Current through Register Vol. 30, No. 50, December 13, 2024
Section R18-2-410 - Visibility and Air Quality Related Value Protection
A. Applicability.1. All of the requirements of this Section apply to a new major source or major modification that would be constructed in an area that is designated attainment or unclassifiable.2. Subsections (B) to (D) apply to the following:a. A new major source or major modification that may have an impact on any integral vista of a mandatory federal Class I area, if it is identified in accordance with 40 CFR 51.304 by the Federal Land Manager at least twelve months before submission of a complete permit application for the source or modification, except where the Federal Land Manager has provided notice and opportunity for public comment on the integral vista, in which case the review must include impacts on any integral vista identified at least six months before submission of a complete permit application. This subsection shall not apply if the Director determines under 40 CFR 51.304(d) that the identification was not in accordance with the identification criteria. b. A new major source or major modification that proposes to locate in an area designated as nonattainment and that may have an impact on visibility in any mandatory federal Class I area. B. Application Requirements. Any application for a permit or permit revision to construct a major source or major modification subject to this section shall contain: 1. An analysis of the impairment to visibility, soils, and vegetation that would occur as a result of the new source or modification and general commercial, residential, industrial, and other growth associated with the new source or modification. The applicant need not provide an analysis of the impact on vegetation having no significant commercial or recreational value.2. An analysis of the air quality impact projected for the area as a result of general commercial, residential, industrial, and other growth associated with the new source or modification.C. Notification Requirements.1. The Director shall provide written notice of the application for a permit or permit revision subject to this section to the Administrator, the Federal Land Manager and the federal official charged with direct responsibility for management of any lands within any Class I area that may be affected by the source or modification. The notice shall be provided within 30 days of receipt of the application and at least 60 days before any public hearing on the application. The notice shall: a. Include a copy of the application and all information relevant to the permit or permit revision under this Article;b. Include an analysis of the anticipated impacts of the proposed source on visibility in any federal Class I area; andc. Provide for no less than a 30-day period within which written comments may be submitted.2. The Director shall notify the individuals identified in subsection (C)(1) within 30 days of receipt of any advance notification of any such permit or permit revision.3. The Director shall notify the individuals identified in subsection (C)(1) of the preliminary determination for the application under R18-2-402(I)(2)(c) and shall make available any materials used in making that determination.4. The Director shall provide notice to the administrator of every action related to the consideration of such permit or permit revision.D. Consideration of Federal Land Manager Analysis. 1. The Federal Land Manager and the federal official charged with direct responsibility for management of federal Class I areas have an affirmative responsibility to protect the air quality related values, including visibility, of any such areas and to consider, in consultation with the Administrator, whether a proposed source or modification would have an adverse impact on such values.2. The Director shall consider any analysis performed by the Federal Land Manager and provided within 30 days of the notification required by subsection (C)(1) that shows that a proposed new major stationary source or major modification may have an adverse impact on visibility in a federal Class I area or integral vista.3. In considering the analysis, the Director shall ensure that the source's emissions will be consistent with making reasonable progress toward the national visibility goal referred to in 40 CFR 51.300(a), taking into account the costs of compliance, the time necessary for compliance, the energy and nonair quality environmental impacts of compliance, and the useful life of the source.4. If the Director concurs with the analysis, the Director shall deny the permit or permit revision.5. If the Director finds that the analysis does not demonstrate to the satisfaction of the Director that an adverse impact on visibility will result in the federal Class I area or integral vista, the Director shall, in the notice required by R18-2-402(I)(2)(c), either explain that decision or give notice as to where the explanation can be obtained.E. Federal Land Manager Analysis Showing Adverse Impact Despite Compliance with Maximum