Iroquois Gas Transmission System, L.P.; Notice of Request for Extension of Time

Download PDF
Federal RegisterNov 7, 2024
89 Fed. Reg. 88266 (Nov. 7, 2024)
Document Headings

Document headings vary by document type but may contain the following:

  • the agency or agencies that issued and signed a document
  • the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to
  • the agency docket number / agency internal file number
  • the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions
  • See the Document Drafting Handbook for more details.

    Department of Energy Federal Energy Regulatory Commission
  • [Docket No. CP20-48-001]
  • Take notice that on October 28, 2024, Iroquois Gas Transmission System, L.P. (Iroquois) requested that the Commission grant an extension of time, until March 25, 2027, to construct and place into service its Enhancement by Compression Project (Project) located in Greene and Dutchess Counties, New York and Fairfield and New Haven Counties, Connecticut as authorized in the Order Issuing Certificate (Order). The Order required Iroquois to complete construction of the Project and make it available for service within three years of the date of the Order or by March 25, 2025.

    Iroquois Gas Transmission Sys., L.P., 178 FERC ¶ 61,200 (2022).

    Iroquois states that construction of the Project has been delayed due to pending state permit approvals, specifically air permits from the New York State Department of Environmental Conservation and the Connecticut Department of Energy and Environmental Protection. Iroquois asserts that it has been working in good faith with these agencies and expects to receive approvals for the Project in the near future. Thus, Iroquois is requesting an extension of time until March 25, 2027, to complete construction of the Project and make it available for service.

    This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on Iroquois's request for an extension of time may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (NGA) (18 CFR 157.10).

    As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for NGA facilities when such requests are contested before order issuance. For those extension requests that are contested, the Commission will aim to issue an order acting on the request within 45 days. The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension. The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission's environmental analysis for the certificate complied with the National Environmental Policy Act (NEPA). At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance. The Director of the Office of Energy Projects, or his or her designee, will act on all of those extension requests that are uncontested.

    Contested proceedings are those where an intervenor disputes any material issue of the filing. 18 CFR 385.2201(c)(1).

    Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020).

    Id. at P 40.

    Similarly, the Commission will not re-litigate the issuance of an NGA section 3 authorization, including whether a proposed project is not inconsistent with the public interest and whether the Commission's environmental analysis for the permit order complied with NEPA.

    Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020).

    In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( https://www.ferc.gov ). From the Commission's Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field.

    User assistance is available for eLibrary and the Commission's website during normal business hours from FERC Online Support at (202) 502-6652 (toll free at 1-866-208-3676) or email at ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502-8371, TTY (202) 502-8659. Email the Public Reference Room at public.referenceroom@ferc.gov.

    The Commission strongly encourages electronic filings of comments in lieu of paper using the “eFile” link at https://www.ferc.gov . In lieu of electronic filing, you may submit a paper copy which must reference the Project docket number.

    To file via USPS: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426

    To file via any other courier: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852

    The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202)502-6595 or OPP@ferc.gov.

    Comment Date: 5:00 p.m. Eastern Time on November 15, 2024.

    Dated: October 31, 2024.

    Carlos D. Clay,

    Acting Deputy Secretary.

    [FR Doc. 2024-25845 Filed 11-6-24; 8:45 am]