AGENCY:
Office of the Secretary, USDA.
ACTION:
Proposed rule.
SUMMARY:
The United States Department of Agriculture (USDA) is proposing to make amendments to the Agriculture Acquisition Regulation (AGAR) to align the AGAR with changes to acquisition law, regulations, and internal USDA policies since the AGAR's last major revision in 1996.
DATES:
Interested parties should submit written comments on or before August 26, 2024, to be considered in the formation of the final rule.
ADDRESSES:
Submit comments in response to the proposed rule to the Federal eRulemaking portal at https://www.regulations.gov by searching for “AGAR.” Follow the instructions provided on the “Comment Now” screen. If your comment cannot be submitted using Regulations.gov, email the point of contact in the FOR FURTHER INFORMATION CONTACT section of this document for alternate instructions.
FOR FURTHER INFORMATION CONTACT:
Crandall Watson, Procurement Policy Division, Office of Contracting and Procurement, USDA, Telephone: (202) 617-7067; Email: Procurement.Policy@usda.gov.
SUPPLEMENTARY INFORMATION:
This rulemaking is necessary to update the AGAR located in 48 CFR parts 401 through 499.
I. Background
The AGAR implements the Federal Acquisition Regulation (FAR) (48 CFR ch. 1) where further implementation is needed, and supplements the FAR when coverage is needed for subject matter not covered by the FAR. USDA identified parts of the AGAR which required updating or streamlining based on updates to acquisition law, regulations, and internal USDA policies. USDA's review indicated that almost all parts of the AGAR required revision. Accordingly, USDA has reviewed and revised substantially all parts of the AGAR.
What we're proposing in terms of changes?
USDA is proposing to make administrative amendments to the AGAR to align the AGAR with changes to acquisition law, regulations, and internal USDA policies since the AGAR's last major revision. There are many aspects that are no longer relevant and are consequently deleted or revised as necessary. Also, there are various parts of the FAR that have been updated since the AGAR's last revision, many of which compel USDA to establish agency-specific guidance on how to comply with the newer FAR requirements.
II. Procedural Requirements
Executive Orders 12866 and 13563
Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This proposed rule is an internal rule of agency procedure and therefore is not a significant regulatory action under Executive Order 12866.
Regulatory Flexibility Act
The Regulatory Flexibility Act (RFA), as amended by the Small Business Regulatory Enforcement Fairness Act of 1996 (SBREFA), 5 U.S.C. 601 et seq., generally requires an agency to prepare a regulatory flexibility analysis of any rule subject to the notice and comment rulemaking requirements under the Administrative Procedure Act (5 U.S.C. 553) or any other statute. Under section 605(b) of the RFA, however, if the head of an agency certifies that a rule will not have a significant impact on a substantial number of small entities, the statute does not require the agency to prepare a regulatory flexibility analysis.
The proposed changes would update the AGAR to bring it up to date and to make sure correspondence with the FAR is maintained. The proposed rule would amend the AGAR to correct and update internal references to the FAR; to remove sections supplementing material that has been removed from the FAR; and to update designations of USDA. Therefore, pursuant to section 605(b), USDA certifies that this proposed rule, if promulgated, will not have a significant impact on a substantial number of small entities.
Paperwork Reduction Act
The proposed rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).
List of Subjects
48 CFR Part 401
- Government procurement
- Reporting and recordkeeping requirements
48 CFR Parts 402, 405 Through 406, 411 Through 416, 434 Through 437, and 447 Through 470
- Government procurement
48 CFR Part 403
- Antitrust
- Conflict of interest
- Government procurement
48 CFR Part 404
- Classified information
- Government procurement
48 CFR Part 408
- Government procurement
- Printing
48 CFR Part 419
- Government procurement
- Small businesses
48 CFR Part 422
- Equal employment opportunity
- Government procurement
- Individuals with disabilities
- Labor
48 CFR Part 423
- Air pollution control
- Government procurement
- Occupational safety and health
- Water pollution control
48 CFR Part 425
- Foreign currencies
- Foreign trade
- Government procurement
48 CFR Part 428
- Government procurement
- Insurance
- Surety bonds
48 CFR Parts 430 Through 432
- Accounting
- Government procurement
48 CFR Part 433
- Administrative practice and procedure
- Government procurement
48 CFR Part 445
- Government procurement
- Government property
Accordingly, for the reasons set out in the preamble, and under the authority of 5 U.S.C. 301 and 40 U.S.C. 486(c), USDA proposes to revise and republish 48 CFR chapter 4 to read as follows:
CHAPTER 4—DEPARTMENT OF AGRICULTURE
- SUBCHAPTER A—GENERAL
PART 400—[RESERVED]
PART 401—AGRICULTURE ACQUISITION REGULATION SYSTEM
PART 402—DEFINITIONS OF WORDS AND TERMS
PART 403—IMPROPER BUSINESS PRACTICES AND PERSONAL CONFLICTS
PART 404—ADMINISTRATIVE AND INFORMATION MATTERS
SUBCHAPTER B—ACQUISITION PLANNINGPART 405—PUBLICIZING CONTRACT ACTIONS
PART 406—COMPETITION REQUIREMENTS
PART 407—[RESERVED]
PART 408—REQUIRED SOURCES OF SUPPLIES AND SERVICES
PARTS 409 and 410—[RESERVED]
PART 411—DESCRIBING AGENCY NEEDS
PART 412—ACQUISITION OF COMMERICAL ITEMS
SUBCHAPTER C—CONTRACTING METHODS AND CONTRACT TYPESPART 413—SIMPLIFIED ACQUISITION PROCEDURES
PART 414—SEALED BIDDING
PART 415—CONTRACTING BY NEGOTIATION
PART 416—TYPES OF CONTRACTS
PARTS 417 AND 418—[RESERVED]
SUBCHAPTER D—SOCIOECONOMIC PROGRAMSPART 419—SMALL BUSINESS PROGRAMS
PARTS 420 AND 421—[RESERVED]
PART 422—APPLICATION OF LABOR LAWS TO GOVERNMENT ACQUISITIONS
PART 423—ENVIRONMENT, SUSTAINABLE ACQUISITION, AND MATERIAL SAFETY
PART 424—[RESERVED]
PART 425—FOREIGN ACQUISITION
PART 426—OTHER SOCIOECONOMIC PROGRAMS
SUBCHAPTER E—GENERAL CONTRACTING REQUIREMENTSPART 427—[RESERVED]
PART 428—BONDS AND INSURANCE
PART 429—[RESERVED]
PART 430—COST ACCOUNTING STANDARDS ADMINISTRATION
PART 431—CONTRACT COST PRINCIPLES AND PROCEDURES
PART 432—CONTRACT FINANCING
PART 433—PROTESTS, DISPUTES AND APPEALS
SUBCHAPTER F—SPECIAL CATEGORIES OF CONTRACTINGPART 434—MAJOR SYSTEM ACQUISITION
PART 435—[RESERVED]
PART 436—CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS
PART 437—SERVICE CONTRACTING
PARTS 438 THROUGH 441—[RESERVED]
SUBCHAPTER G—CONTRACT MANAGEMENTPARTS 442 THROUGH 444—[RESERVED]
PART 445—GOVERNMENT PROPERTY
PARTS 446 THROUGH 448—[RESERVED]
PART 449—TERMINATION OF CONTRACTS
PART 450—EXTRAORDINARY CONTRACTUAL ACTIONS AND THE SAFETY ACT
PART 451—[RESERVED]
SUBCHAPTER H—CLAUSES AND FORMSPART 452—SOLICITATION PROVISIONS AND CONTRACT CLAUSES
PARTS 453 THROUGH 469—[RESERVED]
SUBCHAPTER I—FOOD ASSISTANCE PROGRAMSPART 470—COMMODITY ACQUISITIONS
PARTS 471 THROUGH 499—[RESERVED]
SUBCHAPTER A—GENERAL
PART 400—[RESERVED]
PART 401—AGRICULTURE ACQUISITION REGULATION SYSTEM
- Subpart 401.1—Purpose, Authority, Issuance
- 401.101
- Purpose.
- 401.103
- Authority.
- 401.104
- Applicability.
- 401.105
- Issuance.
- 401.105-1
- Publication and code arrangement.
- 401.105-2
- Arrangement of regulations.
- 401.105-3
- Copies.
- 401.170
- Electronic access to regulatory information. Subpart 401.2—Administration
- 401.201
- Maintenance of the FAR.
- 401.201-1
- The two councils. Subpart 401.3—Agency Acquisition Regulations
- 401.301
- Policy.
- 401.304
- Agency control and compliance procedures.
- 401.370
- Exclusions.
- 401.371
- USDA Contracting Desk Book.
- 401.372
- Departmental directives. Subpart 401.4—Deviations From the FAR and AGAR 401.402
- Policy.
- 401.403
- Individual deviations.
- 401.404
- Class deviations. Subpart 401.6—Career Development, Contracting Authority, and Responsibilities
- 401.601
- General.
- 401.602
- Contracting officers.
- 401.602-3
- Ratification of unauthorized commitments.
- 401.603
- Selection, appointment, and termination of appointment for contracting officers.
- 401.603-1
- General.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 401.1—Purpose, Authority, Issuance
The United States Department of Agriculture's (USDA's) Acquisition Regulation (AGAR) provides for the codification and publication of uniform policies and procedures for acquisitions by contracting activities within USDA. The purpose of the AGAR is to implement the Federal Acquisition Regulation (FAR), where further implementation is needed, and to supplement the FAR when coverage is needed for subject matter not covered in the FAR. The AGAR is not by itself a complete document, as it must be used in conjunction with the FAR.