Allowable Increases for Class I Area.1. Within 30 days after the notification required by subsection (C)(3), the Federal Land Manager may present to the Director a demonstration that the emissions attributed to a new major source or major modification would have an adverse impact on visibility or other specifically defined air quality related values of any mandatory federal Class I area, even though the change in air quality resulting from emissions attributable to the source or modification will not cause or contribute to concentrations that exceed the maximum increases allowed for the area in R18-2-218.2. If the Director concurs with the demonstration, the Director shall not issue a permit or permit revision for the major source or major modification.F. Class I Variance with Federal Land Manager Concurrence.1. The owner or operator of a proposed source or modification may demonstrate to the Federal Land Manager that emissions from the source will have no adverse impact on the air quality related values (including visibility) of federal Class I areas, even though the change in air quality resulting from emissions from the source or modification are projected to cause or contribute to concentrations that exceed the maximum increases allowed for a Class I area under R18-2-218.2. If the Federal land manager concurs with the demonstration and so certifies to the Director, the Director may issue the permit, provided that:a. Applicable requirements are otherwise met; andb. The permit contains emission limits necessary to assure that emissions of sulfur dioxide, PM2.5, PM10, and nitrogen oxides will not cause increases in ambient concentrations of those pollutants exceeding the following maximum allowable increases over minor source baseline concentrations: Pollutant | Maximum allowable increase (micrograms per cubic meter) |
PM2.5 |
Annual arithmetic mean | 4 |
24-hr maximum | 9 |
PM10 |
Annual arithmetic mean | 17 |
24-hr maximum | 30 |
Sulfur dioxide: |
Annual arithmetic mean | 20 |
24-hr maximum | 91 |
3-hr maximum | 325 |
Nitrogen dioxide |
Annual arithmetic mean | 25 |
G. Class I Sulfur Dioxide Variance by Governor with Concurrence by Federal Land Manager or President. 1. The owner or operator of a proposed source or modification that cannot be approved under subsection (F) may demonstrate to the Governor that the source cannot be constructed by reason of any maximum allowable increase for sulfur dioxide for a period of twenty-four hours or less applicable to any Class I area and, in the case of mandatory federal Class I areas, that a variance under this clause would not adversely affect the air quality related values of the area (including visibility). The Governor, after consideration of the Federal Land Manager's recommendation (if any) and subject to his concurrence, may, after notice and public hearing, grant a variance from the maximum allowable increase. If the variance is granted, the Director shall issue a permit or permit to the source or modification pursuant to the requirements of subsection (G)(3), provided that the applicable requirements of R18-2-406 are otherwise met.2. In any case where the Governor recommends a variance in which the Federal Land Manager does not concur, the recommendations of the Governor and the Federal Land Manager shall be transmitted to the President. The President may approve the Governor's recommendation if the President finds that the variance is in the national interest. If the variance is approved, the Director shall issue a permit pursuant to subsection (G)(3), provided that the applicable requirements of R18-2-406 are otherwise met.3. In the case of a permit issued pursuant to subsection (G)(1) or (G)(2) the source or modification shall comply with emission limitations necessary to assure that emissions of sulfur dioxide from the source or modification will not (during any day on which the otherwise applicable maximum allowable increases are exceeded) cause or contribute to concentrations that would exceed the following maximum allowable increases over the baseline concentration and to assure that the emissions will not cause or contribute to concentrations that exceed the otherwise applicable maximum allowable increases for periods of exposure of 24 hours or less for more than 18 days, not necessarily consecutive, during any annual period: Maximum Allowable Increase [Micrograms per cubic meter] |
Period of exposure | Terrain areas |
Low | High |
24-hr maximum | 36 | 62 |
3-hr maximum | 130 | 221 |
H. Visibility Monitoring. The Director may require monitoring of visibility in any federal Class I area near a proposed major source or major modification for such purposes and by such means as the Director deems necessary and appropriate.Ariz. Admin. Code § R18-2-410
Adopted effective May 14, 1979 (Supp. 79-1). Former Section R9-3-410 renumbered without change as Section R18-2-410 (Supp. 87-3). Section R18-2-410 renumbered to R18-2-610, new Section R18-2-410adopted effective November 15, 1993 (Supp. 93-4). Amended by final rulemaking at 23 A.A.R. 333, effective 3/21/2017.