M. B. Kahn Construction Co., Inc.Download PDFNational Labor Relations Board - Board DecisionsMay 29, 1974210 N.L.R.B. 1050 (N.L.R.B. 1974) Copy Citation 1050 DECISIONS OF NATIONAL LABOR RELATIONS BOARD M. B. Kahn Construction Co., Inc. and Carpenters District Council of Washington, D.C. and Vicinity, United Brotherhood of Carpenters and Joiners of America, AFL-CIO, Petitioner and Laborers District Council of Washington, D.C. and Vicinity, affiliated with Laborers International Union of North America, AFL-CIO, Petitioner. Cases 5-RC-8792 and 5-RC-8801 May 29, 1974 DECISION ON REVIEW AND ORDER On January 28, 1974, the Regional Director for Region 5 issued his Decision and Direction of Elections in the above-entitled proceeding in which he directed elections in separate units of carpenters and laborers, respectively, employed by the Employ- er at its Winchester, Virginia, project. In his Decision, the Regional Director denied the Employ- er's request to dismiss the petitions because of the imminent reduction in the employee complement and cessation of these operations. Thereafter, the Employer, in accordance with the National Labor Relations Board's Rules and Regulations, Series 8, as amended, filed a timely request for review of the Regional Director's Decision on the grounds, inter alia, that, in denying its motion to dismiss, he departed from officially reported Board precedent and made erroneous findings of fact. By telegraphic order, as amended, February 26, 1974, the National Labor Relations Board granted the request for review with respect to the issues concerning the alleged cessation of operations, denied it in all other respects, and stayed the elections pending decision on review. The Employer filed a brief on review. The Board has considered the entire record in this case with respect to the issues under review, including the Employer's brief on review, and finds no question affecting commerce exists herein con- cerning the representation of certain employees of the Employer within the meaning of Section 9(c)(1) and Section 2(6) and (7) of the Act, for the following reasons: The Employer contends that the Regional Director erred in finding that target dates for the reduction in the employee complement and the ultimate cessation of operations are not definite and that a substantial number of employees are now employed and will continue to work for some time. We agree. The Employer is engaged in the general construc- tion business . On or about April I, 1973, it entered into a contract for the construction of a plant for General Electric Company in Winchester, Virginia. The expected completion date of the entire project, when all employees of the Employer will be terminat- ed, was between June and July 1974. The first major phase of the work was to be completed by March 4, 1974, when General Electric scheduled the moving of production machinery into the plant; the second major phase was to be completed April 15, 1974, when General Electric is scheduled to begin prod- uction of lamps; final completion of the plant is expected in June 1974. With respect to the Carpenters unit, it was anticipated at the time of the hearing (December 13, 1973) that the complement of the 24 to 30 carpenters and 12 helpers then employed would be reduced on March 4 to approximately 10 carpenters and 5 or 6 helpers; and that, after April 15, there would be only 4 carpenters and 2 or 3 helpers employed. As to the Laborers unit, it was anticipated that the 30 to 40 employees working at the time of the hearing would be reduced on March 4 to 20 to 30, and further reduced on April 15 to 10 to 15. After June, the work force would be reduced to "practically nothing." At the hearing, the Employer's project manager stated that the March and April target dates are expected to be met and that, while certain areas of the project are behind schedule, the overall project is on schedule. This evidence has not been controvert- ed. Moreover, it appears that the employees involved were recruited from the Winchester area, that the Employer does not have any work, other than this project, in the area, and that it does not contemplate any in the future. On the basis of the foregoing, we find that, in view of the imminent completion of the construction project here involved, no useful purpose would be served by conducting elections in the units found appropriate. The Employer's motion to dismiss the petitions filed herein is hereby granted.' ' Our dissenting colleague suggests that we expedite cases such as this in an effort to serve employee interests However, this suggestion ignores the requirements of due process . Our colleague correctly notes that the "initial step of the review procedure consumed most of the time during which an election would ordinarily have been held " In this case, the Employer's request for review was timely filed, but Petitioners' statements in opposition were not due until February 19 The election , which had been scheduled for February 22, was postponed Statements in opposition were not filed, and on Friday, February 