COMMISSION FOR ARKANSAS PUBLIC SCHOOL ACADEMIC FACILITIES AND TRANSPORTATION RULES GOVERNING THE ACADEMIC FACILITIES PARTNERSHIP PROGRAM
The Commission for Arkansas Public School Academic Facilities and Transportation (CAPSAFT) authority for promulgating these Rules is pursuant to Ark. Code Ann. §§ 6-21-114, 6-20-2507, 6-20-2512, and 25-15-201et seq.
Districts may request to use ten (10) year enrollment projections to be used in calculating all spaces and space sizes.
* Warm, Safe, and Dry Space Replacement and Systems Replacement Projects, and;
* Space/Growth Projects (new facilities, additions, conversions)
If the state provides financial participation for an addition or conversion project, or a consolidation or annexation project that adds space to an existing campus, the district must construct any missing component to the POR specification. The district will have to submit an accurate and complete POR, to include all existing spaces. If the POR indicates deficient space components, the district must satisfy these components in the following order:
* Academic Core Areas;
* Special Education;
* Student Dining;
* Administrative
The state will not participate in addition projects concerning gymnasiums, media centers, or auditoriums if the district already has this space or is in need (according to the POR) of Academic Core Areas, Special Education, or Student Dining Areas. State Financial Participation shall not be used for any gym space used for competition. State financial participation for undersized facilities shall be limited to the space required to bring a facility up to size, and shall not be approved for a new facility based on size alone. Any new project must be deemed a prudent use of state funds.
School districts are encouraged to discuss with the Division before entering into demolition projects when the districts will be filing applications for state partnership assistance.
School districts applying for state financial participation for projects that support their facilities master plan shall file applications (that include accurate and complete PORs, resolutions, schematic drawings, and other required documentation) in a format prescribed by the Division and shall list the applications in the district's Facilities Master Plan. No project shall be approved if the district does not have a complete and approved facilities master plan as of September 1 of each even-numbered year. No project application shall be submitted, reviewed, or approved if the district has begun construction on the project.
All Warm, Safe, and Dry Space Replacement projects that involve the Division-approved demolition or repurposing of space for replacement of the same space will be considered a prudent and resourceful expenditure of state funds issue upon approval by the Division and in compliance with POR requirements.
Once each district is ranked, the Division shall publish a list with the district with the lowest score being ranked first and the district with the highest score being ranked last.
For each of the two years of a Partnership Program funding cycle there will be two (2) categories of funds from which to fund projects: one for Warm, Safe, and Dry System Replacement and Space Replacement projects; and one for Space/Growth projects. Projects will be funded as follows for each year of a funding cycle:
By September of each even-numbered year, the Division may notify districts of the approval or disapproval of projects, as well as of the approved square footage, and approved components of a Warm, Safe, and Dry Systems Replacement project. Districts wishing to appeal any of these Division determinations must do so within sixty (60) days of receipt of the Division's determination letter. Districts may appeal the funding cost factor calculation within sixty (60) days of the Commission's determination concerning projected funding.
The Division's notice of its decision on a school district's application for state financial participation in a new construction project will include an explanation of the evaluation factors underlying the decision of the Division to provide or not provide state financial participation in support of the new construction project.
ACADEMIC FACILITIES PARTNERSHIP PROGRAM
PROJECT AGREEMENT
(Applicable beginning with Partnership Projects for 2023-2025 Biennium)
Project Name: Click to enter Project Name.
Project Number: Click to enter Project Number.
This Project Agreement ("Agreement") is made and entered into by and between the Division of Public School Academic Facilities and Transportation ("Division") and the Click to enter District Name School District ("District"), Click to enter County. County, pursuant to A.C.A. § 6-20-2507.
