Current through Register Vol. 30, No. 50, December 13, 2024
Section R11-2-603 - RoadsA. Reclamation of a road that is not included in the approved reclamation plan as part of the approved post-mining land use shall begin once the road is no longer needed for operations, reclamation, or monitoring.B. The following reclamation measures shall be conducted, as necessary, to achieve the post-mining land use included in the approved reclamation plan: 1. Vehicular traffic shall be controlled on the reclamation area to achieve the reclamation objectives;2. Surface drainage patterns shall be restored to pre-mining conditions or new patterns shall be established;3. All bridges and culverts shall be removed or stabilized in place;4. Bridges and culverts left in place shall be protected from erosion with rock, concrete, or riprap; and5. Roadbeds shall be ripped, plowed, and scarified and revegetated, as necessary, to achieve the post-mining land use.Ariz. Admin. Code § R11-2-603
Adopted effective January 6, 1997 (Supp. 97-1).