11 Alaska Admin. Code § 25.020

Current through October 17, 2024
Section 11 AAC 25.020 - Qualified person
(a) To qualify under AS 43.90.300 for a royalty inducement under AS 43.90.310 for qualified gas, a lessee or other person must
(1) for firm transportation capacity on the Alaska mainline,
(A) enter into a pre-subscription agreement with the licensee before the commencement of the first binding open season of the project;
(B) submit a bid before the close of the first binding open season of the project; however, the person may submit a bid after the close of the first binding open season, but no later than 180 days after the close of the first binding open season, if
(i) the licensee accepts the bid under 18 C.F.R. 157.34(d)(2); and
(ii) the lessee or other person makes, to the satisfaction of the commissioners, a good-faith showing of the circumstances that prevented the lessee or other person from submitting a timely bid, and the commissioners, on the basis of that showing, approve the tender of the bid; or
(C) be the holder of an inducement voucher issued to a person that qualifies under (A) or (B) of this paragraph;
(2) execute, no later than 180 days after the close of the first binding open season of the project, a precedent agreement for firm transportation capacity on the Alaska mainline arising out of an action taken to qualify under (1) of this subsection, or must be the holder of an inducement voucher issued by the commissioners to a person that executed a precedent agreement as required under this paragraph;
(3) obtain rights under a transportation services agreement
(A) as a party that executes, no later than five years after the close of the first binding open season of the project or two years after the effective date of the certificate of public convenience and necessity issued for the Alaska mainline, whichever date is later, a transportation services agreement arising out of an action taken to qualify under (1) and (2) of this subsection for firm transportation capacity on the Alaska mainline; or
(B) as the holder of an inducement voucher issued to a person qualified under (A) of this paragraph;
(4) file with the commissioners or be the holder of an inducement voucher obtained from a person that filed with the commissioners a complete copy of each of the following no later than 30 days after execution, or, under (E) of this paragraph, no later than 30 days after receipt of a request:
(A) the bid, precedent agreement, and transportation services agreement required to qualify under (1) - (3) of this subsection;
(B) an amendment to or termination of the bid, precedent agreement, or transportation services agreement required to qualify under (1) - (3) of this subsection;
(C) a bid, precedent agreement, or transportation services agreement, if any, arising out of a first binding open season for the Canada mainline;
(D) an amendment to or termination of the bid, precedent agreement, or transportation services agreement filed under (C) of this paragraph;
(E) other documents and information requested by the commissioners to determine qualification for resource inducements under AS 43.90 and this chapter; and
(5) submit, on a form provided by the commissioners, no later than 90 days after the issuance of a certificate of public convenience and necessity for the Alaska mainline, the agreement regarding rolling in expansion costs required by AS 43.90.310(c) or 43.90.330(d), as applicable.
(b) A person eligible for an inducement under AS 43.90.330 must execute the agreement set out in (a)(5) of this section no later than 90 days after issuance of a certificate of public convenience and necessity for the Alaska mainline, unless the person is eligible by reason of an agreement to transfer the inducement voucher, in which case the person must execute the agreement set out in (a)(5) of this section no later than 90 days after issuance of a certificate of public convenience and necessity for the Alaska mainline or the time of filing an application for transfer of the inducement voucher, whichever is later.
(c) The commissioners may extend the deadline set out in (a)(2) of this section if they determine that an extension is in the best interest of the state. However, the commissioners will not extend the deadline later than December 5, 2011.
(d) A person that satisfies the requirements of (a) and (b) of this section and that claims a resource inducement under AS 43.90.310 and this chapter may file an application with the commissioners for a determination that the requirements of (a) and (b) of this section have been met. Upon receipt of the application, the commissioners will make a joint determination whether the applicant meets the requirements for qualification set out in (a) and (b) of this section. A person is not qualified for a resource inducement before application to the commissioners and approval by the commissioners under this section.

11 AAC 25.020

Eff. 5/29/2010, Register 194

Authority:AS 38.05.020

AS 38.05.180

AS 43.90.300

AS 43.90.310

AS 43.90.330

AS 43.90.410