Ariz. Admin. Code § 12-15-820

Current through Register Vol. 30, No. 45, November 8, 2024
Section R12-15-820 - Request for Variance
A. If extraordinary or unusual conditions exist, a well drilling contractor or owner may request a variance from the provisions of this Article.
B. The request for variance shall be in writing and shall set forth the location of the well site, the reasons for the request, and the recommended requirements to be applied. The Director may approve the request only if the well drilling contractor or owner has clearly demonstrated that the variance will not adversely affect other water users or the local aquifers.
C. A variance shall not be effective until the well drilling contractor or owner receives from the Director a written approval of the variance and a new drilling card stamped "variance issued."

Ariz. Admin. Code § R12-15-820

Adopted effective March 5, 1984 (Supp. 84-2). Amended effective June 18, 1990 (Supp. 90-2).