On June 29, 2024, the Department of Justice lodged with the United States District Court for the Western District of Michigan a proposed Eighth Modification of Consent Decree (“Eighth Modification”) in the lawsuit entitled United States v. Enbridge Energy, Limited Partnership, et al., Civil Action No. 1:16-cv-914.
On May 23, 2017, the United States District Court for the Western District of Michigan approved and entered a Consent Decree that resolved specified claims asserted by the United States against Enbridge Energy, Limited Partnership and eight affiliated entities (“Enbridge”) under the Clean Water Act and Oil Pollution Act arising from two separate 2010 oil spills resulting from failures of Enbridge oil transmission pipelines near Marshall, Michigan and Romeoville, Illinois. The complaint filed by the United States alleged that Enbridge's pipelines had unlawfully discharged oil into waters of the United States and sought civil penalties, recovery of removal costs, and injunctive relief. The Consent Decree established various requirements applicable to a network of 14 pipelines that comprise Enbridge's Lakehead System—including dig selection criteria governing excavation, repair or mitigation, and imposition of interim pressure restrictions for various features, such a cracks, that are detected through In-Line Inspections (“ILI”) of such pipelines. The proposed Modification would revise provisions of the Consent Decree relating to the investigation and repair of “circumferential cracks”— i.e., cracks that are predominantly oriented around the circumference of the pipeline as opposed to cracks oriented along the length (or central axis) of the pipeline.
First, the proposed Eighth Modification would require Enbridge to investigate circumferential crack features in four pipelines. In three pipelines (Lines 2, 62 and a portion of Line 1), Enbridge will deploy ILI tools that are specifically designed to identify and measure circumferential crack features. In a fourth pipeline (Line 4), Enbridge will undertake a newly-created program to excavate and examine a minimum of ten pipe joints that are likely to contain the most severe circumferential crack features. Based upon the results of this investigation, Enbridge will attempt to pass an agreed-upon statistical test for determining whether unexcavated portions of the pipeline are likely to contain any Circumferential Cracks that require repair.
Second, the proposed Eighth Modification would revise the methods used by Enbridge for assessing whether a circumferential crack must be excavated and repaired. The new methods are tailored to address the unique threats posed by circumferential crack features, taking into account all stresses and loading conditions that may cause a circumferential crack to grow and ultimately fail. The proposed Eighth Modification would require Enbridge to apply these new assessment methods not only to circumferential crack features in Lines 1, 2, 4, and 62 that Enbridge would be required to investigate under the proposed Eighth Modification, but also those circumferential crack features in Lines 5, 6A, and 10 that Enbridge previously discovered through past ILIs but that Enbridge has not yet excavated and repaired.
Third, the proposed Eighth Modification adjusts certain requirements relating to the repair and mitigation of Circumferential Crack features. The proposed Eighth Modification allows more time for the excavation and repair of Circumferential Cracks than is generally afforded for the excavation and repair of axially-aligned cracks ( i.e., a crack oriented in parallel to the flow of oil through the pipeline). Further, Enbridge will not be required, in all instances, to limit operating pressure in a pipeline until such repairs are completed. Rather, Enbridge will be required to establish an interim pressure restriction only if a Circumferential Crack is growing at a rate that poses a threat to the integrity of the pipeline.
Fouth, the proposed Eighth Modification would eliminate two requirements in the Consent Decree relating to Circumferential Cracks. In contrast to axially-aligned cracks, circumferential crack features that do not require excavation and repair would not be evaluated to determine their remaining life ( i.e., the estimated time remaining before a feature may fail either by leaking or rupturing). In addition, the proposed Eighth Modification would not impose any requirements on Enbridge with respect to the future deployment of ILI tools to re-inspect circumferential crack features in Lines 1, 2, 4, 5, 6A, 10, and 62.
Finally, the proposed Eighth Modification would revise the Termination Section of the Consent Decree, enabling Enbridge to seek early termination of certain requirements relating to circumferential crack features. The proposed Eighth Modification would require Enbridge to incorporate the circumferential crack remedial program into its operating manual, which is enforceable by the Pipeline and Hazardous Materials Safety Administration (“PHMSA”). Once the manual is revised, Enbridge may request “Phase 1” Final Termination, which, upon approval by EPA, will terminate all aspects of the Consent Decree other than two discrete programs relating to circumferential cracks. Phase 2 Final Termination will occur once the United States files notice with the Court confirming that Enbridge has fully implemented these two remaining programs.
The publication of this notice opens a period for public comment on the proposed Eighth Modification of Consent Decree. Comments should be addressed to the Assistant Attorney General, Environment and Natural Resources Division, and should refer to United States v. Enbridge Energy, Limited Partnership, et al., D.J. Ref. No. 90-5-1-1-10099. All comments must be submitted no later than thirty (30) days after the publication date of this notice. Comments may be submitted either by email or by mail:
To submit comments: | Send them to: |
---|---|
By email | pubcomment-ees.enrd@usdoj.gov. |
By mail | Assistant Attorney General, U.S. DOJ—ENRD, P.O. Box 7611, Washington, DC 20044-7611. |
During the public comment period, the proposed Eighth Modification may be examined and downloaded at this Justice Department website: https://www.justice.gov/enrd/consent-decrees. If you require assistance accessing the proposed Eighth Modification, you may request assistance by email or by mail to the address provided above for submitting comments.
Laura A. Thoms,
Assistant Section Chief, Environmental Enforcement Section, Environment and Natural Resources Division.
[FR Doc. 2024-14965 Filed 7-8-24; 8:45 am]
BILLING CODE 4410-15-P