Green Mountain Power Corporation; Notice of Intent To Prepare an Environmental Assessment

Download PDF
Federal RegisterOct 15, 2024
89 Fed. Reg. 83006 (Oct. 15, 2024)
Document Headings

Document headings vary by document type but may contain the following:

  • the agency or agencies that issued and signed a document
  • the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to
  • the agency docket number / agency internal file number
  • the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions
  • See the Document Drafting Handbook for more details.

    Department of Energy Federal Energy Regulatory Commission
  • [Project No. 2490-031]
  • On August 30, 2022, the Green Mountain Power Corporation filed a minor relicense application for the 0.5-megawatt Taftsville Hydroelectric Project No. 2490 (project). The project is located on the Ottauquechee River in the Village of Taftsville, in Windsor County, Vermont. No Federal or Tribal lands occur within or adjacent to the project boundary.

    In accordance with the Commission's regulations, on June 12, 2024, Commission staff issued a notice that the project was ready for environmental analysis (REA Notice). Based on the information in the record, staff does not anticipate that licensing the project would constitute a major Federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to relicense the project.

    In accordance with the Council on Environmental Quality's regulations, the unique identification number for documents relating to this environmental review is EAXX-019-20-000-1728292340. 40 CFR 1501.5(c)(4) (2024).

    The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission's final licensing decision.

    The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members, and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502-6595 or OPP@ferc.gov.

    The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate.

    Milestone Target date
    Commission issues EA August 25, 2025.