Summary
including as force majeure events those caused "by a strike, fire, war, civil disturbance, act of god; by federal, state, or municipal laws; by any rule, regulation, or order of a governmental agency; by inability to secure materials; or by any other cause or causes beyond reasonable control of the party "
Summary of this case from Point Energy Partners Permian, LLC v. MRC Permian Co.Opinion
NO. 03-12-00247-CV
02-27-2015
ON MOTION FOR REHEARING
FROM THE DISTRICT COURT OF TRAVIS COUNTY, 353RD JUDICIAL DISTRICT
NO. D-1-GN-08-003472, HONORABLE SCOTT H. JENKINS, JUDGE PRESIDING
MEMORANDUM OPINION
We grant the motion for rehearing filed by the Railroad Commission, withdraw our opinion and judgment dated August 29, 2014, and substitute the following in their place. We dismiss as moot the Commission's motion for en banc reconsideration.
This is an administrative appeal from a 2008 Railroad Commission final order cancelling an extension of time to plug inactive wells operated by appellant Roland Oil Company. The principal basis for the Commission's order was that Roland lacked a good-faith claim to operate the oil and gas lease on which the subject wells were located. The district court affirmed the Commission's order, and we will affirm that judgment.
Background
Since 1994, Roland has been the operator under the North Charlotte Field Unit Lease in Atascosa County, Texas. The Lease, identified by the Commission as Lease No. 03220, consists of 31 wells that had been drilled as early as the 1950s, some of which are inactive. Commission Rule 14 requires that "dry or inactive well[s]" be plugged either within one year after drilling operations cease or, in the case of "delinquent inactive wells," "immediately unless the well is restored to active operation." Former Commission Rule 14 also required that an inactive well more than twenty-five years old that had been inactive more than one year be tested to ensure that it posed no potential threat to natural resources before it is plugged. The tests used to satisfy this rule, which are called "H-15" and "H-5" in reference to the form submitted to the Commission to report the results, examine fluid level and mechanical integrity of production wells (H-15) and the pressure within injection wells (H-5). Failure to comply with these requirements, among others, can result in Commission action preventing an operator from producing under a lease.
In this context, "unit" or "unitization," simply described, refers to the consolidation or merger of the interests in multiple producing leases or wells located in a single formation of oil or gas. A primary legal consequence is that production and operation anywhere on the unit is treated as if they have taken place in all of the underlying leases within the unit. See Southeastern Pipe Line Co. v. Tichacek, 997 S.W.2d 166, 170 (Tex. 1999).
See 16 Tex. Admin. Code § 3.14(b)(2) (2008) (Railroad Commission, Plugging) (cited hereinafter as "Former 16 Tex. Admin. Code § 3.14"). We cite to the version of Rule 14 in effect during the underlying contested-case hearing, but note that the intervening amendments to the rule did not affect provisions at issue here. See 29 Tex. Reg. 8271 (2004), proposed 29 Tex. Reg. 5994, 6003-04 (2004), amended by 32 Tex. Reg. 287 (2007), proposed 31 Tex. Reg. 9175, 9176 (2006). The current version of this rule was promulgated in 2012, see 37 Tex. Reg. 4892 (2012), proposed 37 Tex. Reg. 2287, 2288-89 (2012), but some version of Commission Rule 14 has been in effect since 1967, see Tex. R.R. Comm'n, Rule 051.02.02.014 (1967), adopted by Docket No. 20-65-5518.
See Former 16 Tex. Admin. Code § 3.14(b)(2)-(3).
See id. § 3.14(b)(2)(A)(iv).
In early 2005, Roland asked the Commission for an extension of time to complete the required testing on certain inactive wells on the Lease. Upon inspecting the Lease and reviewing its history, the Commission determined that Roland had been delinquent on the required testing since 1994 and found additional violations. As a consequence, the Commission denied Roland's extension request and issued a February 2005 "severance" order effectively barring Roland from producing from any well on the Lease. Roland ceased production as of May 2005, and would not resume until August 2006—an interruption of approximately fifteen consecutive months—after Roland completed certain repairs necessary for the testing and the required testing itself to the Commission's satisfaction, and the agency lifted its severance order.
Meanwhile, in June 2006, a mineral owner under the Lease had alerted the Commission to his contention that the Lease had lapsed during the period of non-production. This contention potentially implicated Roland's entitlement to an extension of time from the Commission to complete the required testing and plugging measures on the inactive wells (and, in turn, Roland's ability to avoid the consequences of noncompliance), as the Commission's rules allowed the agency to grant such an extension only if, among other requirements, the "operator has, and upon request provides evidence of, a good faith claim to a continuing right to operate the well." A "good faith claim" in this context is "a factually supported claim based on a recognized legal theory to a continuing possessory right in a mineral estate, such as evidence of a currently valid oil and gas lease or a recorded deed conveying a fee interest in the mineral estate."
Id. § 3.14(b)(2)(A)(iii) (unbonded operators), (B)(ii) (bonded operators); see Magnolia Petroleum Co. v. Railroad Comm'n, 170 S.W.2d 189, 190-91 (Tex. 1943). (recognizing need for permit applicant to make "a reasonably satisfactory showing of a good-faith claim of ownership" in the property to Commission).
Former 16 Tex. Admin. Code § 3.14(a)(1)(E). It should be emphasized that the Commission's determination regarding the good-faith-claim requirement bears upon its authority to grant oil and gas permits under the conservation laws, but does not determine or affirmatively create title or a right of possession in the property itself. See Magnolia, 170 S.W.2d at 190-91. Likewise, our decision here addresses only the correctness of the Commission's actions, not any underlying property rights.
