Ariz. Admin. Code § tit. 18, ch. 14, art. 1, tbl. 3

Current through Register Vol. 30, No. 45, November 8, 2024
Table 3 - AZPDES Annual Fees

Permit Type

Annual Fee

Annual Fee if New Facility Under New AZPDES Not Yet Constructed

Municipal separate storm sewer system

$14,270

N/A

Wastewater treatment plant (based on gallons of discharge per day):

* Less than 99,999

$357

$357

* 100,000 to 999,999

$714

$714

* 1,000,000 to 9,999,999

$3,568

$892

* 10,000,000 or more

$5,708

$1,070

Facility or activity that is not a wastewater treatment plant or municipal separate storm sewer and designated in the permit as either:

Major

$3,568

$892

Minor

$714

$714

Pretreatment program

$4,281

N/A

Consolidated individual permit for multiple AZPDES individual permits, as allowed under A.A.C. R18-9-B901(C)

Aggregate of the applicable annual fees of each individual permit

Aggregate of the applicable annual fees of each individual permit

Ariz. Admin. Code tit. 18, ch. 14, art. 1, tbl. 3

Table 3 by final rulemaking at 17 A.A.R. 568, effective July 1, 2011 (Supp. 11-2). Amended by final rulemaking at 29 A.A.R. 1869, effective 8/4/2023.