Section 17 AAC 05.185 - STIP protests

An interested person aggrieved with the evaluation of projects under 17 AAC 05.180 may, within 15 days after the release of a notice of adoption under 17 AAC 05.180, file objections with the commissioner. The commissioner may issue a decision on the objections. If the commissioner does not issue a decision on any timely filed objections within 45 days after their receipt, the objections will be considered denied and the project will be considered in the next evaluation cycle under 17 AAC 05.175. The commissioner's action sustaining or denying an objection is the final agency action on the issue raised. Absent a court order, a pending appeal does not stay the execution of the STIP.