Section 3 AAC 107.360 - Conditions for receiving a utility improvements grant

A recipient of a grant under 3 AAC 107.300 - 3 AAC 107.430 may not use the proceeds of the grant to pay for costs of a project that were incurred before the applicant entered into a grant agreement under 3 AAC 107.350(a) unless the executive director of the authority approves payment of the costs.

3 AAC 107.360

Eff. 6/29/94, Register 131; am 11/25/94, Register 132

Authority:AS 42.45.100

AS 42.45.180

AS 44.83.080