An operator completing a new well or recompleting an old well shall first obtain approval to produce pursuant to Rule 400-3-5-.03, and during production, test the well to determine its capacity to produce. The test shall be for a minimum of twenty-four (24) hours' duration. The results thereof shall be verbally reported to the Supervisor immediately and filed with the Board on Form OGB-9, First Production or Retest Report, within fifteen (15) days after such test is completed. When more than one test is made, the reverse side of Form OGB-9 may be used to give complete test data. The test shown on the front side shall be considered the official test results for such well.