Ala. Admin. Code r. 170-X-8-.05

Current through Register Vol. 43, No. 1, October 31, 2024
Section 170-X-8-.05 - Final Cost Of The Work

The final cost of the work for the permit fee shall be adjusted for change orders and for sales tax credit received by the Owner. The final cost of the work for plan review fees shall be adjusted to include the lowest bid on additive unawarded alternates. The final adjustment along with a copy of the contractor's final pay request shall be submitted to the Building Commission with the Certificate of Substantial Completion.

Ala. Admin. Code r. 170-X-8-.05

Amended by Alabama Administrative Monthly Volume XXXII, Issue No. 11, August 29, 2014, eff. 9/11/2014.

Author: Katherine Lynn

Statutory Authority:Code of Ala. 1975, § 41-9-141(a)(8).