In addition to the definitions in A.A.C. R18-1-501, and 18 A.A.C. 4, the following terms apply to this Article:
"Design review" means the process for reviewing an application for an Approval to Construct as prescribed in A.A.C. R18-5-505(B).
"Design review service" means all activities related to processing an application for an Approval to Construct, including reviewing, approving, or denying an application, conducting a pre-application meeting or site visit, or other activity required to review an Approval to Construct application.
"Distribution system" has the same meaning prescribed in A.A.C. R18-5-101.
"Priority Review" means a design review service where a license application is reviewed using not more than 50% of the total review time-frame for an Approval to Construct license application.
"Public water system" has the same meaning prescribed in A.R.S. § 49-352(B).
"Licensing time-frame" means a period of time described and defined in A.R.S. Title 41, Chapter 6, Article 7.1, and 18 A.A.C. 1, Article 5.
"Water treatment plant" has the same meaning prescribed in A.A.C. R18-5-101.
Ariz. Admin. Code § R18-14-201