Ala. Admin. Code r. 535-X-11-.08

Current through Register Vol. 43, No. 1, October 31, 2024
Section 535-X-11-.08 - Plumbing Plan And Drawing Requirements

The plumbing plans submitted pursuant to Rule 535-X-11-.07 of this chapter must:

(a) Provide plan and riser diagram of the plumbing layout showing size of piping, fittings, traps and vents, cleanouts and valves, etc., for gas, water, drainage, waste, and vent systems.
(b) Indicate plumbing materials to be used and approvals, as well as for fired appliances and equipment. Show make, model, rating/capacity.
(c) Indicate make and model of safety controls and their location, such as for water heaters, etc.
(d) Indicate how piping is to be supported and intervals of support.
(e) Indicate how piping, valves, and risers are to be supported such as by backing, as necessary.
(f) Show location of flues and vents above roofs and required clearances, such as from air intakes, and other vents and flues, etc.
(g) Indicate method of testing.

Author: Harold A. Hendrix

Ala. Admin. Code r. 535-X-11-.08

Filed February 6, 1990.

Statutory Authority:Code of Ala. 1975, §§ 24-4A-3, 24-6-4.