United States v. Foster Construction

United States Court of Appeals, Fifth Circuit
Mar 6, 1972
456 F.2d 250 (5th Cir. 1972)

Summary

holding that the general contractor was entitled to withhold payment from the subcontractor for damages it incurred as a result of the subcontractor's delay

Summary of this case from U.S. v. Dick Corp.

Opinion

No. 71-2369. Summary Calendar.

Rule 18, 5 Cir.; See Isbell Enterprises, Inc. v. Citizens Casualty Co. of New York et al., 5 Cir. 1970, 431 F.2d 409, Part I.

March 6, 1972.

Henry L. Newell, Balboa, Canal Zone, for plaintiff-appellant.

W. J. Sheridan, Jr., Balboa Heights, Canal Zone, for defendants-appellees.

Appeal from the United States District Court for the Canal Zone.

Before BELL, DYER and CLARK, Circuit Judges.



In the district court Foster, the prime contractor, was held entitled to withhold from Federal, its subcontractor, provable overhead expenses incurred by Foster from project delay caused by Federal in excess of the amount of liquidated damages recovered by the Government against Foster. We affirm.

The amount of liquidated damages which the prime contract required be paid to the Government, as owner of the project, bears no absolute relationship to the amount of overhead expenses suffered by the prime contractor because of the subcontractor's failure to timely perform its obligations under the subcontract. Therefore, this amount does not govern, as between the latter parties, unless such liquidated damage amount was adopted by the prime and subcontractor as the measure of damages for any breach of their agreement. While the subcontract contained a clause providing that "in general" the parties would assume the correlative positions of the parties in the prime contract, it also contained a specific proviso that payments due the subcontractor would be subject to offset for reasonable claims arising out of performance of the subcontract work. Accordingly, Foster is entitled to withhold from payment to its subcontractor Federal provable damages which it has incurred under the subcontract.

Affirmed.


Summaries of

United States v. Foster Construction

United States Court of Appeals, Fifth Circuit
Mar 6, 1972
456 F.2d 250 (5th Cir. 1972)

holding that the general contractor was entitled to withhold payment from the subcontractor for damages it incurred as a result of the subcontractor's delay

Summary of this case from U.S. v. Dick Corp.

holding thatthe amount of liquidated damages in the prime contract did not govern the general contractor's claim against the subcontractor in the absence of language in the subcontract adopting the liquidated damages in the prime contract as the measure of damages for breach of the subcontract, even though the subcontract contained a clause providing that the parties generally would assume the correlative positions of the parties in the prime contract

Summary of this case from U.S. v. Dick Corp.
Case details for

United States v. Foster Construction

Case Details

Full title:THE UNITED STATES OF AMERICA FOR THE USE AND BENEFIT OF FEDERAL ROOFING…

Court:United States Court of Appeals, Fifth Circuit

Date published: Mar 6, 1972

Citations

456 F.2d 250 (5th Cir. 1972)

Citing Cases

U.S. v. Dick Corp.

Id. (quoting 40 U.S.C. § 3133(b)(1)).See also U.S. for Use and Benefit of Martin Steel Constructors, Inc. v.…

E B Specialties Co., Inc. v. Phillips

Here, there is no evidence upon which the trial court could have correctly decided that the damages suffered…