Section R12-15-1207 - Application Process
A. An applicant shall obtain written approval from the Director before constructing, reconstructing, repairing, enlarging, removing, altering, or breaching a dam. Application requirements differ according to the hazard potential of the dam.
1. To construct, reconstruct, repair, enlarge, or alter a high or significant hazard potential dam, the applicant shall comply with R12-15-1208.
2. To breach or remove a high or significant hazard potential dam, the applicant shall comply with R12-15-1209.
3. To construct, reconstruct, repair, enlarge, alter, breach, or remove a low hazard potential dam, the applicant shall comply with R12-15-1210.
4. To construct, reconstruct, repair, enlarge, alter, breach, or remove a very low hazard potential dam, the applicant shall comply with R12-15-1211.
B. An application shall not be filed with the Director under the following circumstances:
1. The dam is exempt under R12-15-1203;
2. A dam owner starts repairs to an existing dam that are necessary to safeguard human life or property and the Director is notified without delay;
3. The owner performs general maintenance or ordinary repairs as prescribed in R12-15-1217(A) or (B); or
4. Breach, removal, or reduction of a very low hazard dam as prescribed in R12-15-1211(C).
C. An applicant is not required to comply with a requirement in this Article if the Director finds that, considering the site characteristics and the proposed design, the requirement is unduly burdensome or expensive and is not necessary to protect human life or property. The Director shall consider the size, hazard potential classification, physical site conditions, and applicability of a requirement to a proposed dam. The Director shall state in writing the reason or reasons the applicant is not required to comply with a requirement.
D. An applicant shall schedule pre-application conferences with the Department to discuss the requirements of this Article and to resolve issues essential to the design of a dam while the design is in preliminary stages. The Director shall view the dam site during the pre-application process. The following are examples of issues for pre-application conferences: the hazard potential classification, the approximate inflow design flood, the basic design concepts, and any requirements that may be found by the Director to be unduly burdensome or expensive and not necessary to protect human life or safety. In addition, the applicant may submit preliminary design calculations to the Department for review and comment. The Department shall comment as soon as practicable, depending on the size of the submittal and the current workload.
E. The Department shall review applications as follows:
1. Applications will be received by appointment. During this meeting the Department shall make a brief review of the application to determine that the application contains each of the items required by R12-15-1208, R12-15-1209, R12-15-1210, or R12-15-1211.
2. Following receipt of an application submitted under R12-15-1208, R12-15-1209, R12-15-1210, or R12-15-1211, the Director shall complete an administrative review as prescribed in R12-15-401(1) and notify the applicant in writing whether the application is administratively complete. If the application is not administratively complete, the notification shall include a list of additional information that is required to complete the application.
3. After finding the application submitted under R12-15-1208, R12-15-1209, R12-15-1210, or R12-15-1211 administratively complete, the Director shall complete a substantive review as prescribed in R12-15-401(3) and notify the applicant in writing of the Director's approval or disapproval. If during this review period, the Director determines that there are defects in the application that would impact human life and property, a written notice of the defects shall be sent to the applicant.
4. An applicant may request in writing that the Director expedite the review of an application by employing an expert consultant on a contract basis under A.R.S. § 45-104(D). The Director shall establish on-call contracts with expert consultants to facilitate the process of expediting review. The Director may retain a consultant to review all or a portion of the application as necessary to expedite the process in response to an owner's request or to comply with time-frame rules. Before conducting the review, the consultant shall provide the Director and the applicant with a proposed time schedule and cost estimate. If the applicant agrees to the consultant's proposal for an expedited review of an application and the Director employs the consultant, the applicant shall pay to the Department the cost of the consultant's services in addition to the application fees. The Director retains the authority to review and approve, disapprove, or modify the findings and recommendations of the consultant.
5. The Director shall not approve an application in less than 10 days from the date of receipt.
6. If the Director disapproves the application, the Director shall provide the applicant with a statement of the Director's objections.
7. If the Director approves an application, the applicant shall submit in triplicate revised drawings and specifications that incorporate any required changes.
a. The Director shall return to the applicant 1 set of final construction drawings and specifications with the Department's approval stamp to be retained onsite during construction;
b. The Director shall retain for permanent state record 1 set of final construction drawings and specifications with the Department's approval stamp; and
c. The Director shall retain for use by the Department during construction the 3rd set of final construction drawings and specifications with the Department's approval stamp.
8. The Director shall impose conditions and limitations that the Director deems necessary to safeguard human life and property. Examples of the conditions of approval include but are not limited to:
a. The applicant shall not cover the foundation or abutment with the material of the dam until the Department has been given notice and a reasonable time to inspect and approve them.
b. The applicant shall start construction within 1 year from the date of approval.
c. The applicant shall maintain a safe storage level for an existing dam being reconstructed, repaired, enlarged, altered, or breached.
F. An approval to construct a new dam or repair, enlarge, alter, breach, or remove an existing dam is valid for 1 year.
1. If construction does not begin within 1 year, the approval is void.
2. Upon written request and good cause shown by the owner, the time for commencing construction may be extended. An applicant shall not start construction before the Director reviews the application for changes and grants approval.

Ariz. Admin. Code § R12-15-1207