The purpose of these rules is to administer and implement Ark. Code Ann. § 22-10-101 et seq. regarding partnerships for public facilities and infrastructure.
Additional information may include, but is not limited to, architectural and engineering (A/E) drawings and feasibility studies.
The following timelines shall be followed for the development of Qualified Projects. If an RPE has requested and been approved for an accelerated timeline, the Expedited Timeline shall be followed for the selection of a Qualified Project. The days listed are calendar days.
Event | Standard Timeframe | Expedited Timeframe |
Affected local jurisdiction and other public entity notification prior to RFP issuance | 60 days | 30 days |
Submittal of RFP to TSS prior to publication | 60 days | 30 days |
Duration of RFP publication from advertisement to response deadline | 45-120 days* | 45-90 days* |
Execution of Comprehensive Agreement | 180 days** after RFP response deadline | 120 days** |
* May be extended by the RPE up to an additional 120 days with the consent of TSS.
** This deadline may be extended to up to 365 calendar days by mutual written agreement of both parties.