The AGAR and subsequent amendments are issued under 5 U.S.C. 301 and 40 U.S.C. 486(c). The Senior Procurement Executive (SPE) has the delegated authority to transmit Departmental acquisition regulations.
The FAR and AGAR apply to all USDA acquisitions of supplies and services (including construction) which obligate appropriated funds, unless otherwise specified or excepted by law.
(a) The AGAR is codified in the Code of Federal Regulations (CFR) as chapter 4 of title 48, Federal Acquisition Regulations System, to implement and supplement chapter 1 which constitutes the FAR. Parts 400 through 499 of this title have been assigned to USDA by the Office of the Federal Register.
(b) The AGAR and its subsequent changes are published in:
(1) Daily issues of the Federal Register ;
(2) Cumulative form in the CFR; and
(3) Electronic form on the USDA Departmental Administration procurement website (see AGAR 401.170).
(c) Section 553(a)(2) of the Administrative Procedure Act, 5 U.S.C. 553, provides an exception from the standard public rulemaking procedures to the extent that the rule involves a matter relating to agency management or personnel or to public property, loans, grants, benefits, or contracts.
(d) The AGAR may be revised from time to time in accordance with the rulemaking procedures of the Administrative Procedure Act. The USDA is also required to publish for public comment procurement regulations in the Federal Register , pursuant to the Office of Federal Procurement Policy Act (41 U.S.C. 418b), and FAR 1.301.
AGAR coverage parallels the FAR in format, arrangement, and numbering system. However, subdivisions below the section and subsection levels may not always correlate directly to FAR designated paragraphs and subparagraphs.
Copies of the AGAR published in the CFR form may be purchased from the Superintendent of Documents, Government Printing Office, Washington, DC 20402. Requests should reference chapter 4 of title 48 CFR.
The USDA procurement website provides access to the AGAR, AGAR amendments (circulars), the USDA Contracting Desk Book, and other USDA procurement policy and guidance.
Subpart 401.2—Administration
(a) USDA's representative on the Civilian Agency Acquisition Council is designated by the SPE.
(b) USDA Office of Contracting and Procurement, Procurement Policy Division will coordinate proposed FAR revisions within USDA.
Subpart 401.3—Agency Acquisition Regulations
(a) The SPE, subject to the authorities in AGAR 401.103 and FAR 1.301, may issue and publish Departmental regulations, that together with the FAR constitute Department-wide policies, procedures, solicitation provisions, and contract clauses governing the contracting process or otherwise controlling the relationship between USDA (including any of its contracting activities) and contractors or prospective contractors.
(b) Each designated Mission Area senior contracting official is authorized to issue or authorize the issuance of, at any organizational level, internal guidance which does not have a significant effect beyond the internal operating procedures of the activity, or a significant cost or administrative impact on offerors or contractors. Internal guidance issued by contracting activities will not be published in the Federal Register . Mission Area contracting leadership shall ensure that the guidance, procedures, or instructions issued—
(1) Are consistent with the policies and procedures contained in this regulation and the USDA Contracting Desk Book;
(2) Follow the format, arrangement, and numbering system of this regulation to the extent practicable;
(3) Contain no material which duplicates, paraphrases, or is inconsistent with this regulation; and
(4) Are numbered and identified by use of alphabetical suffices to the chapter number as follows:
(i) Marketing and Regulatory Programs (MRP).
(ii) Research, Education and Economics (REE).
(iii) Food, Nutrition and Consumer Services (FNCS).
(iv) Natural Resources and Environment (NRE).
(v) Farm Production and Conservation (FPAC).
(vi) Food Safety and Inspection Services (FSIS).
(vii) [Reserved]
(viii) Departmental Administration (DA) or Departmental Management (DM).
(ix) [Reserved]
(x) Rural Development (RD).
(a) The AGAR System is under the direct oversight and control of the SPE, who is responsible for review and issuance of all Department-wide acquisition regulations published in the Federal Register to assure compliance with FAR part 1.
(b) The SPE is also responsible for review and issuance of unpublished, Department-wide internal guidance under the AGAR System.
(c) The Mission Area senior contracting official is responsible for establishment and implementation of formal procedures for oversight and control of unpublished internal guidance issued within the contracting activity to implement FAR or AGAR requirements. These procedures shall be subject to the review and approval by the SPE.
(d) The SPE is responsible for evaluating coverage under the AGAR system to determine applicability to other agencies and for recommending coverage to the FAR Secretariat for inclusion in the FAR.
(e) Recommendations for revision of existing FAR coverage or new FAR coverage shall be submitted by the Mission Area senior contracting official to the SPE for further action.
Subject to the policies of FAR 1.3, certain USDA acquisition policies and procedures may be excluded from the AGAR under appropriately justified circumstances, such as:
(a) Subject matter which is effective for a period less than 12 months.
(b) Subject matter which is instituted on an experimental basis for a reasonable period.
(c) Acquisition procedures instituted on an interim basis to comply with the requirements of statute, regulation, Executive order, Office of Management and Budget (OMB) Circular, or Office of Federal Procurement Policy (OFPP) Policy Letter.
(a) The SPE may issue and update the USDA Contracting Desk Book, consistent with the policies of the FAR and the AGAR, for the following purposes:
(1) To communicate Department-wide policy and/or procedural guidance to contracting activities;
(2) To delegate to procurement officials the authority to make determinations or to take action to implement the policies of the FAR or the AGAR; and
(3) To establish internal policy and procedures on an interim basis, prior to incorporation in the AGAR or in a Departmental Directive.
(b) The USDA Contracting Desk Book is only available in electronic format on the USDA procurement website.
Subject to the policies of FAR 1.3, USDA from time to time may issue internal directives to establish procedures, standards, guidance, methods of performing duties, functions, or operations. Such directives include Departmental Regulations (DRs), Departmental Notices, and Secretary's Memoranda.
Subpart 401.4—Deviations From the FAR and AGAR
401.402Requests for authority to deviate from the provisions of the FAR or the AGAR shall be submitted in writing as far in advance of the situation as time will permit. Each request for deviation shall contain the following:
(a) A statement of the deviation desired, including identification of the specific paragraph number(s) of the FAR and AGAR;
(b) The reason why the deviation is considered necessary or would be in the best interest of the Government;
(c) If applicable, the name of the contractor and identification of the contract affected;
(d) A statement as to whether the deviation has been requested previously and, if so, circumstances of the previous request;
(e) A description of the intended effect of the deviation;
(f) A statement of the period of time for which the deviation is needed; and
(g) Any pertinent background information which will contribute to a full understanding of the desired deviation.
In individual cases, deviations from either the FAR or the AGAR will be authorized only when essential to effect a necessary acquisition or where special circumstances make such deviations clearly in the best interest of the Government. Except for cost principles, the Head of the Contracting Activity (HCA) may approve individual deviations from the AGAR, after coordinating with the Office of General Counsel (OGC) and the SPE. No deviations from the FAR or AGAR may be authorized by an individual contracting officer or an individual contracting office. A copy of each deviation and its supporting documents shall be provided to the SPE. Deviations from the FAR shall not be made unless such action is authorized by the SPE after consultation with the OGC and any other appropriate office, based on a written justification stating clearly the special circumstances involved.
Where deviations from the FAR or AGAR are considered necessary for classes of contracts, requests for authority to deviate shall be submitted in writing to the SPE for approval. The SPE may authorize class deviations from the FAR without consulting the Chairperson of the Civilian Agency Acquisition Council (CAAC) where urgency precludes consultation. The SPE shall subsequently inform the Chairperson of the CAAC of the deviation, including the circumstances under which it was required.
Subpart 401.6—Career Development, Contracting Authority, and Responsibilities
(a) The authority and responsibility vested in the Secretary to manage USDA's acquisition function is delegated through the Assistant Secretary for Administration to the SPE. This broad authority includes, but is not limited to, the following responsibilities:
(1) Prescribing and publishing Departmental acquisition policies, regulations, and procedures.
(2) Taking any necessary actions consistent with policies, regulations, and procedures with respect to purchases, contracts, leases, and other transactions.
(3) Designating contracting officers.
(4) Establishing clear lines of contracting authority.
(5) Evaluating and monitoring the performance of USDA's acquisition system.
(6) Managing and enhancing career development of the acquisition workforce.
(7) Participating in the development of Government-wide acquisition policies, regulations, and standards; and determining specific areas where government-wide performance standards should be established and applied.
(8) Determining areas of Department—unique standards and developing unique Department-wide standards.
(9) Certifying to the Secretary that the acquisition system meets approved standards.
(b) The SPE may delegate specified contracting authority and the responsibility to manage related acquisition functions.
(c) Unless prohibited by the FAR, the AGAR, or by other applicable statutes and regulations, the SPE may redelegate specified authority to make determinations in order to implement the policies and procedures of the FAR. Such delegations shall be in writing but need not be published. Such delegations may be made by the HCA if authority has been delegated by the SPE.
(a) Ratification means the signed, documented action taken by an authorized official to approve and sanction a previously unauthorized commitment.
(b) Unauthorized commitment means an agreement made by a Government representative who lacked the authority to enter into a contract on behalf of the Government. Procedures for unauthorized commitments are in accordance with the USDA Contracting Desk Book, part 401.602-3.
