AGENCY:
Nuclear Regulatory Commission.
ACTION:
License renewal application; notice of docketing and opportunity to request a hearing and to petition for leave to intervene.
SUMMARY:
This is a notice of acceptance for docketing and notice of opportunity for hearing regarding the renewal of operating licenses for the Byron Nuclear Station (Byron), Units 1 and 2, and the Braidwood Nuclear Station (Braidwood), Units 1 and 2. The NRC is considering an application for the renewal of operating licenses NPF-37, NPF-66, NPF-72, and NPF-77, which authorize Exelon Generation Company, LLC (Exelon), to operate Byron, Units 1 and 2, at 3586.6 megawatts thermal each, and Braidwood, Units 1 and 2, at 3586.6 megawatts thermal each. Byron, Units 1 and 2, are located near Byron, IL; Braidwood, Units 1 and 2, are located near Braidwood, IL. The renewed licenses would authorize the applicant to operate both Byron and Braidwood for an additional 20 years beyond the period specified in each of the respective current licenses. The current operating licenses for Byron expire as follows: Unit 1 (NPF-37) on October 31, 2024, and Unit 2 (NPF-66) on November 6, 2026. The current operating licenses for Braidwood expire as follows: Unit 1 (NPF-72) on October 17, 2026, and Unit 2 (NPF-77) on December 18, 2027.
ADDRESSES:
Please refer to Docket ID NRC-2013-0126 when contacting the U.S. Nuclear Regulatory Commission (NRC) about the availability of information regarding this document. You may access information related to this document, which the NRC possesses and is publicly available, using any of the following methods:
- Federal rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2013-0126. Address questions about NRC dockets to Carol Gallagher; telephone: 301-287-3422; email: Carol.Gallagher@nrc.gov.
- NRC's Agencywide Documents Access and Management System (ADAMS): You may access publicly available documents online in the NRC Library at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select “ADAMS Public Documents” and then select “Begin Web-based ADAMS Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email to PDR.Resource@nrc.gov. The ADAMS accession number for each document referenced in this notice (if that document is availa ble in ADAMS) is provided the first time that a document is referenced.
- NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
John Daily, Senior Project Manager, Projects Branch 1, Division of License Renewal, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washing ton, DC 20555; telephone: 301-415-3873; email: John.Daily@nrc.gov.
SUPPLEMENTARY INFORMATION:
Exelon submitted the application dated May 29, 2013, pursuant to Part 54 of Title 10 of the Code of Federal Regulations (10 CFR Part 54), to renew operating licenses NPF-37, NPF-66, NPF-72, and NPF-77. A notice of receipt and availability of the license renewal application (LRA) was published in the Federal Register on June 13, 2013 (78 FR 35646).
The Commission's staff has determined that Exelon has submitted sufficient information in accordance with 10 CFR 54.19, 54.21, 54.22, 54.23, 51.45, and 51.53(c), to enable the staff to undertake a review of the application, and that the application is therefore acceptable for docketing. The current Docket numbers, 50-454, 50-455, 50-456, and 50-457, for operating license numbers NPF-37, NPF-66, NPF-72, and NPF-77, respectively, will be retained. The determination to accept the LRA for docketing does not constitute a determination that a renewed license should be issued, and does not preclude the NRC staff from requesting additional information as the review proceeds.
Before issuance of the requested renewed licenses, the NRC will have made the findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations. In accordance with 10 CFR 54.29, the NRC may issue a renewed license on the basis of its review if it finds that actions have been identified and have been or will be taken with respect to: (1) Managing the effects of aging during the period of extended operation on the functionality of structures and components that have been identified as requiring aging management review; and (2) time-limited aging analyses that have been identified as requiring review, such that there is reasonable assurance that the activities authorized by the renewed license will continue to be conducted in accordance with the current licensing basis (CLB) and that any changes made to the plant's CLB will comply with the Act and the Commission's regulations.
Additionally, in accordance with 10 CFR 51.95(c), the NRC will prepare an environmental impact statement for each site as supplements to the Commission's NUREG-1437, “Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants,” dated May 1996. In considering the LRA, the Commission must find that the applicable requirements of Subpart A of 10 CFR part 51 have been satisfied, and that matters raised under 10 CFR 2.335 have been addressed. Pursuant to 10 CFR 51.26, and as part of the environmental scoping process, the staff intends to hold public scoping meetings. Detailed information regarding the environmental scoping meetings will be the subject of a separate Federal Register notice.
