Cal. Code Regs. tit. 2 § 1859.199

Current through Register 2024 Notice Reg. No. 50, December 13, 2024
Section 1859.199 - Program Accountability

A project shall be deemed complete when either of the following occurs, whichever occurs first:

(a) The final notice of completion is filed for the project; or,
(b) Four years have elapsed from the final fund release for the project.

Projects will be subject to a Program Accountability Expenditure Audit pursuant to Section 1859.106. Any repayments due back to the state as a result of these audits will be subject to the repayment provisions identified in Section 1859.106.1.

Cal. Code Regs. Tit. 2, § 1859.199

Note: Authority cited: Sections 17070.35 and 17078.72(k), Education Code. Reference: Section 17078.72, Education Code.

Note: Authority cited: Sections 17070.35 and 17078.72(k), Education Code. Reference: Section 17078.72, Education Code.

1. New section filed 7-13-2007 as an emergency; operative 7-13-2007 (Register 2007, No. 28). Pursuant to Education Code section 17078.72(k) a Certificate of Compliance must be transmitted to OAL by 7-14-2008 or emergency language will be repealed by operation of law on the following day.
2. Editorial correction of History 1 (Register 2007, No. 52).
3. Certificate of Compliance as to 7-13-2007 order transmitted to OAL 3-18-2008 and filed 4-29-2008 (Register 2008, No. 18).
4. Repealer of last paragraph filed 2-1-2024; operative 2/1/2024 pursuant to Government Code section 11343.4(b)(3) (Register 2024, No. 5).