Maximum Points | Category | Factors to consider |
30 | Site Conditions | The applicant's site has favorable site conditions including but not limited to adequate size, favorable slope, minimal wetlands, outside of the 100-year floodplain, industrial zoning, compatible neighboring land use, and controlled access to the site. |
25 | Utilities | The applicant's site has proximity and capacity for: electricity, natural gas, water, sewer, and telecommunications. |
20 | Transportation Infrastructure | The applicant's site has proximity to paved roads, rail infrastructure, intermodal facilities, ports, or commercial airports. |
10 | Site Due Diligence | The applicant's site has undergone site due diligence studies in the last 5 years including but not limited to: geotechnical survey, environmental studies, endangered species survey, archeological survey, wetlands delineation, and soil borings. |
5 | Current Marketing Efforts | The applicant's site is actively being marketed for industrial use, the site has hosted prospects for site visits, the site is currently under consideration for an active economic development project, or both. |
5 | Local Match | The applicant's match is above the minimum 5% required for eligibility. |
5 | Site Certification | The applicant's site is currently a certified site or Competitive Communities Initiative (CCI) designated site. |
100 Total Maximum Points Possible |
003.19.24 Ark. Code R. 003