Current through Register 2024 Notice Reg. No. 44, November 1, 2024
Section 1803 - Alternative Certification Processes for Geothermal Power Plants(a) Eighteen-month certification process. The commission shall issue its decision on a geothermal notice as specified in Section 1727 of Article 2 within nine months from the date of accepting such notice, and except as provided in subsection (b), shall issue its final decision on an application within nine months from the date of acceptance of the application, or at such later times as are mutually agreed upon by the commission and the applicant.(b) Twelve-month certification process. If the applicant can demonstrate at the outset of the proceedings that the project complies with the provisions of Public Resources Code Section 25540.2(a), the commission shall issue its decision within 12 months of the acceptance of the application. Any application filed pursuant to Public Resources Code Section 25540.2(a) shall explicitly state that a commercial resource has been discovered and that a 12-month process is requested.Cal. Code Regs. Tit. 20, § 1803
1. Amendment filed 1-11-83; designated effective 2-1-83 pursuant to Government Code section 11346.2(d) (Register 83, No. 3).
2. Amendment filed 8-10-93; operative 9-9-93 (Register 93, No. 33). Note: Authority cited: Sections 25218(e) and 25541.5, Public Resources Code. Reference: Sections 25540, 25540.2(a) and 25540.3, Public Resources Code.