Within 90 days following the declaration by a county that an airport has a noise problem, and current estimates indicate that a noise impact area exists, the airport proprietor shall forward a schedule of major actions and events involved in the initiation of noise monitoring to the county and to the department. The schedule shall include an estimate of the number of dwelling units inside the 70 dB CNEL contour based upon current airport operations, and the forecast dates for budget amendments, contract award, system design, system construction, system installation, and the system becoming operational in cases where continuous monitoring is required.
Cal. Code Regs. Tit. 21, § 5035
Note: Authority cited: Section 21669, Public Utilities Code. Reference: Sections 21669- 21669.4, Public Utilities Code.