Cal. Code Regs. tit. 21 § 7503

Current through Register 2024 Notice Reg. No. 50, December 13, 2024
Section 7503 - Information Required in the Application

As a minimum, an eligible project must be submitted with an application to include:

(a) A description of the project, statement of reasons why the project is eligible for funding and anticipated benefits;
(b) A budget estimate, including capital and operating costs, revenues and sources and amounts of funding;
(c) An implementation schedule;
(d) Discussion of the following as each relates to the project:
(1) If the project is contained in the current adopted regional or state transportation improvement program, a statement to that effect is sufficient. If the project is not contained in the current adopted regional or state transportation improvement program, explain how the project is compatible with the current regional or state transportation plans.
(2) Summarize how the proposed project will meet special public transportation needs.
(3) If environmental clearance has been obtained, provide a copy of the Notice of Determination or the Notice of Exemption. If environmental clearance has not been obtained, provide an estimated date by which final environmental clearance will be obtained and indicate the type of document that will be prepared.
(4) Provide the estimated date that any allocated funds will be expended.

Cal. Code Regs. Tit. 21, § 7503

Note: Authority cited: Section 99241, Public Utilities Code. Reference: Section 99312, Public Utilities Code.