An APDES permit must include a condition requiring a notification level that exceeds the notification level of 18 AAC 83.610(b) (1)(A) - (C), if the permittee in a petition or the department on its own initiative, seeks a new notification level. A new notification level imposed under this section may not exceed the level that can be achieved by the technology-based treatment requirements appropriate to the permittee under 40 C.F.R. 125.3(c), adopted by reference in 18 AAC 83.010.
18 AAC 83.445
Authority:AS 44.46.020
AS 46.03.010
AS 46.03.020
AS 46.03.050
AS 46.03.100
AS 46.03.110