COMMISSION FOR ARKANSAS PUBLIC SCHOOL ACADEMIC FACILITIES AND TRANSPORTATION RULES GOVERNING THE ACADEMIC FACILITIES PARTNERSHIP PROGRAM
The Commission for Arkansas Public School Academic Facilities and Transportation (CAPSAFT) authority for promulgating these Rules is pursuant to Ark. Code Ann. §§ 6-21-114, 6-20-2507, 6-20-2512, and 25-15-201et seq.
* Warm, Safe, and Dry Space Replacement and Systems Replacement Projects, and;
* Space/Growth Projects (new facilities, additions, conversions)
If the state provides financial participation for an addition or conversion project, or a consolidation or annexation project that adds space to an existing campus, the district must construct any missing component to the POR specification. The district will have to submit an accurate and complete POR, to include all existing spaces. If the POR indicates deficient space components, the district must satisfy these components in the following order:
* Academic Core Areas;
* Special Education;
* Student Dining;
* Administrative
The state will not participate in addition projects concerning gymnasiums, media centers, or auditoriums if the district already has this space or is in need (according to the POR) of Academic Core Areas, Special Education, or Student Dining Areas. State Financial Participation shall not be used for any gym space used for competition. State financial participation for undersized facilities shall be limited to the space required to bring a facility up to size, and shall not be approved for a new facility based on size alone. Any new project must be deemed a prudent use of state funds.
School districts are encouraged to discuss with the Division before entering into demolition projects when the districts will be filing applications for state partnership assistance.
School districts applying for state financial participation for projects that support their facilities master plan shall file applications (that include accurate and complete PORs, resolutions, schematic drawings, and other required documentation) in a format prescribed by the Division and shall list the applications in the district's Facilities Master Plan. No project shall be approved if the district does not have a complete and approved facilities master plan as of September 1 of each even-numbered year. No project application shall be submitted, reviewed, or approved if the district has begun construction on the project.
For each of the two years of a Partnership Program funding cycle there will be two (2) categories of funds from which to fund projects: one for Warm, Safe, and Dry System Replacement and Space Replacement projects; and one for Space/Growth projects. Projects will be funded as follows for each year of a funding cycle:
By September of each even-numbered year, the Division may notify districts of the approval or disapproval of projects, as well as of the approved square footage, and approved components of a Warm, Safe, and Dry Systems Replacement project. Districts wishing to appeal any of these Division determinations must do so within sixty (60) days of receipt of the Division's determination letter. Districts may appeal the funding cost factor calculation within sixty (60) days of the Commission's determination concerning projected funding.
The Division's notice of its decision on a school district's application for state financial participation in a new construction project will include an explanation of the evaluation factors underlying the decision of the Division to provide or not provide state financial participation in support of the new construction project.
203.01.22 Ark. Code R. 001