The SPE may delegate contracting authority to the extent authorized by general written delegation of acquisition authority appointing qualified individuals as contracting officers, in accordance with selection and appointment procedures as stated in the USDA Contracting Desk Book.
PART 402—DEFINITIONS OF WORDS AND TERMS
- Subpart 402.1—Definitions
- 402.101
- Definitions.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 402.1—Definitions
Acquisition official means an individual who has been delegated authority to manage or to exercise acquisition functions and responsibilities.
Agency head or head of the agency means the Secretary of Agriculture (Secretary), Deputy Secretary, or the Assistant Secretary for Administration (ASA).
Head of the Contracting Activity (HCA) means the official with overall responsibility of one or more USDA contracting activities.
Mission Area senior contracting official means the official designated by the Senior Procurement Executive or Head of the Contracting Activity with specific responsibilities within an individual Mission Area's contracting activity.
Senior Procurement Executive (SPE) means the agency official appointed as such by the Head of the Agency pursuant to Executive Order 12931. The Director, Office of Contracting and Procurement, has been designated as the USDA SPE.
PART 403—IMPROPER BUSINESS PRACTICES AND PERSONAL CONFLICTS
- Subpart 403.1—Safeguards
- 403.101
- Standards of conduct.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 403.1—Safeguards
(a) The standards of conduct for USDA procurement officials are the uniform standards established by the Office of Government Ethics in 5 CFR part 2635, Standards of Ethical Conduct for Employees of the Executive Branch, and FAR 3.104, Procurement Integrity.
(b) Procurement officials and other employees who require advice concerning the application of standards of conduct to any acquisition issue shall obtain opinions from the USDA Office of Ethics or the ethics advisory officials within their agency.
PART 404—ADMINISTRATIVE AND INFORMATION MATTERS
- Subpart 404.8—Government Contract Files
- 404.804
- Closeout of contract files. Subpart 404.13—Personal Identity Verification
- 404.1303
- Contract clause.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 404.8—Government Contract Files
The contracting officer shall insert the clause at AGAR 452.204-70, Modification for Contract Closeout, in all solicitations and contracts that use simplified acquisition procedures.
Subpart 404.13—Personal Identity Verification
FAR 4.13, Personal Identity Verification, establishes the policy and use requirements for FAR 52.204-9. The contracting officer shall insert a clause that contains language similar to that in AGAR 452.204-71 in all covered solicitations and contracts which include FAR 52.204-9.
SUBCHAPTER B—ACQUISITION PLANNING
PART 405—PUBLICIZING CONTRACT ACTIONS
- Subpart 405.4—Release of Information
- 405.404
- Release of long-range acquisition estimates.
- 405.404-1
- Release procedures. Subpart 405.5—Paid Advertisements
- 405.502
- Authority.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 405.4—Release of Information
The HCA is the agency head designee pursuant to FAR 5.404-1.
Subpart 405.5—Paid Advertisements
The authority vested in the HCA to authorize publication of paid advertisements in newspapers (44 U.S.C. 3702) is delegated, with power of redelegation, to Mission Area senior contracting officials. A Mission Area senior contracting official's redelegation of this authority shall be in writing.
PART 406—COMPETITION REQUIREMENTS
- Subpart 406.2—Full and Open Competition After Exclusion of Sources
- 406.202
- Establishing or maintaining alternative sources. Subpart 406.3—Other Than Full and Open Competition 406.302
- Circumstances permitting other than full and open competition.
- 406.302-70
- Otherwise authorized by law.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 406.2—Full and Open Competition After Exclusion of Sources
The SPE is authorized to make determinations pursuant to FAR 6.202(a) and sign the determination and findings required by FAR 6.202(b).
Subpart 406.3—Other Than Full and Open Competition
406.302(a) Authority. Section 1472 of the National Agricultural Research, Extension, and Teaching Policy Act of 1977 (7 U.S.C. 3318) (the Act) authorizes the Secretary of Agriculture to award contracts, without competition, to further research, extension, or teaching programs in the food and agricultural sciences.
(b) Limitations. The use of this authority is limited to those instances where it can be determined that contracting without full and open competition is in the best interest of the Government and necessary to the accomplishment of the research, extension, or teaching program. Therefore:
(1) Contracts under the authority of the Act shall be awarded on a competitive basis to the maximum practicable extent.
(2) When full and open competition is not deemed appropriate, the contracting officer shall make a written justification on a case-by-case basis in accordance with procedures in FAR 6.303 and 6.304.
PART 407—[RESERVED]
PART 408—REQUIRED SOURCES OF SUPPLIES AND SERVICES
- Subpart 408.8—Acquisition of Printing and Related Supplies
- 408.802
- Policy.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 408.8—Acquisition of Printing and Related Supplies 408.802 Policy.
The Director, Office of Communications (OC) has been designated as the central printing authority in USDA, with the authority to represent the USDA before the Joint Committee on Printing (JCP), the Government Printing Office, and other Federal and State agencies on all matters related to printing.
PARTS 409 AND 410—[RESERVED]
PART 411—DESCRIBING AGENCY NEEDS
- Subpart 411.1—Selecting and Developing Requirements Documents
- 411.101
- Order of precedence for requirements documents. Subpart 411.2—Using and Maintaining Requirements Documents
- 411.202
- Maintenance of standardization documents. Subpart 411.6—Priorities and Allocations
- 411.602
- General.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 411.1—Selecting and Developing Requirements Documents
(a) OMB Circular A-119 establishes a Federal policy requiring the use of voluntary consensus standards in lieu of government-unique standards except where inconsistent with law or otherwise impractical.
(b) An HCA is authorized to submit the determination required by OMB Circular A-119 that a voluntary standard is inconsistent with law or otherwise impracticable. The HCA must submit the determination to OMB through the National Institute of Standards and Technology (NIST) in accordance with the Circular with a copy provided to the SPE.
Subpart 411.2—Using and Maintaining Requirements Documents
Recommendations for changes to standardization documents are to be submitted through the SPE, who will coordinate the submission of these recommendations to the cognizant preparing activity.
Subpart 411.6—Priorities and Allocations
USDA has authority to issue rated orders under section 202(c) of Executive Order 13603, and the Defense Production Act of 1950, as Amended (DPA), 50 U.S.C. 4501 et seq.
PART 412—ACQUISITION OF COMMERICAL ITEMS
- Subpart 412.3—Solicitation Provisions and Contract Clauses for the Acquisition of Commercial Items
- 412.302
- Tailoring of provisions and clauses for the acquisition of commercial items.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 412.3—Solicitation Provisions and Contract Clauses for the Acquisition of Commercial Items
The HCA is authorized to approve waivers in accordance with FAR 12.302(c). The approved waiver may be either for an individual contract or for a class of contracts for the specific item. The approved waiver and supporting documentation shall be incorporated into the contract file.
SUBCHAPTER C—CONTRACTING METHODS AND CONTRACT TYPES
PART 413—SIMPLIFIED ACQUISITION PROCEDURES
- Subpart 413.3—Simplified Acquisition Methods
- 413.302
- Purchase orders.
- 413.302-5
- Clauses.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 413.3—Simplified Acquisition Methods
The contracting officer shall insert the clause at AGAR 452.204-70, Modification for Contract Closeout, in all solicitations and contracts that use simplified acquisition procedures.
PART 414—SEALED BIDDING
- Subpart 414.4—Opening of Bids and Award of Contract 414.404
- Rejection of bids.
- 414.404-1
- Cancellation of invitations after opening.
- 414.407
- Mistakes in bids.
- 414.407-3
- Other mistakes disclosed before award.
- 414.407-4
- Mistakes after award.
- 414.409
- Information to bidders.
- 414.409-2
- Award of classified contracts.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 414.4—Opening of Bids and Award of Contract
414.404An acquisition official at a level above the contracting officer is authorized to request the determinations under FAR 14.404-1(c) and (e)(1).
The authority to make the determinations under FAR 14.407-3(a), (b), and (d) is delegated, without power of redelegation, to the HCA. The authority to make the determination under FAR 14.407-3(c) is delegated to the contracting officer. Each determination pursuant to FAR 14.407- 3 shall have the concurrence of the Office of the General Counsel (OGC).
If a mistake in bid is disclosed after award, the contracting officer shall make a final determination in accordance with the provisions of FAR 14.407-4(b) and (c) and shall coordinate each proposed determination with OGC. Such coordination shall, at a minimum, consist of the contracting officer providing the proposed determination and the case file to OGC for comment.
Disposition of classified information shall be in accordance with Departmental Regulation and Manual (3400-001 Series) and in accordance with direction issued by the USDA Office of Homeland Security (OHS), Personnel and Document Security Division.
PART 415—CONTRACTING BY NEGOTIATION
- Subpart 415.2—Solicitation and Receipt of Proposals and Information
- 415.204
- Contract format. Subpart 415.3—Source Selection
- 415.305
- Proposal evaluation. Subpart 415.6—Unsolicited Proposals
- 415.604
- Agency points of contact.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 415.2—Solicitation and Receipt of Proposals and Information
The HCA is authorized to exempt contracts from the uniform contract format.
Subpart 415.3—Source Selection
Each Mission Area senior contracting official is responsible for establishing procedures regarding the release of cost information to the members of the technical evaluation team per FAR 15.305(a)(4).
Subpart 415.6—Unsolicited Proposals
Each Mission Area senior contracting official is responsible for establishing points of contact for the control of unsolicited proposals. An unsolicited proposal must be formally submitted to the Agency by way of the point of contact.
