Current through Register Vol. 30, No. 50, December 13, 2024
Section R9-1-505 - Sliding Fee Schedule Approval Time-framesA. The overall time-frame described in A.R.S. § 41-1072(2) for a request for sliding fee schedule approval is 32 days. 1. A provider and the Department may agree in writing to extend the substantive review time-frame and the overall time-frame.2. An extension of the substantive review time-frame and the overall time-frame shall not exceed eight days.B. The administrative completeness review time-frame described in A.R.S. § 41-1072(1) for a request for sliding fee schedule approval is 11 days, beginning on the day the Department receives the request. 1. Except as provided in subsections (B)(3) and (B)(4), the Department shall mail to a provider a written notice of administrative completeness when the provider's request for sliding fee schedule approval is complete.2. If a request for sliding fee schedule approval is incomplete, the Department shall mail to the provider a written notice of administrative deficiencies that:a. Lists the missing documents or incomplete information, andb. Suspends the administrative completeness review time-frame and the overall time-frame from the date on the notice of administrative deficiencies: i. Until the date the Department receives a complete request for sliding fee schedule approval; orii. For 60 days, whichever comes first.3. If the Department does not receive all the additional documents or information required under subsection (B)(1) within 60 days after the date on the notice of administrative deficiencies, the Department deems the request for sliding fee schedule approval withdrawn.4. If the Department approves a sliding fee schedule during the administrative completeness review time-frame, the Department does not issue a separate written notice of administrative completeness.C. The substantive review time-frame described in A.R.S. § 41-1072(3) for a request for sliding fee schedule approval is 21 days, beginning on the date on the Department's notice of administrative completeness under subsection (B)(1). 1. The Department shall mail to a provider a written notice granting or denying approval according to A.R.S. § 41-1076 by the last day of the substantive review time-frame and the overall time-frame.2. If the Department issues to a provider a written request for additional information according to A.R.S. § 41-1075(A), the request for additional information suspends the substantive review time-frame and the overall time-frame from the date on the request for additional information:a. Until the date the Department receives all the information requested; orb. For 60 days, whichever comes first.3. If the Department does not receive all the information requested under subsection (C)(2) within 60 days after the postmark date of the request for additional information, the Department shall deny sliding fee schedule approval.D. If a time-frame's last day falls on a Saturday, Sunday, or state service holiday listed in A.A.C. R2-5-402, the Department considers the next business day the time-frame's last day. Ariz. Admin. Code § R9-1-505
New Section made by final rulemaking at 12 A.A.R. 3990, effective December 4, 2006 (Supp. 06-4).