Current through Register Vol. 30, No. 50, December 13, 2024
Section R12-7-187 - Injection Project ReportA. Each operator of an injection project shall furnish for each injection well for each calendar month a report of injection project containing information and data including the lease and well number, the well's state permit number, average injection pressure during the month, amount of fluid in barrels injected during the month, the total amount of fluid injected to date, the source of the injected fluid, and the number of days the injection well was operated during the month.B. Operators of injection projects shall file reports required in this Section with the Commission on or before the 25th day of the next succeeding month.Ariz. Admin. Code § R12-7-187
Adopted effective February 23, 1993 (Supp. 93-1).