Within 60 days after the date of publication of this Federal Register notice, any person whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written request for a hearing and a petition for leave to intervene with respect to the renewal of the licenses. Requests for a hearing or petitions for leave to intervene must be filed in accordance with the Commission's “Agency Rules of Practice and Procedure” in 10 CFR part 2. Interested persons should consult a current copy of 10 CFR 2.309, which is available at the NRC's Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland 20852, and is accessible from the NRC Library on the Internet at http://www.nrc.gov/reading-rm/adams.html.http://www.nrc.gov/readingrm/adams.html Persons who do not have access to the Internet or who encounter problems in accessing the documents located in ADAMS should contact the NRC's PDR reference staff by telephone at 1-800-397-4209, or 301-415-4737, or by email at PDR.Resource@nrc.gov. If a request for a hearing/petition for leave to intervene is filed within the 60-day period, the Commission or a presiding officer designated by the Commission or by the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel will rule on the request and/or petition; and the Secretary of the Commission (Secretary) or the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel will issue a notice of a hearing or an appropriate order. In the event that no request for a hearing or petition for leave to intervene is filed within the 60-day period, the NRC may, upon completion of its evaluations and upon making the findings required under 10 CFR parts 51 and 54, renew the license without further notice.
As required by 10 CFR 2.309, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding, taking into consideration the limited scope of matters that may be considered pursuant to 10 CFR parts 51 and 54. Pursuant to 10 CFR 2.309(d), the petition must provide the name, address, and telephone number of the petitioner; and specifically explain the reasons why intervention should be permitted with particular reference to the following factors for the Byron and/or Braidwood sites: (1) The nature of the requestor's/petitioner's right under the Act to be made a party to the proceeding; (2) the nature and extent of the requestor's/petitioner's property, financial, or other interest in the proceeding; and (3) the possible effect of any decision or order which may be entered in the proceeding on the requestor's/petitioner's interest. The petition must also set forth the specific contentions which the petitioner/requestor seeks to have litigated at the proceeding.
In accordance with 10 CFR 2.309(f), each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the requestor/petitioner shall provide a brief explanation of the basis for each contention and a concise statement of the alleged facts or the expert opinion that supports the contention on which the requestor/petitioner intends to rely in proving the contention at the hearing. The requestor/petitioner must also provide references to those specific sources and documents of which the requestor/petitioner is aware and on which the requestor/petitioner intends to rely to establish those facts or expert opinion. The requestor/petitioner must provide sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. Contentions shall be limited to matters within the scope of the action under consideration. The contention must be one that, if proven, would entitle the requestor/petitioner to relief. A requestor/petitioner who fails to satisfy these requirements with respect to at least one contention will not be permitted to participate as a party.
Petitions filed after the deadline, amended petitions, and supplemental petitions will not be entertained absent a determination by the Commission, the Atomic Safety and Licensing Board Panel or a Presiding Officer that the filing demonstrates good cause by satisfying the following three factors in 10 CFR 2.309(c)(1): (i) The information upon which the filing is based was not previously available; (ii) The information upon which the filing is based is materially different from information previously available; and (iii) The filing has been submitted in a timely fashion based on the availability of the subsequent information.
A State, county, municipality, Federally-recognized Indian Tribe, or agencies thereof, may submit a petition to the Commission to participate as a party under 10 CFR 2.309(d)(2). The petition should state the nature and extent of the petitioner's interest in the proceeding. The petition should be submitted to the Commission by September 23, 2013. The petition must be filed in accordance with the filing instructions described above in this notice, and should meet the requirements for petitions for leave to intervene set forth in this section, except that State and Federally-recognized Indian tribes do not need to address the standing requirements in 10 CFR 2.309(d)(1) if the facility is located within its boundaries. The entities listed above could also seek to participate in a hearing as a nonparty pursuant to 10 CFR 2.315(c).
Any person who does not wish, or is not qualified, to become a party to this proceeding may request permission to make a limited appearance pursuant to the provisions of 10 CFR 2.315(a). A person making a limited appearance may make an oral or written statement of position on the issues, but may not otherwise participate in the proceeding. A limited appearance may be made at any session of the hearing or at any prehearing conference, subject to such limits and conditions as may be imposed by the Atomic Safety and Licensing Board. Persons desiring to make a limited appearance are requested to inform the Secretary of the Commission by September 23, 2013.
The Commission requests that each contention be given a separate numeric or alpha designation within one of the following groups: (1) Technical (primarily related to safety concerns); (2) environmental; or (3) miscellaneous.
As specified in 10 CFR 2.309, if two or more requestors/petitioners seek to co-sponsor a contention or propose substantially the same contention, the requestors/petitioners will be required to jointly designate a representative who shall have the authority to act for the requestors/petitioners with respect to that contention.
