Current through Register Vol. 30, No. 50, December 13, 2024
Section R14-2-306 - Service Lines and EstablishmentsA. Priority and timing of service establishments 1. After an applicant has complied with the utility's application and deposit requirements and has been accepted for service by the utility, the utility shall schedule that customer for service establishment.2. Service establishments shall be scheduled for completion within five working days of the date the customer has been accepted for service, except in those instances when the customer requests service establishment beyond the five working day limitation.3. When the utility has made arrangements to meet with a customer for service establishment purposes and the utility or the customer cannot make the appointment during the prearranged time, the utility shall reschedule the establishment to the satisfaction of both parties.4. Each utility shall schedule service establishment appointments within a maximum range of four hours during normal working hours, unless another time-frame is mutually acceptable to the utility and the customer.5. Service establishments shall be made only by qualified utility service personnel.6. For the purposes of this rule, service establishments are where the customer's facilities are ready and acceptable to the utility and the utility needs only to install or read a meter or turn the service on.B. Service lines 1. Customer provided facilities a. An applicant for services shall be responsible for the safety and maintenance of all customer piping from the point of delivery.b. Meters shall be installed in a location suitable to the utility where the meters will be safe from street traffic, readily and safely accessible for reading, testing and inspection, and where such activities will cause the least interference and inconvenience to the customer. The customer shall provide, without cost to the utility, at a suitable and easily accessible location, sufficient and proper space for the installation of meters.c. Where the meter or service line location on the customer's premises is changed at the request of the customer or due to alterations on the customer's premises, the customer shall provide and have installed at his expense all customer piping necessary for relocating the meter and the utility may make a charge for moving the meter and/or service line.2. Company provided facilities a. Each utility shall file for Commission approval, a service line tariff which defines the maximum footage and/or equipment allowance to be provided by the utility at no charge; the maximum footage and/or equipment allowance may be differentiated by customer class.b. Any service line in excess of that allowed at no charge shall be paid by the customer as a contribution in aid of construction.3. Easements and rights-of-way a. Each customer shall grant adequate easement and right-of-way satisfactory to the utility to ensure proper service connection. Failure on the part of the customer to grant adequate easement and right-of-way shall be grounds for the utility to refuse service.b. When a utility discovers that a customer or his agent is performing work or has constructed facilities adjacent to or within an easement or right-of-way and such work, construction or facility poses a hazard or is in violation of federal, state or local laws, ordinances, statutes, rules or regulations, or significantly interferes with the utility's access to equipment, the utility shall notify the customer or his agent and shall take whatever actions are necessary to eliminate the hazard, obstruction or violation at the customer's expense.Ariz. Admin. Code § R14-2-306
Adopted effective March 2, 1982 (Supp. 82-2).