PART 416—TYPES OF CONTRACTS
- Subpart 416.1—Selecting Contract Types
- 416.102
- Policies. Subpart 416.2—Fixed-Price Contracts 416.203
- Fixed-price contracts with economic price adjustment.
- 416.203-4
- Contract clauses. Subpart 416.6—Time-and-Materials, Labor- Hour, and Letter Contracts 416.603
- Letter contracts.
- 416.603-2
- Application.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 416.1—Selecting Contract Types
The contracting officer shall insert the clause at AGAR 452.204-70, Modification for Contract Closeout, in all solicitations and contracts that use other than cost reimbursement contract types.
Subpart 416.2—Fixed-Price Contracts
416.203An economic price adjustment clause based on cost indexes of labor or material may be used under the conditions listed in FAR 16.203-4(d) after HCA approval and consultation with the Office of the General Counsel (OGC).
Subpart 416.6—Time-and-Materials, Labor-Hour, and Letter Contracts
416.603The HCA is authorized to extend the period for defining a letter contract required by FAR 16.603-2(c) in extreme cases where it is determined in writing that such action is in the best interest of the Government.
PARTS 417 AND 418—[RESERVED]
SUBCHAPTER D—SOCIOECONOMIC PROGRAMS
PART 419—SMALL BUSINESS PROGRAMS
- Subpart 419.2—Policies
- 419.201
- General Policy.
- 419.201-71
- Small business coordinators.
- 419.201-72
- Reports. Subpart 419.6—Certificates of Competency and Determinations of Responsibility
- 419.602
- Procedures.
- 419.602-3
- Resolving differences between the agency and the Small Business Administration.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 419.2—Policies
The Mission Area senior contracting official shall designate, in writing, small business coordinator(s). The number of coordinators shall be determined by the Mission Area senior contracting official and sufficient for the number of contracting officers or contracting offices.
The Office of Small & Disadvantaged Business Utilization (OSDBU) Director shall be responsible for submitting reports concerning USDA's progress and achievements in the procurement preference program.
Subpart 419.6—Certificates of Competency and Determinations of Responsibility
The HCA is authorized to appeal the issuance of a Certificate of Competency (COC) to SBA as provided by FAR 19.602-3(a).
PARTS 420 AND 421—[RESERVED]
PART 422—APPLICATION OF LABOR LAWS TO GOVERNMENT ACQUISITIONS
- Subpart 422.3—Contract Work Hours and Safety Standards Act
- 422.302
- Liquidated damages and overtime pay. Subpart 422.4—Labor Standards for Contracts Involving Construction 422.404
- Construction Wage Rate Requirements statute wage determinations.
- 422.404-6
- Modifications of wage determinations.
- 422.406
- Administration and enforcement.
- 422.406-8
- Investigations. Subpart 422.8—Equal Employment Opportunity
- 422.804
- Affirmative action programs.
- 422.804-2
- Construction.
- 422.807
- Exemptions. Subpart 422.13—Equal Opportunity for Veterans
- 422.1305
- Waivers. Subpart 422.14—Employment of Workers With Disabilities
- 422.1403
- Waivers.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 422.3—Contract Work Hours and Safety Standards Act
The Mission Area senior contracting official is authorized to review determinations of liquidated damages due under section 104(c) of the Contract Work Hours and Safety Standards Act, and to recommend remedial action, if appropriate, in accordance with FAR 22.302(c). Contractors or subcontractors may request review of administrative determinations of liquidated damages by written notice to the contracting officer. The contracting officer shall promptly forward appeals of liquidated damages determinations to the Mission Area senior contracting official.
Subpart 422.4—Labor Standards for Contracts Involving Construction
422.404The Mission Area senior contracting official is authorized to process the request for extension of the 90-day period for award after bid opening as provided in FAR 22.404-6(b)(6).
The HCA is authorized to submit reports of violations to the agency head in accordance with FAR 22.406-8(d).
Subpart 422.8—Equal Employment Opportunity
The Mission Area senior contracting official shall ensure that each contracting office awarding nonexempt construction contracts maintains a current listing of covered geographical areas subject to affirmative action requirements specifying goals for minorities and women in covered construction trades, as provided in FAR 22.804-2(b).
The HCA oversees exemptions of all or part of the requirements of E.O. 11246 pursuant to FAR 22.807(c).
Subpart 422.13—Equal Opportunity for Veterans
The Assistant Secretary for Administration (ASA) is authorized to make the waiver determination in FAR 22.1305(b) that a contract is essential to the national security. The waiver shall be prepared for the ASA's signature and submitted by the Mission Area senior contracting official to the SPE for referral to the ASA.
Subpart 422.14—Employment of Workers With Disabilities
The ASA is authorized to make the waiver determinations under FAR 22.1403(a) and FAR 22.1403(b) with the concurrence of the Deputy Assistant Secretary for Federal Contract Compliance Programs, Department of Labor. The waiver shall be prepared for the ASA's signature and submitted by the Mission Area senior contracting official to the SPE for referral to the ASA.
PART 423—ENVIRONMENT, SUSTAINABLE ACQUISITION, AND MATERIAL SAFETY
- Subpart 423.1—Use of Recovered Materials
- 423.107
- Agency affirmative procurement programs. Subpart 423.3—Hazardous Material Identification, Material Safety Data, and Notice of Radioactive Materials
- 423.303
- Notice of radioactive materials.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 423.1—Use of Recovered Materials
The USDA affirmative procurement program (APP) policy applicable to all USDA agencies and staff offices is hereby established. Components of the APP are in the USDA Contracting Desk Book part 423.
Subpart 423.3—Hazardous Material Identification, Material Safety Data, and Notice of Radioactive Materials
The HCA shall establish a system of instructions to identify the installation/facility radiation protection officer.
PART 424—[RESERVED]
PART 425—FOREIGN ACQUISITION
- Subpart 425.6—American Recovery and Reinvestment Act—Buy American Statute—Construction Materials
- 425.603
- Exceptions.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 425.6—American Recovery and Reinvestment Act—Buy American Statute—Construction Materials
The Secretary, without power of redelegation, has the authority to make the necessary determination(s) and authorize award(s) of contract(s) in accordance with FAR 25.603(b).
PART 426—OTHER SOCIOECONOMIC PROGRAMS
- Subpart 426.5—Drug-Free Workplace
- 426.505
- Suspension of payments, termination of contract, and debarment and suspension actions.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 426.5—Drug-Free Workplace
The SPE will submit the request for a waiver to the agency head with a recommendation for action per FAR 23.506(e).
SUBCHAPTER E—GENERAL CONTRACTING REQUIREMENTS
PART 427—[RESERVED]
PART 428—BONDS AND INSURANCE
- Subpart 428.1—Bonds and Other Financial Protections
- 428.101
- Bid guarantees.
- 428.101-1
- Policy on use.
- 428.106
- Administration.
- 428.106-6
- Furnishing information. Subpart 428.2—Sureties and Other Security for Bonds
- 428.203
- Individual sureties.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 428.1—Bonds and Other Financial Protections
The SPE may authorize class waivers of the requirement to obtain bid guarantees per FAR 28.101-1(c).
HCAs or their designees may furnish certified copies of bonds and the contracts for which they were given as provided by FAR 28.106-6(c). Requesters may be required to pay costs of certification and copying established by the Departmental Fee Schedule for records requests (7 CFR part 1, subpart A, appendix A).
Subpart 428.2—Sureties and Other Security for Bonds
Evidence of possible criminal or fraudulent activities by an individual surety shall be reported to the OIG in accordance with Departmental Regulations (1700 series). The Mission Area senior contracting official shall establish procedures to ensure protection and conveyance of deposited securities of the types listed in FAR 28.204-1 through 28.204-3.
PART 429—[RESERVED]
PART 430—COST ACCOUNTING STANDARDS ADMINISTRATION
- Subpart 430.2—CAS Program Requirements
- 430.201
- Contract requirements.
- 430.201-5
- Waiver.
- 430.202
- Disclosure requirements.
- 430.202-2
- Impracticality of submission.
- 430.202-8
- Subcontractor disclosure statements.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 430.2—CAS Program Requirements
The SPE, without the authority to further redelegate, is authorized to request the Cost Accounting Standards Board to waive the application of the Cost Accounting Standards (CAS) in accordance with FAR 30.201-5.
The Secretary, without the power to redelegate, is authorized to determine, in accordance with 48 CFR 9903.202-2, that the Disclosure Statement is impractical to secure and to authorize award without obtaining the Disclosure Statement.
The Secretary, without the power to redelegate, is authorized to determine, in accordance with 48 CFR 9903.202-2, that the Disclosure Statement for a subcontractor is impractical to secure and to authorize award without obtaining the Disclosure Statement.
PART 431—CONTRACT COST PRINCIPLES AND PROCEDURES
- Subpart 431.1—Applicability
- 431.101
- Objectives.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 431.1—Applicability
(a) The SPE is designated as the official authorized to give advance approval of an individual deviation concerning cost principles.
(b) The SPE is designated as the official authorized to give advance approval of a class deviation concerning cost principles after coordination with the Civilian Agency Acquisition Council (CAAC).
PART 432—CONTRACT FINANCING
432.001Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Agency contract finance office is the office, other than the office of the requisitioner, providing funding or performing funding record keeping for the contract action.
Head of agency. For the purposes of this part, head of the agency means, exclusively, the Secretary or the Deputy Secretary.