All documents filed in NRC adjudicatory proceedings, including a request for hearing, a petition for leave to intervene, any motion or other document filed in the proceeding prior to the submission of a request for hearing or petition to intervene, and documents filed by interested governmental entities participating under 10 CFR 2.315(c), must be filed in accordance with the NRC E-Filing rule (72 FR 49139, August 28, 2007). The E-Filing process requires participants to submit and serve all adjudicatory documents over the internet, or in some cases to mail copies on electronic storage media. Participants may not submit paper copies of their filings unless they seek an exemption in accordance with the procedures described below.
To comply with the procedural requirements of E-Filing, at least ten 10 days prior to the filing deadline, the participant should contact the Office of the Secretary by email at hearing.docket@nrc.gov, or by telephone at 301-415-1677, to request (1) a digital identification (ID) certificate, which allows the participant (or its counsel or representative) to digitally sign documents and access the E-Submittal server for any proceeding in which it is participating; and (2) advise the Secretary that the participant will be submitting a request or petition for hearing (even in instances in which the participant, or its counsel or representative, already holds an NRC-issued digital ID certificate). Based upon this information, the Secretary will establish an electronic docket for the hearing in this proceeding if the Secretary has not already established an electronic docket.
Information about applying for a digital ID certificate is available on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals/apply-certificates.html. System requirements for accessing the E-Submittal server are detailed in the NRC's “Guidance for Electronic Submission,” which is available on the agency's public Web site at http://www.nrc.gov/site-help/e-submittals.html. Participants may attempt to use other software not listed on the Web site, but should note that the NRC's E-Filing system does not support unlisted software, and the NRC Meta System Help Desk will not be able to offer assistance in using unlisted software.
If a participant is electronically submitting a document to the NRC in accordance with the E-Filing rule, the participant must file the document using the NRC's online, Web-based submission form. In order to serve documents through the Electronic Information Exchange System, users will be required to install a Web browser plug-in from the NRC's Web site. Further information on the Web-based submission form, including the installation of the Web browser plug-in, is available on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals.html.
Once a participant has obtained a digital ID certificate and a docket has been created, the participant can then submit a request for hearing or petition for leave to intervene. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the documents are submitted through the NRC's E-Filing system. To be timely, an electronic filing must be submitted to the E-Filing system no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an email notice confirming receipt of the document. The E-Filing system also distributes an email notice that provides access to the document to the NRC's Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the documents on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before a hearing request/petition to intervene is filed so that they can obtain access to the document via the E-Filing system.
A person filing electronically using the NRC's adjudicatory E-Filing system may seek assistance by contacting the NRC Meta System Help Desk through the “Contact Us” link located on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals.html,, by email to MSHD.Resource@nrc.gov, or by a toll-free call at 866-672-7640. The NRC Meta System Help Desk is available between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday, excluding government holidays.
Participants who believe that they have a good cause for not submitting documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by: (1) First class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by first-class mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service. A presiding officer, having granted an exemption request from using E-Filing, may require a participant or party to use E-Filing if the presiding officer subsequently determines that the reason for granting the exemption from use of E-Filing no longer exists.
Documents submitted in adjudicatory proceedings will appear in the NRC's electronic hearing docket which is available to the public at http://ehd1.nrc.gov/ehd/,, unless excluded pursuant to an order of the Commission, or the presiding officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home phone numbers in their filings, unless an NRC regulation or other law requires submission of such information. However, a request to intervene will require including information on local residence in order to demonstrate a proximity assertion of interest in the proceeding. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants are requested not to include copyrighted materials in their submission.
Detailed information about the license renewal process can be found under the Nuclear Reactors icon at http://www.nrc.gov/reactors/operating/licensing/renewal.html on the NRC's Web site. Copies of the application to renew the operating licenses for Byron and Braidwood are available for public inspection at the Commission's Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland 20852-2738, and at http://www.nrc.gov/reactors/operating/licensing/renewal/applications.html,, the NRC's Web site while the application is under review. The application may be accessed in ADAMS through the NRC Library on the Internet at http://www.nrc.gov/reading-rm/adams.html under ADAMS Accession No. ML131550528. As stated above, persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS may contact the NRC PDR reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by email to pdr.resources@nrc.gov.
The NRC staff has verified that a copy of the license renewal application is also available to local residents near Byron at the Byron Public Library, 100 S. Washington Street, Byron, IL 61010, and near Braidwood at the Fossil Ridge (Braidwood) Public Library, 386 W. Kennedy Road, Braidwood, IL 60408.
Dated at Rockville, Maryland, this 18th day of July, 2013.
For the Nuclear Regulatory Commission.
David L. Pelton,
Acting Deputy Director, Division of License Renewal, Office of Nuclear Reactor Regulation.
[FR Doc. 2013-17809 Filed 7-23-13; 8:45 am]
BILLING CODE 7590-01-P