22, 3 days after these statements were due, the Board met and considered the request for review. We granted review on Monday, February 25, as amended on February 26, 1974, 4 working days after these statements were due Any ruling on the request for review before February 19, 1974, would have deprived the Petitioners of their right to file statements in opposition. Surely we cannot diminish the period of time afforded parties who wish to file statements in opposition to requests for review To do so, even in an effort to expedite cases, would effectively deprive parties of their right to due process. Our colleague asserts we beg the question when we state that evidence of the overall project being on schedule is not controverted He notes that in its brief mailed on March 7, 1974, the Employer did not attempt to confirm the actual occurrence of the initial complement reductions anticipated for March 4 We note, however, that the Petitioners had ample opportunity to inform us in their briefs of any failure 210 NLRB No. 166 M B. KAHN CONSTRUCTION CO., INC. 1051 ORDER It is hereby ordered that the petitions herein be, and they hereby are, dismissed. MEMBER FANNING, dissenting: On November 20 and 23, 1973, petitions were filed by the Carpenters and the Laborers, respectively, covering the employees of this Employer. On December 13, 1973, a hearing was conducted and on January 28, 1974, the Regional Director issued his Decision and Direction of Elections to be held in two units at a Winchester, Virginia, construction project -one of carpenters and one of laborers. The Employer requested Board review asking the Board to find the units inappropriate or, in any event, to dismiss the petitions, predicting completion of the project "by" June 1974, with the work force "after" June "reduced to practically nothing." This contention had been denied by the Regional Director inasmuch as the predictions of interim reductions outlined by the Employer for March and April of this year were based on "completing certain phases of construction in accordance with projected time targets." Noting that a substantial number of the approximately 36 to 42 carpenters and helpers and 30 to 40 laborers employed would continue to work "for some time," the Regional Director perceived no reason to deprive them of the opportunity to select a collective-bargaining representative "at this time." On February 25, 1974, by telegraphic order, amended February 26, the Board affirmed the ruling of the Regional Director on the appropriateness of the units, a Pyrrhic victory, for the Petitioners, however, in view of the subsequent action by my colleagues. Units of this sort are not uncommon in the construction industry. R. B. Butler, Inc., 160 NLRB 1595. My colleagues granted review of the Employer's second contention only, and now, 5 months after the petitions were filed and almost 3 months after an election could have been held, they are reversing the Regional Director and dismissing these petitions during perhaps the most critical period of this employment relationship. They are not reversing the Regional Director because of any erroneous unit determinations, but because they say, in effect, an election cannot be conducted in timely fashion to produce effective or worthwhile collective bargaining to meet the target date Petitioners' briefs were due on March 8, 1974, but none were filed Unlike the Regional Director, we find that the record as a whole provides convincing evidence that the target dates will be met Employer's project manager, Khalil, testified that although there had been a strike at the project it had no effect on the target dates originally contemplated Khalil also testified that obstacles such as bad weather, the energy crisis in diesel fuel , and material shortages could not affect the target dates of the project. Apparently, the Regional Director relied on Khalil's affirmative responses to a series of hypothetical questions concerning the in the time probably remaining in this employment relationship. This kind of "expertise," I think, is best left to the parties and hardly comports with the statutory mandate to encourage collective bargaining. I know of no statutory observation that no collective bargaining at all is better than limited collective bargaining, or that a collective-bargaining relation- ship must last for a certain period of time to be effective. Obviously, if the mechanics of running an election and certifying the results cannot be complet- ed before the employment relationship terminates, there is some argument for not investing time, money, and effort in futile action. But that is not the case here. Certainly, it was not when the Regional Director directed elections on January 28, 1974. When, at the December 13 hearing, the Employer predicted completion of unit work in June, based on a contract target date, 6 months of operations admittedly remained and no layoffs were anticipated for 3 months. The Employer thereafter filed a brief to the Regional Director and urged dismissal. The Regional Director denied