Remedy coordination official (RCO). The USDA RCO is the Assistant Secretary for Administration.
Responsible fiscal authority is that officer in the agency contract finance office with the responsibility to ensure that adequate funds are available and usable for the intended purpose.
The annual report required by FAR 32.006-5 is to be prepared by the SPE and submitted to the Secretary within 90 calendar days after the end of the fiscal year. When signed by the Secretary, the report is to be maintained by the SPE.
The Mission Area senior contracting official may prescribe, on a case-by-case basis, a shorter period for financing payments.
Subpart 432.1—Non-Commercial Item Purchase Financing
The HCA is authorized to approve unusual contract financing.
Subpart 432.2—Commercial Item Purchase Financing
The responsibility for administration of the liquidation provisions of a contract may not be transferred from the contracting officer.
Subpart 432.3—Loan Guarantees for Defense Production
Within this subpart, the agency or guaranteeing agency is the HCA and may not be redelegated.
Subpart 432.4—Advance Payments for Non-Commercial Items
An HCA is designated as the individual responsible for making the findings and determination, and for approval of the contract terms concerning advance payments.
The HCA is designated as the individual responsible for coordination with the Department of Treasury concerning letters of credit.
(a) The HCA is designated as the individual who may authorize, on a case-by-case basis, advance payments without interest for the contract types described in FAR 32.407(d)(1) through
(4). The signed determination and findings supporting these authorizations shall be included in the contract files.
(b) The SPE is designated as the individual who may authorize advance payments without interest other than those described in paragraph (a) of this section.
The decision to use Alternates I or III to FAR 52.232-12 must be supported by a determination and finding.
Subpart 432.7—Contract Funding
Use the clause AGAR 452.232-70, Limitation of Government's Obligation, in solicitations and resultant incrementally funded fixed-price contracts.
Funds appropriated to USDA may be used for one-year contracts which are to be performed in two fiscal years so long as the total amount for such contracts is obligated in the year for which the funds are appropriated (7 U.S.C. 2209c).
The expenditure of any USDA appropriation for any consulting service through any contract, pursuant to section 3109 of title 5 of the U.S. Code shall be limited to those contracts where such expenditures are a matter of public record and available for public inspection, except where otherwise provided under existing law, or under existing Executive order issued pursuant to existing law (7 U.S.C. 2225a).
Subpart 432.8—Assignment of Claims
432.802Written notices of assignment and a true copy of the assigned instrument are to be sent to the contracting officer rather than the agency head per FAR 32.802(e)(1). Other copies are distributed as directed in FAR 32.802.
PART 433—PROTESTS, DISPUTES AND APPEALS
- Subpart 433.1—Protests
- 433.102
- General. Subpart 433.2—Disputes and Appeals
- 433.203
- Applicability.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 433.1—Protests
The SPE is responsible for coordinating the processing of bid protests lodged with the Government Accountability Office (GAO).
Subpart 433.2—Disputes and Appeals
The Assistant Secretary for Administration is authorized to determine the applicability of the Contract Disputes Act to contracts with foreign governments pursuant to FAR 33.203.
SUBCHAPTER F—SPECIAL CATEGORIES OF CONTRACTING
PART 434—MAJOR SYSTEM ACQUISITION
434.001Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Pursuant to OMB Circular No. A-11 (Circular A-11) and the definition at FAR 2.101, within USDA, a system shall be considered a major system if:
(a) The system has been identified as a Major IT Investment pursuant to USDA Departmental Regulation 3030- 008, Definition of Major Information Technology Investments;
(b) The total non-IT acquisition costs are estimated to be $50 million or more; or
(c) The system, regardless of estimated acquisition or life cycle costs, has been specifically designated to be a major system by the USDA Acquisition Executive or by the Major Information Technology Systems Executive. The Assistant Secretary for Administration (ASA) is the USDA Acquisition Executive for major system acquisition other than acquisitions of information technology.
In addition to the policy guidance at FAR 34.002 and other parts of the FAR, the policies outlined in part 7 of Circular A-11 should serve as guidelines for all contracting activities in planning and developing systems, major or otherwise.
(a) The key executives of USDA (Secretary, Deputy Secretary, Under Secretaries and Assistant Secretaries) individually or as a group will participate in making four key decision in each major system acquisition process.
(1) Identification and definition of a specific mission need to be fulfilled, the relative priority assigned within the agency, and the general magnitude of resources that may be invested.
(2) Selection of competitive system design concepts to be advanced to a test/demonstration phase or authorization to proceed with the development of a noncompetitive (single concept) system.
(3) Commitment of a system to full-scale development and limited production.
(4) Commitment of a system to full production.
(b) The Chief Information Officer (CIO) is the Major Information Technology Systems Executive. For acquisitions of information technology, the CIO will ensure that Circular A-11 is implemented in USDA and that the management objectives of Circular A-11 are realized. The CIO is responsible for designating the program manager for each major information technology system acquisition, designating an acquisition to be a major information technology system acquisition, and approving the written charter and project control system for each major information technology system acquisition.
(c) The ASA will ensure that Circular A-11 is implemented in USDA and that the management objectives of Circular A-11 are realized. The SPE is responsible for designating the program manager for each major system non-IT acquisition, designating an acquisition to be a major system non-IT acquisition, and approving the written charter and project control system for each major system non-IT acquisition.
(d) The Mission Area senior contracting official must:
(1) Ensure compliance with the requirements of Circular A-11, FAR part 34, and AGAR part 434.
(2) Ensure that potential major system acquisitions are brought to the attention of the USDA Acquisition Executive or the Major Information Technology Systems Executive, as appropriate.
(3) Coordinate with Mission Area Program Managers (MASPMs) to recommend qualified candidates for designation as program managers for each major system acquisition within their jurisdiction.
(4) Coordinate with MASPMs to verify that program managers fulfill their responsibilities and discharge their duties.
(5) Cooperate with the ASA and Major Information Technology Systems Executive in implementing the requirements of Circular A-11.
(e) The program manager is responsible for planning and executing the major system acquisition, ensuring appropriate coordination with the USDA Acquisition Executive, Major Information Technology Systems Executive, and other key USDA executives.
The Secretary or the Secretary's designee for the specific program is the agency head for the purposes of FAR 34.005-6.
PART 435—[RESERVED]
PART 436—CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS
- Subpart 436.2—Special Aspects of Contracting for Construction 436.205
- Statutory cost limitations.
- 436.209
- Construction contracts with architect-engineer firms.
- 436.213
- Special procedures for sealed bidding in construction contracting.
- 436.213-2
- Presolicitation notices. Subpart 436.5—Contract Clauses 436.500
- Scope of subpart.
- 436.570
- Emergency response, fire suppression and liability. Subpart 436.6—Architect-Engineer Services
- 436.602
- Selection of firms for architect- engineer contracts.
- 436.602-1
- Selection criteria.
- 436.602-2
- Evaluation boards.
- 436.602-5
- Short selection process for contracts not to exceed the simplified acquisition threshold.
- 436.603
- Collecting data on and appraising firm's qualifications.
- 436.609
- Contract clauses.
- 436.609-1
- Design within funding limitations.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 436.2—Special Aspects of Contracting for Construction
436.205(a) When it appears that funds may be insufficient for all the desired features of construction, the contracting officer may provide in the solicitation for a base bid item covering the work as specified and for one or more additive or deductive bid items which progressively add or omit specified features of the work in a stated order of priority.
(b) In the alternative, the contracting officer may use the policies and procedures found in FAR 17.2, Options.
The HCA is authorized to approve a contract to construct a project, in whole or in part, to the firm that designed the project (inclusive of its subsidiaries or affiliates).
The authority to waive a presolicitation notice on any construction requirement when the proposed contract is expected to exceed the simplified acquisition threshold is restricted to the HCA.
Subpart 436.5—Contract Clauses
436.500This subpart prescribes clauses for insertion in USDA solicitations and contracts for construction and for dismantling, demolition, or removal of improvements or structures. The contracting officer shall use the clauses as prescribed in contracts that exceed the simplified acquisition threshold. The contracting officer may use the clauses if the contract amount is expected to be at or below the simplified acquisition threshold.
The contracting officer shall insert the clause at AGAR 452.236-70, Emergency Response, Fire Suppression and Liability, in Integrated Resource Service Contracts (IRSCs) awarded for the Forest Service. The clause AGAR 452.236-70, Emergency Response, Fire Suppression and Liability, is optional for non-IRSCs.
Subpart 436.6—Architect-Engineer Services
The Mission Area senior contracting official is authorized to approve the use of design competition under the conditions in FAR 36.602-1(b).
The Mission Area senior contracting official shall establish written procedures for providing permanent or ad hoc architect-engineer evaluation boards as prescribed in FAR 36.602-2.
The Mission Area senior contracting official may include either or both procedures in FAR 36.602-5(a) and (b) in the procedures for evaluation boards.
Mission Area senior contracting officials for Mission Areas that require architect- engineer services shall establish procedures to comply with the requirements of FAR 36.603.
(a) Should the HCA appoint a designee to make the determination in FAR 36.609-1(c)(1), the appointment may be to one no lower than the official authorized to commit program funds for the work being acquired.
(b) The contracting officer, with the advice of appropriate technical representatives, may make the determination in FAR 36.609-1(c)(2) or (3).
