Ala. Admin. Code r. 355-13-1-.03

Current through Register Vol. 43, No. 1, October 31, 2024
Section 355-13-1-.03 - Pre-Bid Review And Approval Required

Submissions of plans and specifications to the Technical Staff shall be made, and final approval obtained, prior to the receipt of bids to insure that the Technical Staff's comments are incorporated into the bid documents.

Ala. Admin. Code r. 355-13-1-.03

Repealed and Replaced: Filed August 29, 1997; effective October 3, 1997.

Author: Stedmann B. McCollough, Director

Statutory Authority:Code of Ala. 1975, § 41-9-141