WHEREAS, The Division, created pursuant to Act 1327 of 2005 is a body corporate and politic, an agency of state government and an instrumentality of the State of Arkansas ("State"), performing essential government functions of the State; and
WHEREAS, the District is acting as an agency of state government, performing essential functions of government pursuant to the laws of the State of Arkansas, and
WHEREAS, the District and the Division have approved a Master Facilities Plan describing the classroom facilities needs of the entire student population of the District, and the total budget for the Public School Academic Facilities Project ("Project"); and
WHEREAS, the District and the Division acknowledge that for funding and planning purposes, the Project is anticipated to commence on Click to enter Date.
and be completed on Click to enter Date. .
NOW, THEREFORE, in consideration of the mutual promises herein contained, the District and the Division agree to cooperate in the design, construction and terms described herein and as follows.
This Project Agreement ("Agreement") will become effective upon the signing of both parties and be binding on the date signed by the Director of the Division of Public School Academic Facilities. The District certifies that scope planning and financial planning have been completed prior to the project application submission. The District may have, at the District's own expense and risk, begun developing construction plans and specifications and began seeking all required state agency approvals. No additional aspect of the project including construction will proceed prior to the signing of this Agreement. By signing the Agreement the District certifies that it has not begun the project beyond the steps outlined above. The Division and State of Arkansas is not obligated to pay any expenditures until the project has been approved and funded by the Commission. The signing of this Agreement certifies that the Commission for Arkansas Public School Academic Facilities and Transportation ("Commission") has approved the project and funding under the Academic Facilities Partnership Program. The District further acknowledges by signing the Agreement that, should it be determined that the Project began prior to the signing of this Agreement, the Commission may exercise one of the following options:
If this is a warm, safe and dry project, give complete description of the system, or systems, being replaced in the detailed scopes of steps 3 and 43. District inserts detail scope of the actual total project here:
(Do not attach the application/funded scope as the total scope)
(Do not attach the application as the scope)
State financial participation of the total Project budget shall be: $ Click to enter State Participation.
State "green building incentive": $ Click to enter Green Building Incentive.
Total State financial participation: $ Click to enter Total State Financial Participation.
The District's local share of the total Project budget shall be $ Click to enter Districts Local Share of Project. as set forth in Article IV of this Agreement.
The Division and District shall be responsible for the following:
School District | Division |
Determination of Project Scope (Partnership Project Application) | Review and approval (application review) |
Architect/Engineer, Construction Manager (if desired), Construction Contractor selection process | Provide guidance as requested pertaining to procurement laws |
Submittal of Project Construction drawings in PDF format and full sized printed copy (preliminary floor plans for space projects recommended for preliminary review) | Review for conformance with the Arkansas Public School Academic Facility Manual |
Site selection and request | Provide recommended guidelines contained in the Arkansas Public School Academic Facility Manual |
Request for variance consideration of the Arkansas Public School Academic Facility Manual | Division plan review and variance determination |
Bid procedures | No action |
Submission of project approval forms and state reviews | Final project approval |
Recommendation of award, notification of bids Fund management in accordance with Arkansas Department of Education accounting guidelines | No action Audit option |
Provide Maintenance Plan/Certification | Verify new buildings are in the MAPPSl database and the computerized maintenance management system |
Enter new buildings and spaces into the Master Plan Web Tool as prescribed by the Division | Division review |
(To include letters of credit, moneys donated or contributions spent directly by a third party.)
(Specify origin of Grant and any special conditions that might affect this Project as a result of the grant award.) Includes FEMA/ADEM (safe rooms).
(To include Maintenance Escrow accounts.)
No Fund moneys shall be spent for any items inconsistent with the provisions of the Arkansas School Facility Manual and Division policies, unless a variance is approved by the Division.
Upon completion of the project and prior to final payment by the Division, the District will create the preventative maintenance schedules of any new space facility included in the District's overall maintenance plan contained in the District's computerized maintenance management system as required by the Academic Facilities Master Plan prior to final payment by the Division.
In witness whereof, the parties have executed this Agreement on the date(s) set forth below.
203.01.21 Ark. Code R. 002