PART 437—SERVICE CONTRACTING
- Subpart 437.1—Service Contracts—General 437.104
- Personal services contracts. Subpart 437.2—Advisory and Assistance Services
- 437.204
- Guidelines for determining availability of personnel.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 437.1—Service Contracts—General
437.104USDA has the following specific statutory authorities to contract for personal services:
(a) Section 706(a) of the Organic Act of 1944 (7 U.S.C. 2225) authorizes contracting with persons or organizations on a temporary basis, without regard to civil service compensation classification standards in 5 U.S.C., chapter 51 and subchapter III of chapter 53, Provided:
(1) That no expenditures shall be made unless specifically provided for in the applicable appropriation; and
(2) Expenditures do not exceed any limitations prescribed in the appropriation.
(b) Title 7 of the U.S.C., section 1627 authorizes the Secretary of Agriculture to contract with technically qualified persons, firms or organizations to perform research, inspection, classification, technical, or other special services, without regard to the civil- service laws, if it is for a temporary basis and for a term not to exceed six months in any fiscal year.
Subpart 437.2—Advisory and Assistance Services
The HCA is authorized to request the use of non-Government evaluators in proposal evaluations. Each decision shall be supported by a written determination in accordance with FAR 37.204.
PARTS 438 THROUGH 441—[RESERVED]
SUBCHAPTER G—CONTRACT MANAGEMENT
PARTS 442 THROUGH 444—[RESERVED]
PART 445—GOVERNMENT PROPERTY
- Subpart 445.1—General
- 445.103
- General. Subpart 445.3—Authorizing the Use and Rental of Government Property
- 445.301
- Use and rental.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 445.1—General
The Mission Area senior contracting official is authorized to make determinations for charging rent on the basis of use under the Use and Charges clause in FAR 52.245-9 as prescribed in FAR 45.103(a)(5).
Subpart 445.3—Authorizing the Use and Rental of Government Property
(a) The Mission Area senior contracting official is authorized to make determinations for providing facilities to contractors as prescribed in FAR 45.301(f).
(b) Requests for non-Government use of plant equipment as prescribed in FAR 45.301 shall be submitted by the HCA to the SPE for approval.
PARTS 446 THROUGH 448—[RESERVED]
PART 449—TERMINATION OF CONTRACTS
- Subpart 449.5—Contract Termination Clauses 449.501
- General.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 449.5—Contract Termination Clauses
449.501Use of special purpose termination clauses pursuant to the authority of FAR 49.501 shall be approved in advance by the HCA.
PART 450—EXTRAORDINARY CONTRACTUAL ACTIONS AND THE SAFETY ACT
- Subpart 450.1—Extraordinary Contractual Actions
- 450.100
- Definitions.
- 450.102
- Delegation of and limitations on exercise of authority.
- 450.102-1
- Delegation of authority.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 450.1—Extraordinary Contractual Actions
Approving authority, as used in this part, means the Assistant Secretary for Administration.
Secretarial level, as used in this part means the Assistant Secretary for Administration.
The Assistant Secretary for Administration is authorized to approve all actions under FAR part 50 except indemnification actions listed in FAR 50.102-1(d), which must be approved by the Secretary, without power of redelegation.
PART 451—[RESERVED]
SUBCHAPTER H—CLAUSES AND FORMS
PART 452—SOLICITATION PROVISIONS AND CONTRACT CLAUSES
- Subpart 452.2—Texts of Provisions and Clauses 452.204-70
- Modification for Contract Closeout 452.204-71
- Personal Identity Verification of Contractor Employees.
- 452.232-70
- Limitation of Government's Obligation.
- 452.236-70
- Emergency Response, Fire Suppression, and Liability.
Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
Subpart 452.2—Texts of Provisions and Clauses
452.204-70As prescribed in AGAR 404.804, 413.302-5, and 416.102, insert the following clause:
Modification for Contract Closeout (Month Year)
“Upon contract closeout for contracts utilizing anything other than cost reimbursement:
(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the Contracting Officer (CO) shall issue a unilateral modification for deobligation. The contractor will receive a copy of the modification but will not be required to provide a signature. The CO shall immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.
(b) Upon contract closeout for contracts utilizing SAP: if unliquidated funds of more than $1000 remain on the contract, the CO shall issue a bilateral modification for deobligation. The contractor will receive a copy of the modification and will be required to provide a signature. (The CO may also request a “Contractor Release of Claims” be completed by the contractor, although not required for contracts and orders using SAP.) If the bilateral modification and Release of Claims are not returned to the CO within 60 days, the CO shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.
(c) Upon contract closeout for contracts utilizing anything other than cost reimbursement, if unliquidated funds of more than $1000 remain on the contract, the CO shall issue a bilateral modification for deobligation. The contractor will receive a copy of the modification and a “Contractor Release of Claims” and will be required to provide a signature on both forms. If the bilateral modification and Release of Claims are not returned to the CO within 120 days, the CO shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.
(End of Clause)
As prescribed in AGAR 404.1303, insert the following clause:
Personal Identity Verification of Contractor Employees (Month Year)
(a) The contractor shall comply with the personal identity verification (PIV) policies and procedures established by the United States Department of Agriculture (USDA) Directives 4620-002 series.
(b) Should the USDA Directives 4620-002 require the exclusion of a contractor's employee, the contracting officer will notify the contractor in writing. The contractor must appoint a representative to manage compliance with the PIV policies established by the USDA Directives 4620-002 and to maintain a list of employees eligible for a USDA LincPass required for performance of the work.
(c) The responsibility of maintaining a sufficient workforce remains with the contractor. Contractor employees may be barred by the Government from performance of work should they be found ineligible or to have lost eligibility for a USDA LincPass. Failure to maintain a sufficient workforce of employees eligible for a USDA LincPass may be grounds for termination of the contract.
(d) The contractor shall insert this clause in all subcontracts when the subcontractor is required to have routine unaccompanied physical access to a federally controlled facility and/or routine unaccompanied access to a federally controlled information system.
(e) The PIV Sponsor for this contract is a designated program point of contact, which in most cases is the COR, unless otherwise specified in this contract. The PIV Sponsor will be available to receive contractor identity information from [hours and days to be added by CO] to [hours and days to be added by CO] at [office address for registration to be added by CO]. The Government will notify the contractor if there is a change in the PIV Sponsor, the office address, or the office hours for registration; however, it is the contractor's responsibility to meet all aspects of paragraphs (c), (d), and (e).
(End of Clause)
As prescribed in AGAR 432.703, insert the following clause:
Limitation of Government's Obligation (Month Year)
(a) Contract line item(s) listed below is/are incrementally funded. For this/these item(s), the sum of $ [Contracting Officer insert after negotiations] of the total price is presently available for payment and allotted to this contract. An allotment schedule is set forth in paragraph (j) below.
Line Item Price Currently Allotted Funding Funds Required for Complete Funding
(b) For item(s) identified in paragraph (a) as not fully funded, the Contractor agrees to perform up to the point at which the total amount payable by the Government, including reimbursement of costs in the event of termination of those item(s) for the Government's convenience, approximates the total amount currently allotted to the contract. The Contractor is not authorized to continue work on those item(s) beyond that point. The Government will not be obligated in any event to reimburse the Contractor more than the amount allotted to the contract for those item(s) regardless of anything to the contrary in the clause entitled “Termination for Convenience of the Government”. The total amount payable by the Government in the event of termination of applicable contract line item(s) for convenience includes costs, profit, and estimated termination settlement costs for those item(s).
(c) Notwithstanding the dates specified in the allotment schedule in paragraph (j), the Contractor will notify the contracting officer in writing at least [30, 60, or 90, as appropriate] days prior to the date when, in the Contractor's best judgment, the work will reach the point at which the total amount payable by the Government, including any cost for termination for convenience, will approximate 85 percent of the total amount currently allotted to the contract for performance of the applicable item(s). The notification will state (1) the estimated date when that point will be reached and (2) an estimate of additional funding, if any, needed to continue performance of applicable line items up to the next scheduled date for allotment of funds identified in paragraph (j), or to a mutually agreed upon substitute date. The notification will also advise the contracting officer of the estimated amount of additional funds that will be required for the timely performance of the item(s) funded, for a subsequent period as may be specified in the allotment schedule in paragraph (j) or otherwise agreed to by the parties. If after such notification additional funds are not allotted by the date identified in the Contractor's notification, or by an agreed substitute date, the contracting officer will terminate any item(s) for which additional funds have not been allotted, pursuant to the clause of this contract entitled “Termination for Convenience of the Government”.
(d) When additional funds are allotted for continued performance of the contract line item(s) identified in paragraph (a) above, the parties will agree as to the period of contract performance which will be covered by the funds. The provisions of paragraphs (b) through (d) will apply similarly to the additional allotted funds and agreed substitute date, and the contract will be modified accordingly.
(e) If, solely by reason of failure of the Government to allot additional funds, by the dates indicated below, in amounts sufficient for timely performance of the contract line item(s) identified in paragraph (a), the Contractor incurs additional costs or is delayed in the performance of the work under this contract and if additional funds are allotted, an equitable adjustment will be made in the price or prices (including appropriate target, billing, and ceiling prices where applicable) of the item(s), or in the time of delivery, or both. Failure to agree to any such equitable adjustment hereunder will be a dispute concerning a question of fact within the meaning of the clause entitled “Disputes.”
(f) The Government may at any time prior to termination allot additional funds for the performance of the contract line item(s) identified in paragraph (a) above.
