1 The application shall include a surface water monitoring plan based upon the PHC determination required under paragraph (1)(f) of this section and the analysis of all baseline hydrologic, geologic, and other information in the permit application. The plan shall provide for the monitoring of parameters that relate to the suitability of the surface water for current and approved postmined land uses and to the objectives for protection of the hydrologic balance as set forth in paragraph (1)(h) of this section as well as the effluent limitations found at 40 C. F.R. Part 434.
Author: Randall C. Johnson
Ala. Admin. Code r. 880-X-8E-.06
Statutory Authority:Code of Ala. 1975, §§ 9-16-71, 73, 74, 75, 80, 81, 82, 83, 84, 85, 86, 88, 90, 96.