Ariz. Admin. Code § 18-12-219

Current through Register Vol. 30, No. 50, December 13, 2024
Section R18-12-219 - Installation of New UST Systems
A. An owner or operator that intends to bring a new underground storage tank system into operation shall submit to the Director on a Department form all of the following information at least 30 days before beginning installation:
1. The tank's size, construction material, manufacturer, and intended system contents;
2. The certified UST service provider who will perform or supervise the installation;
3. Detailed installation plans showing the site drawn to scale, piping layouts, electrical service, and stating that the tanks will be installed according to the manufacturer's instructions, and the applicable installation standards and codes of practice in R18-12-220 and R18-12-281;
4. Evidence that the intended system contents are compatible with the UST system;
5. A statement describing how the owner or operator plans to satisfy financial responsibility in accordance with Article 3;
6. The intended installation schedule with the proposed backfill date.
B. Within 15 calendar days of receipt of the information required in subsection (A), the Department shall send the owner or operator an email indicating whether the proposed installation may or may not proceed, or whether further information is necessary.
C. An owner or operator may not backfill a new tank system installation until approval by a representative of the Director after an onsite inspection. At the time of inspection the owner or operator shall have on site certifications for all equipment and test results for all piping.

Ariz. Admin. Code § R18-12-219

Amended by final rulemaking at 25 A.A.R. 3123, effective 1/1/2020.