(g) The termination provisions do not limit the rights of the Government under the clauses entitled “Default” and “Termination for Cause”. The provisions are limited to the work and allotment of funds for the contract line item(s) set forth in paragraph (a) above. These terms no longer apply once the contract is fully funded except with regard to the rights or obligations of the parties concerning equitable adjustments negotiated under paragraphs (e) and (f) above.
(h) Nothing herein affects the right of the Government to terminate this contract pursuant to the clause of this contract entitled “Termination for Convenience of the Government”.
(i) Nothing herein shall be construed as authorization of voluntary services whose acceptance is otherwise prohibited under 31 U.S.C. 1342.
(j) The parties agree that the Government will allot funds to this contract in accordance with the following schedule:
On execution of contract $
(month) (day), (year) $
(month) (day), (year) $
(month) (day), (year) $
(End of Clause)
As prescribed in AGAR 436.570, the following clause shall be used in Forest Service Integrated Resource Service Contracts (IRSCs), and is optional for non-IRSCs:
Emergency Response, Fire Suppression and Liability (Month Year)
(a) Contractor's Responsibility for Responding to Emergencies. When directed by the contracting officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to firefighting). This is considered to be within the general scope of the contract. An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-4.
(b) Contractor's Responsibility for Fire Fighting. The Contractor, under the provisions of FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work. The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor's agents, subcontractors, or employees subject to the fire classifications listed in paragraph (c).
(c) Fire Suppression Costs. The Contractor's obligations for cost of fire suppression vary according to three classifications of fires as follows:
(1) Operations Fire. An “operations fire” is a fire caused by the Contractor's operations other than a negligent fire. The Contractor agrees to reimburse the Forest Service for such cost for each operations fire, subject to a maximum dollar amount of [Contracting Officer insert amount]. The cost of the Contractor's actions, supplies, and equipment expended or used on suppressing any such fire, or otherwise provided at the request of Forest Service, shall be credited toward such maximum. If the Contractor's actual cost exceeds the contractor's maximum obligation stated above, the Forest Service shall reimburse the contractor for the excess.
(2) Negligent Fire. A “negligent fire” is a fire caused by the negligence or fault of the Contractor's operations including, but not limited to, one caused by smoking by persons engaged in the Contractor's operations during the course of their employment, or during rest or lunch periods; or if the Contractor's failure to comply with requirements under this contract results in a fire starting or permits a fire to spread. Damages and the cost of suppressing negligent fires shall be borne by the Contractor.
(3) Other Fires on Contract Area. The Forest Service shall pay the Contractor, at firefighting rates common in the area or at prior agreed rates, for equipment or personnel furnished by the Contractor at the request of the Forest Service, on any fire on the contract area other than an operations fire or a negligent fire.
(d) Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.
(e) Performance by the Contractor. Where the Contractor's employees, agents, contractors, subcontractors, or their employees or agents perform the Contractor's operations in connection with fire responsibilities, the Contractor's obligations shall be the same as if performance was by the Contractor.
(f) State Law. The Contractor shall not be relieved by the terms of this contract of any liability to the United States for fire suppression costs recovered in an action based on State law, except for such costs resulting from operations fires. Amounts due to the Contractor for firefighting expenditures on operations fires shall not be withheld pending settlement of any such claim or action based on State law.
(End of Clause)
PARTS 453 THROUGH 469—[RESERVED]
SUBCHAPTER I—FOOD ASSISTANCE PROGRAMS
PART 470—COMMODITY ACQUISITIONS
470.000Authority: 5 U.S.C. 301 and 40 U.S.C. 486(c).
This part sets forth the policies, procedures and requirements governing the procurement of agricultural commodities by the Department of Agriculture for use:
(a) Under child nutrition programs such as the National School Lunch Program, The Emergency Food Assistance Program, Commodity Supplemental Food Program, Food Distribution Program on Indian Reservations, and any other domestic food assistance program.
(b) Under title II of the Food for Peace Act (7 U.S.C. 1721 et seq.), the Food for Progress Act of 1985, the McGovern-Dole International Food for Education and Child Nutrition Program, and any other international food assistance program.
The following definitions are applicable to this subpart:
Commingled product means grains, oilseeds, rice, pulses, other similar commodities and the products of such commodities, when such commodity or product is normally stored on a commingled basis in such a manner that the commodity or product produced in the United States cannot be readily distinguished from a commodity or product not produced in the United States.
Foreign Agriculture Service (FAS) means such agency located within the Department of Agriculture.
Free alongside ship (f.a.s.) (* * named port of shipment) means a term of sale where the seller fulfills its obligation to deliver when the goods have been placed alongside the vessel on the quay or in lighters at the named port of shipment. The buyer bears all costs and risks of loss of or damage to the goods from that moment.
Grantee organization means an organization which will receive commodities from the United States Agency for International Development under title II of the Food for Peace Act (7 U.S.C. 1721 et seq.) or from the Foreign Agricultural Service under the Food for Progress Act of 1985; the McGovern-Dole International Food for Education and Child Nutrition Program; and any other international food assistance program.
Ingredient means spices, vitamins, micronutrients, desiccants, and preservatives when added to an agricultural commodity product.
Last contract lay day means the last day specified in an ocean freight contract by which the carriage of goods must start for contract performance.
Lowest landed cost means with respect to an agricultural product acquired under this part, the lowest aggregate cost for the acquisition of such product and the shipment of such product to a foreign destination.
Multi-port or multi-trip voyage charter means the charter of an ocean carrier in which the carrier will stop at two or more ports to discharge cargo.
(a) Policy. USDA follows the policies and procedures set forth in the FAR as supplemented by the AGAR, in the procurement of agricultural commodities and products of agricultural commodities that are used in domestic and international food assistance and nutrition programs.
(b) Electronic submission. To the maximum extent possible, the use of electronic submission of solicitation- related documents shall be used with respect to the acquisition of agricultural commodities and related freight. However, to the extent that a solicitation allows for the submission in paper or hard copy format in addition to information in an electronic format and there is a discrepancy in such submissions, the information submitted in paper or hard copy format shall prevail unless the electronic submission states that a specific existing written term is superseded by the electronic submission.
(c) Freight. With respect to the acquisition of freight for the shipment of agricultural commodities and products of agricultural commodities, the provisions of the FAR, including part 47, shall be utilized as applicable and various types of services to be obtained may include multi-trip voyage charters.
(a) Products for use in international food assistance programs. As provided by 7 U.S.C. 1732(2) and 1736o-1(a) commodities and the products of agricultural commodities acquired for use in international feeding and development programs shall be products of United States origin. A product shall not be considered to be a product of the United States if it contains any ingredient that is not produced in the United States if that ingredient is:
(1) Produced in the United States; and
(2) Commercially available in the United States at fair and reasonable prices from domestic sources.
(b) Products for use in domestic food assistance programs. Commodities and the products of agricultural commodities acquired by USDA for use in domestic food assistance programs shall be a product of the United States, except as may otherwise be required by law, and shall be considered to be such a product if it is grown, processed, and otherwise prepared for sale or distribution exclusively in the United States except with respect to ingredients as defined above. Ingredients from non- domestic sources will be allowed to be utilized as a United States product if such ingredients are not otherwise:
(1) Produced in the United States; and
(2) Commercially available in the United States at fair and reasonable prices from domestic sources.
(c) Commingled product. (1) Except as provided in paragraph (c)(2) of this section, a commingled product shall be considered to be a product of the United States if the offeror can establish that the offeror has in inventory at the time the contract for the commodity or product is awarded to the offeror, or obtains during the contract performance period specified in the solicitation, or a combination thereof, a sufficient quantity of the commodity or product that was produced in the United States to fulfill the contract being awarded, and all unfulfilled contracts that the offeror entered into to provide such commingled product to the United States.
(2) To the extent USDA has determined a commodity is one that is generally commingled but is also one which can be readily stored on an identity preserved basis with respect to its country of origin, USDA may require that the commodity procured shall be of 100 percent United States origin.
(d) Product derived from animals. With respect to the procurement of products derived from animals, the solicitation will set forth any specific requirement that is applicable to the country in which the animal was bred, raised, slaughtered or further processed.
(a) Lowest landed cost and delivery considerations. (1) Except as provided in paragraphs (a)(3) and (4) of this section, in contracts for FAS for commodities and related freight shipment for delivery to foreign destinations, the contracting officer shall consider the lowest landed cost of delivering the commodity to the intended destination. This lowest landed cost determination will be calculated on the basis of rates and service for that portion of the commodities being purchased that is determined is necessary and practicable to meet cargo preference requirements and on an overall (foreign and U.S. flag) basis for the remaining portion of the commodities being procured and the additional factors set forth in this section. Accordingly, the solicitations issued with respect to a commodity procurement, or a related freight procurement will specify that in the event an offer submitted by a party is the lowest offered price, the contracting officer reserves the right to reject such offer if the acceptance of another offer for the commodity or related freight, when combined with other offers for commodities or related freight, results in a lower landed cost.
(2) USDA may contact any port prior to award to determine the port's cargo handling capabilities, including the adequacy of the port to receive, accumulate, handle, store, and protect the cargo. Factors considered in this determination may include, but not be limited to: The adequacy of building structures, proper ventilation, freedom from insects and rodents, cleanliness, and overall good housekeeping and warehousing practices. USDA may consider the use of another coastal range or port if a situation exists at a port that may adversely affect the ability of USDA to have the commodity delivered in a safe and timely manner. Such situations include:
(i) A port is congested;
(ii) Port facilities are overloaded;
(iii) A vessel would not be able to dock and load cargo without delay;
(iv) Labor disputes or lack of labor may prohibit the loading of the cargo onboard a vessel in a timely manner; or
(v) Other similar situation that may adversely affect the ability of USDA to have the commodity delivered in a timely manner.
