Southern California Edison Company; Notice of Waiver Period for Water Quality Certification Application

Download PDF
Federal RegisterOct 23, 2024
89 Fed. Reg. 84571 (Oct. 23, 2024)
Document Headings

Document headings vary by document type but may contain the following:

  • the agency or agencies that issued and signed a document
  • the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to
  • the agency docket number / agency internal file number
  • the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions
  • See the Document Drafting Handbook for more details.

    Department of Energy Federal Energy Regulatory Commission
  • [Project No. 382-108]
  • On September 17, 2024, Southern California Edison Company submitted to the Federal Energy Regulatory Commission (Commission) a copy of its application for a Clean Water Act section 401(a)(1) water quality certification filed with the California State Water Resources Control Board, in conjunction with the above captioned project. Pursuant to Section 5.23(b) of the Commission's regulations, we hereby notify the California State Water Resources Control Board of the following:

    Date of Receipt of the Certification Request: September 17, 2024.

    Reasonable Period of Time to Act on the Certification Request: One year (September 17, 2025).

    If the California State Water Resources Control Board fails or refuses to act on the water quality certification request on or before the above date, then the agency certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1).

    Dated: October 17, 2024.

    Debbie-Anne A. Reese,

    Secretary.

    [FR Doc. 2024-24521 Filed 10-22-24; 8:45 am]

    BILLING CODE 6717-01-P