The recipient shall immediately notify the Department in writing of events or proposed changes that may require a modification to the assistance agreement, including:
(a) Changes in plans and specifications for the project;(b) Changes to the scope or objectives of the project;(c) Significant, changed conditions at the project site;(d) Significant changes to the construction schedule; and(e) Changes that may substantially change the total cost of the project.Ala. Admin. Code r. 335-11-1-.13
New Rule: Filed August 31, 2010; effective October 4, 2010.Amended by Alabama Administrative Monthly Volume XXXVIII, Issue No. 05, February 28, 2020, eff. 4/13/2020.Authors: Aubrey H. White III, Kris Berry
Statutory Authority: Code of Ala. 1975, §§ 22-34-1, 22-34-2, 22-34-3.