this request in his January 28 decision, directing that elections be held within the customary 30 days. Approximately 4 months of postelection bargaining was then possible: March, April, May, and June. The Employer then requested Board review, which the Board majority granted on February 26, again, I point out, not because of unit problems. This initial step of the review procedure consumed most of the time during which an election would ordinarily have been held. It also consumed most of the period during which the Employer admitted that the units would be at maximum strength. When finally this process of Board review has been completed by decision, scarcely 2 months of bargain- ing time will remain-assuming the projected March and April layoffs have in fact occurred and the project is actually completed in June as the Employer predicted last December.2 Thus, in a case of this sort, which by its very nature should be expedited if employee interests are to be served, the standard review procedure can be used to build support for the dismissal result desired by the party requesting review. There are, of course, Board decisions-issued before the delegation of the initial decision function construction industry in general, such as, "Do strikes ever have an impact upon target dates " We prefer to rely on the evidence which relates to this particular project rather than that which related to hypothetical situations. 2 My colleagues ' statement that evidence on the target dates predicted at hearing "has not been controverted" begs the question Neither has there been any attempt to confirm the actual facts to the Board though 4 months have passed since the hearing The Employer's brief to the Board mailed on March 7, which was after the initial layoff predicted for March 4, makes no contention that target dates were then being met 1052 DECISIONS OF NATIONAL LABOR RELATIONS BOARD to Regional Directors-where the Board itself dismissed because an operation would close down "very shortly," or in a month, or 2 to 3 months. Without necessity for appeal, those Board decisions were, timewise, much closer to hearing, and were based on short-term predictions which the Employer made at the hearing.3 Often the period had passed when the decision issued. In this case I view the Employer's 6-month prediction as long term, compared with the predele- gation cases to which I have just referred. Inasmuch -as present procedures permit the period of even a long-term prediction to be consumed in litigation, I consider it unfair to dismiss when the Employer's prediction itself still has perhaps 2 months to run, and particularly so when the dismissal assumes -contrary to the Regional Director-that construc- tion target dates will be met like clockwork. With all due respect to my colleagues' due process conten- 3 Pride Manufacturing Company, 98 NLRB 445 , "shortly after date of hearing"; G H Swalley Logging Company, 91 NLRB 921, "within 30 days of hearing", Lamar-Rankin Company, 81 NLRB 222, at hearing employer predicted no employees a month later ; Weber Showcase and Fixture Company, 85 NLRB 1202 , "within 60 to 90 days" after hearing; General Motors Corporation (GMC Truck & Coach Division), 88 NLRB 119, a 3- month prediction at hearing of which less than 2 months remained at the time of Board decision ; Parsons Corporation, 86 NLRB 74, a 3-month prediction at hearing which showed drastic employment cuts already made; W P Fuller & Company, 122 NLRB 814 , a December 31 decision where the tions, the fact is that these employees, through their unions, filed petitions requesting an election in November 1973, and the Board is now telling them in May 1974 that there is not enough time left for collective bargaining. Whether the due process period started from the last day on which a request for review was due, is of no moment. What is of moment is the passage of time since February 26 when the amended telegram granting review was sent. The whole process of considering what is solely a question of time and progress on a construction job-time to bargain effectively-has been extended inordinately at this stage of review, and foiled one of the primary purposes of the statute. I find no basis for granting review here or for reversing the Regional Director. I would affirm the Regional Director with instructions to proceed with an election without further delay. Board said that the employer's work on the project "will be finished in January"; Clark Construction Company, Inc, 129 NLRB 1348, where project was 95 percent completed at hearing and employer predicted completion of "all" work on January 24, 1961, 8 days after the Board decision issued: Douglas Motors Corp., 128 NLRB 307, where "fundamental" nature of business would change in about 2 months from Board decision and only 25 percent of the work force employed at hearing would then remain An additional case where the prediction date had occurred a week before the Board's decision is Sparton Teleoptic Company, 81 NLRB 1228, cited by Employer Copy with citationCopy as parenthetical citation