Current through Register Vol. 30, No. 50, December 13, 2024
Section R14-2-2513 - Baseline EstimationA. To determine the baseline, an affected utility shall estimate the level of gas demand and consumption and the associated costs that would have occurred in the absence of a DSM program.B. For installations or applications that have multiple fuel choices, an affected utility shall determine the baseline using the same fuel source that would have actually been used for the installation or application in the absence of a DSM program.Ariz. Admin. Code § R14-2-2513
New Section made by final rulemaking at 17 A.A.R. 72, effective March 4, 2011 (Supp. 11-1).