Colorado Interstate Gas Company; Notice of Intent To Prepare An Environmental Assessment for the Proposed Spruce Hill Air Blending Project and Request for Comments on Environmental Issues

Download PDF
Federal RegisterSep 29, 2010
75 Fed. Reg. 60097 (Sep. 29, 2010)
September 21, 2010.

The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Spruce Hill Air Blending Project involving construction and operation of facilities by Colorado Interstate Gas Company (CIG) in Douglas County, Colorado. This EA will be used by the Commission in its decision-making process to determine whether the project is in the public convenience and necessity.

This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues need to be evaluated in the EA. Please note that the scoping period will close on October 21, 2010.

This notice is being sent to the Commission's current environmental mailing list for this project. State and local government representatives are asked to notify their constituents of this proposed project and encourage them to comment on their areas of concern.

If you are a landowner receiving this notice, you may be contacted by a pipeline company representative about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the project is approved by the Commission, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law.

A fact sheet prepared by the FERC entitled “An Interstate Natural Gas Facility On My Land? What Do I Need To Know?” was attached to the project notice CIG provided to landowners. This fact sheet addresses a number of typically-asked questions, including the use of eminent domain and how to participate in the Commission's proceedings. It is also available for viewing on the FERC Web site ( http://www.ferc.gov ).

Summary of the Proposed Project

CIG proposes to construct and operate a new air blending station in Douglas County, Colorado. The Spruce Hill Air Blending Project would increase CIG's firm natural gas transportation capacity to 50,000 dekatherms per day (Dth/day) to meet contractual agreements with Black Hills Utility Holdings, Inc. (Black Hill) as a result of Black Hill's anticipated demand growth. According to CIG, its project would reduce the input factor of the gas to a level that conforms to the gas quality specifications in CIG's Tariff for its existing Valley Line, to which the blended gas would be discharged.

The Spruce Hill Air Blending Project would consist of the following:

  • An air blending compressor station (the Spruce Hill Air Blending Station) containing a 215-, a 390-, and a 500-horsepower air compressor;
  • A back-pressure regulator;
  • Air blending controls and instrumentation;
  • A gas heater;
  • Auxiliary facilities and piping;
  • Modifications to the existing Spruce Hill Meter Station;
  • An interconnection at the air blending station between the existing Spruce Hill Meter Station and CIG's existing Line No. 212A; and
  • A powerline connection within CIG's 35-acre parcel.

The general location of the project facilities is shown in Appendix 1.

The appendices referenced in this notice are not being printed in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at http://www.ferc.gov using the link called “eLibrary” or from the Commission's Public Reference Room, 888 First Street, NE., Washington, DC 20426, or call (202) 502-8371. For instructions on connecting to eLibrary, refer to the last page of this notice.

Land Requirements for Construction

Construction of the proposed facilities would disturb about 5.5 acres of land for the air blending station and its auxiliary facilities. Following construction, about 3.3 acres would be maintained for permanent operation of the project's facilities; the remaining acreage would be restored and allowed to revert to former uses. All construction would occur within a 35-acre land parcel owned by CIG.

The EA Process

The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us to discover and address concerns the public may have about proposals. This process is referred to as “scoping”. The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. All comments received will be considered during the preparation of the EA.

“We”, “us”, and “our” refer to the environmental staff of the Commission's Office of Energy Projects.

In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings:

  • Geology and soils;
  • Land use;
  • Water resources, fisheries, and wetlands;
  • Cultural resources;
  • Vegetation and wildlife;
  • Air quality and noise;
  • Endangered and threatened species; and
  • Public safety.

We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas.

Our independent analysis of the issues will be presented in the EA. The EA will be placed in the public record and, depending on the comments received during the scoping process, may be published and distributed to the public. A comment period will be allotted if the EA is published for review. We will consider all comments on the EA before we make our recommendations to the Commission. To ensure your comments are considered, please carefully follow the instructions in the Public Participation section below.

With this notice, we are asking agencies with jurisdiction and/or special expertise with respect to environmental issues to formally cooperate with us in the preparation of the EA. These agencies may choose to participate once they have evaluated the proposal relative to their responsibilities. Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice.

Consultations Under Section 106 of the National Historic Preservation Act

In accordance with the Advisory Council on Historic Preservation's implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the Colorado State Historic Preservation Office, and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project's potential effects on historic properties. We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project is further developed. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106.

The Advisory Council on Historic Preservation's regulations are at Title 36, Code of Federal Regulations, Part 800. Historic properties are defined in those regulations as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register for Historic Places.

Public Participation

You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that they will be received in Washington, DC on or before October 21, 2010.

For your convenience, there are three methods which you can use to submit your comments to the Commission. In all instances please reference the project docket number (CP10-486-000) with your submission. The Commission encourages electronic filing of comments and has expert eFiling staff available to assist you at (202) 502-8258 or efiling@ferc.gov.

(1) You may file your comments electronically by using the eComment feature, which is located on the Commission's Web site at http://www.ferc.gov under the link to Documents and Filings. An eComment is an easy method for interested persons to submit brief, text-only comments on a project;

(2) You may file your comments electronically by using the eFiling feature, which is located on the Commission's Web site at http://www.ferc.gov under the link to Documents and Filings. With eFiling you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making. A comment on a particular project is considered a “Comment on a Filing”; or

(3) You may file a paper copy of your comments at the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Room 1A, Washington, DC 20426.

Environmental Mailing List

The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission's regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project.

If the EA is published for distribution, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (Appendix 2).

Becoming an Intervenor

In addition to involvement in the EA scoping process, you may want to become an “intervenor” which is an official party to the Commission's proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission's final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are included in the User's Guide under the “e-Filing” link on the Commission's Web site.

Additional Information

Additional information about the project is available from the Commission's Office of External Affairs, at (866) 208-FERC, or on the FERC Web site at http://www.ferc.gov using the “eLibrary” link. Click on the eLibrary link, click on “General Search” and enter the docket number, excluding the last three digits, in the Docket Number field (i.e., CP10-486). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings.

In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to http://www.ferc.gov/esubscribenow.htm.

Finally, public meetings or site visits will be posted on the Commission's calendar located at http://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

Kimberly D. Bose,

Secretary.

BILLING CODE 6717-01-P

[FR Doc. 2010-24233 Filed 9-28-10; 8:45 am]

BILLING CODE 6717-01-C