Ampersand Christine Falls Hydro, LLC; Notice of Revised Procedural Schedule for Environmental Assessment for the Proposed Project Relicense

Download PDF
Federal RegisterSep 11, 2024
89 Fed. Reg. 73647 (Sep. 11, 2024)
Document Headings

Document headings vary by document type but may contain the following:

  • the agency or agencies that issued and signed a document
  • the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to
  • the agency docket number / agency internal file number
  • the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions
  • See the Document Drafting Handbook for more details.

    Department of Energy Federal Energy Regulatory Commission
  • [Project No. 4639-033]
  • On September 29, 2021, Ampersand Christine Falls Hydro, LLC filed an application for a subsequent minor license for the 850-kilowatt Christine Falls Hydroelectric Project (Christine Falls Project or project; FERC No. 4639). On November 9, 2023, Commission staff issued a notice of intent to prepare an environmental assessment (EA) to evaluate the effects of relicensing the project. The notice of intent included an anticipated schedule for issuing the EA.

    By this notice, Commission staff is updating the procedural schedule for completing the EA. The revised schedule is shown below. Further revisions to the schedule may be made as appropriate.

    Milestone Target date
    Issue EA October 2024.