Ariz. Admin. Code § 18-9-B610

Current through Register Vol. 30, No. 50, December 13, 2024
Section R18-9-B610 - Waiver of Requirement by Director
A. When injection does not occur into, through, or above an USDW, the Director may authorize a well or project with less stringent requirements for area of review, construction, mechanical integrity, operation, monitoring, and reporting than required under this Article or R18-9-D636 to the extent that reduction in requirements will not result in an increased risk of movement of fluids into an USDW.
B. When injection occurs through or above an USDW, but the radius of endangering influence when computed under R18-9-B612(A) is smaller or equal to the radius of the well, the Director may authorize a well or project with less stringent requirements for operation, monitoring, and reporting than required under R18-9-D636 to the extent that a reduction in requirements will not result in an increased risk of movement of fluids into an USDW.
C. When reducing requirements under this Section, the Director shall prepare a fact sheet under R18-9-C619 explaining the reasons for the action.

Ariz. Admin. Code § R18-9-B610

New Section made by final rulemaking at 28 A.A.R. 1903, effective 9/6/2022.