6, 2024
Section 60320.328 - Reporting
(a) By July 1st of each year, a SWSAP WRA shall provide a report to the State Board and Regional Board, and make a copy of the report available to each SWSAP PWS affected by the SWSAP. Each SWSAP PWS shall be notified by direct mail and/or electronic mail of the availability of the report. The report shall be prepared by an engineer licensed in California and experienced in the fields of wastewater treatment and public water supply, or California-licensed engineers collectively having the experience. The report shall include the following:
(1) A summary of the SWSAP compliance status with the monitoring requirements and criteria of this Article during the previous calendar year;
(2) For any violations of this Article during the previous calendar year;
(A) the date, duration, and nature of the violation,
(B) a summary of any corrective actions and/or suspensions of delivery of recycled municipal wastewater to an augmented reservoir resulting from a violation, and
(C) if uncorrected, a schedule for and summary of all remedial actions;
(3) Any detections of monitored chemicals or contaminants, and any observed trends in the monitoring results of the augmented reservoir required pursuant to section 60320.326;
(4) A description of any changes in the operation of any unit processes or facilities;
(5) A description of any anticipated changes, along with an evaluation of the expected impact of the changes on subsequent unit processes;
(6) The estimated quantity and quality of the recycled municipal wastewater to be delivered for the next calendar year, as well as the quantity delivered during the previous three years; and
(7) A summary of the measures taken to comply with sections 60320.306 and 60320.301(e), and the effectiveness of the implementation of the measures.
(b) No less frequently than every five years from the date of the initial approval of the engineering report required pursuant to section 60323 of Article 7, Chapter 3, the SWSAP WRA shall update the engineering report to address any SWSAP changes from the previous engineering report, and submit the report to the State Board and Regional Board. The update shall include, but not be limited to, the anticipated increases in delivery of recycled municipal wastewater and a description of the expected impact the increase will have on the SWSAP WRA's ability to meet the requirements of this Article.

Cal. Code Regs. Tit. 22, § 60320.328

1. New section filed 8-7-2018; operative 10-1-2018 (Register 2018, No. 32).

Note: Authority cited: Sections 13521 and 13562, Water Code; and Section 116271, Health and Safety Code. Reference: Sections 13521, 13522.5, 13523, 13523.1 and 13562, Water Code.

1. New section filed 8-7-2018; operative 10/1/2018 (Register 2018, No. 32).