Current through Register Vol. 30, No. 50, December 13, 2024
Section R14-2-2606 - Easements and Rights-of-WayA. Where an easement or right-of-way does not exist, but is required by a Utility to accommodate Interconnection, a Customer shall provide a suitable easement or right-of-way, in the Utility's name, on the premises owned, leased, or otherwise controlled by the Customer. If the required easement or right of way is on another's property, the Customer shall obtain and provide to the Utility a suitable easement or right-of-way, in the Utility's name, at the Customer's expense and in sufficient time to comply with Interconnection Agreement requirements.B. A Utility shall use reasonable efforts to utilize existing easements to accommodate Interconnection.C. A Utility shall use reasonable efforts to assist a Customer in securing necessary easements at the Customer's expense.Ariz. Admin. Code § R14-2-2606
Adopted by final rulemaking at 26 A.A.R. 473, effective 2/25/2020.