(3) Use of other than lowest landed cost. In order to ensure that commodities are delivered in a timely fashion to foreign destinations and without damage, the contracting officer may award an acquisition without regard to the lowest land cost process set forth in paragraph (a)(1) of this section if:
(i) The solicitation specifies that the lowest land cost process will not be followed in the completion of the contract; or
(ii) After issuance of the solicitation, it is determined that:
(A) Internal strife at the foreign destination or urgent humanitarian conditions threatens the lives of persons at the foreign destination;
(B) A specific port's cargo handling capabilities (including the adequacy of the port to receive, accumulate, handle, store, and protect commodities) and other similar factors may adversely affect the delivery of such commodities through damage or untimely delivery. Such similar factors include, but are not limited to: Port congestion; overloaded facilities at the port; vessels not being able to dock and load cargo without delay due to conditions at the port; labor disputes or lack of labor may prohibit the loading of the cargo onboard a vessel in a timely manner; and the existence of inadequate or unsanitary warehouse and other supporting facilities;
(C) The total transit time of a carrier, as it relates to a final delivery date at the foreign destination may impair the timely delivery of the commodity;
(D) Other similar situations arise that materially affect the administration of the program for which the commodity or freight is being procured; or
(E) The contracting officer determines that extenuating circumstances preclude awards on the basis of lowest-landed cost, or that efficiency and cost-savings justify use of types of ocean service that would not involve an analysis of freight. However, in all such cases, commodities would be transported in compliance with cargo preference requirements. Other types of services may include, but are not limited to, multi-trip voyage charters, indefinite delivery/indefinite quantity (IDIQ), delivery cost and freight (C & F), delivery cost insurance and freight (CIF), and indexed ocean freight costs.
(4) If the contracting officer determines that action may be appropriate under paragraph (a)(3) of this section, prior to the acceptance of any applicable offer, the contracting officer will provide to the Head of Contracting Activity or Designee a written request to obtain commodities and freight in a manner other than on a lowest landed cost basis consistent with title 48 of the CFR. This request shall include a statement of the reasons for not using lowest landed cost basis. The HCA, or the designee one level above the contracting officer, may either accept or reject this request and shall document this determination.
(b) Multiple offers or delivery points. If more than one offer for the sale of commodities is received or more than one delivery point has been designated in such offers, in order to achieve a combination of a freight rate and commodity award that produces the lowest landed cost for the delivery of the commodity to the foreign destination, the contracting officer shall evaluate offers submitted on a delivery point by delivery point basis; however, consideration shall be given to prioritized ocean transport service in determining lowest landed cost.
(c) Freight shipping and rates. (1) In determining the lowest-landed cost, USDA shall use the freight rates offered in response to solicitations issued by USDA or, if applicable, the grantee organization.
(2) Freight rates offered must be submitted as specified in the solicitation issued by USDA or, if applicable, the grantee organization. Any such solicitation issued by a grantee organization must contain the following elements:
(i) If directed by USDA, include a closing time for the receipt of written freight offers and state that late written freight offers will not be considered;
(ii) Provide that freight offers are required to have a canceling date no later than the last contract lay day specified in the solicitation;
(iii) Provide the same deadline for receipt of written freight offers from both U.S. flag vessel and non-U.S. flag vessels; and
(iv) Be received and opened prior to any related offer for acquisition of commodities to be shipped.
(3) USDA may require organizations that will receive commodities from USDA to submit information relating to the capacity of a U.S. port, or, if applicable, a terminal, prior to the acquisition of such commodities or freight.
(d) Freight rate notification. If USDA is not the party procuring freight with respect to a shipment of an agricultural commodity for delivery to a foreign destination, the organization that will receive commodities from USDA, or its shipping agent, shall be notified by USDA of the vessel freight rate used in determining the commodity contract award and the organization will be responsible for finalizing the charter or booking contract with the vessel representing the freight rate.
(a) Lowest landed cost and delivery considerations. (1) Except as provided in paragraphs (a)(3) and (e)(2) of this section, with respect to the acquisition of agricultural commodities for delivery to foreign destinations and related freight to transport such commodities under title II of Public Law 83-480, contracts will be entered into in a manner that will result in the lowest landed cost of such commodity delivery to the intended destination. This lowest landed cost determination shall be calculated on the basis of rates and service for that portion of the commodities being purchased that is determined is necessary and practicable to meet cargo preference requirements and on an overall (foreign and U.S. flag) basis for the remaining portion of the commodities being procured and the additional factors set forth in this section. Accordingly, the solicitations issued with respect to a commodity procurement, or a freight procurement will specify that in the event an offer submitted by a party is the lowest offered price, the contracting officer reserves the right to reject such offer if the acceptance of another offer for the commodity or freight, when combined with other offers for commodities or freight, results in a lower landed cost.
(2) USDA may contact any port prior to award to determine the port's cargo handling capabilities, including the adequacy of the port to receive, accumulate, handle, store, and protect the cargo. Factors which will be considered in this determination will include, but not be limited to, the adequacy of building structures, proper ventilation, freedom from insects and rodents, cleanliness, and overall good housekeeping and warehousing practices. USDA may consider the use of another coastal range or port if a situation exists at a port that may adversely affect the ability of USDA to have the commodity delivered in a safe and/or timely manner. Such situations include:
(i) A port is congested;
(ii) Port facilities are overloaded;
(iii) A vessel would not be able to dock and load cargo without delay;
(iv) Labor disputes or lack of labor may prohibit the loading of the cargo onboard a vessel in a timely manner; or
(v) Other similar situation that may adversely affect the ability of the Department to have the commodity delivered in a timely manner.
(3) In order to ensure that commodities are delivered in a timely fashion to foreign destinations and without damage, USDA may complete an acquisition without regard to the lowest land cost process set forth in paragraph (a)(1) of this section, if:
(i) The solicitation specifies that the lowest land cost process will not be followed in the completion of the contract; or
(ii) After issuance of the solicitation, it is determined that:
(A) Internal strife at the foreign destination or urgent humanitarian conditions threatens the lives of persons at the foreign destination;
(B) A specific port's cargo handling capabilities (including the adequacy of the port to receive, accumulate, handle, store, and protect commodities) and other similar factors will adversely affect the delivery of such commodities without damage or in a timely manner. Such similar factors include, but are not limited to: Port congestion; overloaded facilities at the port; vessels would not be able to dock and load cargo without delay; labor disputes or lack of labor may prohibit the loading of the cargo onboard a vessel in a timely manner; and the existence of inadequate or unsanitary warehouse and other supporting facilities;
(C) The total transit time of a carrier, as it relates to a final delivery date at the foreign destination may impair the ability of USDA to achieve timely delivery of the commodity; or
(D) Other similar situations arise that materially affect the administration of the program for which the commodity or freight is being procured.
(4) If the contracting officer determines that action may be appropriate under paragraph (a)(3) of this section, prior to the acceptance of any applicable offer, the contracting officer shall provide to the HCA or Designee and to USAID, a written request to obtain commodities and freight in a manner other than on a lowest landed cost basis. This request shall include a statement of the reasons for not using lowest landed cost basis. The HCA or Designee one level above the contracting officer, with the concurrence of USAID, shall, on an expedited basis, either accept or reject this request and shall document this determination in writing and provide a copy to USAID.
(b) Freight shipping and rates. (1) In determining lowest-landed cost as specified in paragraph (a) of this section, USDA shall use vessel rates offered in response to solicitations issued by USAID or grantee organizations receiving commodities under 7 U.S.C. 1721 et seq.
(2) USAID may require, or direct a grantee organization to require, an ocean carrier to submit offers electronically through a Web-based system maintained by USDA. If electronic submissions are required, USDA may, at its discretion, accept corrections to such submissions that are submitted in a written form other than by use of such Web-based system.
(c) Delivery date. The contracting officer shall consider total transit time, as it relates to a final delivery date, in order to satisfy program requirements for title II of Public Law 83-480.
(d) Multiple awards or delivery points. (1) If more than one offer for the sale of commodities is received or more than one delivery point has been designated in such offers, in order to achieve a combination of a freight rate and commodity award that produces the lowest landed cost for the delivery of the commodity to the foreign destination, the contracting officer shall evaluate offers submitted on a delivery point by delivery point basis; however, consideration shall be given to prioritized ocean transport service in determining lowest landed cost.
(2) The contracting officer may determine that extenuating circumstances preclude awards on the basis of lowest landed cost. However, in all such cases, commodities may be transported in compliance with cargo preference requirements as determined by USAID.
(3) The contracting officer shall notify USAID or, if applicable, the grantee organization, that its shipping agent will be notified of the vessel freight rate used in determining the commodity contract award. The grantee organization or USAID will be responsible for finalizing the charter or booking contract with the vessel representing the freight rate so used.
An agency having responsibility under this subpart shall administer its programs, with respect to this subpart, in accordance with regulations prescribed by the Secretary of Transportation.
PARTS 471 THROUGH 499—[RESERVED]
Donald Baker,
Senior Procurement Executive (SPE), Director, Office of Contracting and Procurement.
[FR Doc. 2024-15329 Filed 7-25-24; 8:45 am]