Commission staff notified Roland of the mineral owner's assertion and asked Roland to provide evidence of its good-faith claim to operate the North Charlotte Field Unit Lease, adding that failure to do so would result in cancellation of Roland's plugging extension, which in turn would require immediate plugging of the Lease's inactive wells. In response, Roland asserted (and the Commission does not dispute) that the relevant instrument in this regard is a 1962 "Unit Agreement" whose term is "for the time that [oil and gas] are produced in paying quantities and as long thereafter as Unit Operations are conducted without a cessation of more than ninety (90) consecutive days." Although Roland did not dispute that production had ceased during the time period the Commission's severance order was in effect, Roland denied that the Unit Agreement had lapsed, urging that the Commission's severance order had triggered the agreement's force majeure clause and suspended its obligation to conduct "Unit Operations" and, in the alternative, arguing that its repair and testing activities constituted "Unit Operations."
See Former 16 Tex. Admin. Code § 3.14(b)(2)(A)(iii) (allowing Commission to grant an extension of the deadline for plugging if, among other requirements, the operator submits "a statement that the operator has, and on request will provide, evidence of a good-faith claim to a continuing right to operate the well").
There were actually two unit agreements, one signed by the working interest owners, the other by the royalty interest owners, but the parties agree that the material terms of each instrument are identical.
As will be discussed in more detail below, the agreement defines "Unit Operations" as "all operations conducted . . . pursuant to this agreement . . . for or on account of the development and operation of the [underlying formation] for the production of [oil and gas]."
For reasons that are not specifically expressed in the record, but presumably based on the conclusion that Roland did not have a good-faith claim to operate the Lease, the Commission staff rejected Roland's arguments and recommended that the plugging extensions be cancelled. In response, Roland sought and was granted a contested-case hearing on the issue. At the conclusion of the contested-case hearing, the hearing examiner issued a proposal for decision recommending that the Commission conclude Roland lacked a good-faith claim to operate the Lease and that the plugging extensions be cancelled. Specifically, the hearing examiner concluded that because Roland had not produced any oil or gas or conducted Unit Operations for more than 90 days between May 2005 and August 2006, Roland lacked a good-faith claim to operate the Lease. Ultimately, the Commission issued a final order adopting the hearing examiner's findings of fact and conclusions of law and cancelling the extensions.
See Former 16 Tex. Admin. Code § 3.14(b)(2)(C)(ii) ("If the Commissioner or its delegate declines to grant or continue a plugging extension or revokes a previously granted extension, the operator shall either return the well to active operation or, within 30 days, plug the well or request a hearing on the matter.").
After exhausting its remaining remedies before the Commission, Roland filed a suit for judicial review of the Commission's final order in Travis County District Court. The district court affirmed the Commission's final order. Roland appeals that judgment.
Analysis
Roland brings two issues on appeal, both of which ultimately challenge the Commission's construction of the Unit Agreement and its resulting conclusion that Roland had not demonstrated a good-faith claim to operate the North Charlotte Field Unit lease. First, Roland argues that under the plain language of the Unit Agreement, the Commission's February 22, 2006 severance order was "an order of a governmental body" that excused the period of non-production under the agreement's force majeure provision. Second, Roland contends that the plain language of the Unit Agreement provides that the testing and repairs Roland undertook during the cessation of production constitute "Unit Operations" that served to continue the term of the agreement.
Standard of review
The parties agree that our review of the Commission's final order is governed by the "substantial evidence" standard codified in the Administrative Procedure Act. This standard requires that we reverse or remand a case for further proceedings "if substantial rights of the appellant have been prejudiced because the administrative findings, inferences, conclusions, or decisions" are:
See Tex. Gov't Code § 2001.174 (codifying "substantial evidence" standard); Railroad Comm'n v. Torch Operating Co., 912 S.W.2d 790, 792 (Tex. 1995) (applying APA substantial-evidence standard to Commission decision under Texas Natural Resources Code).
(A) in violation of a constitutional or statutory provision;
(B) in excess of the agency's statutory authority;
(C) made through unlawful procedure;
(D) affected by other error of law;
(E) not reasonably supported by substantial evidence considering the reliable and probative evidence in the record as a whole; or
(F) arbitrary or capricious or characterized by abuse of discretion or clearly unwarranted exercise of discretion.In reviewing fact-based determinations under this standard, we simply ask whether, considering "the reliable and probative evidence in the record as a whole," some reasonable basis exists in the record for the agency's action. We apply this analysis without deference to the district court's judgment. We presume that the agency's findings, inferences, conclusions, and decisions are supported by substantial evidence, and the burden is on the contestant to demonstrate otherwise.
Tex. Gov't Code §2001.174(2).
See id. § 2001.174(2)(E); Texas Indus. Energy Consumers v. CenterPoint Energy Houston Elec., LLC, 324 S.W.3d 95, 105 (Tex. 2010) (citing Mireles v. Texas Dep't of Pub. Safety, 9 S.W.3d 128, 131 (Tex. 1999) ("A court applying the substantial evidence standard of review may not substitute its judgment for that of the agency. The issue for the reviewing court is not whether the agency's decision was correct, but only whether the record demonstrates some reasonable basis for the agency's action. Courts must affirm administrative findings in contested cases if there is more than a scintilla of evidence to support them.") (citations omitted)); Public Util. Comm'n v. Gulf States Utils. Co., 809 S.W.2d 201, 210-11 (Tex. 1991); Texas Health Facilities Comm'n v. Charter Med.-Dallas, Inc., 665 S.W.2d 446, 452-53 (Tex. 1984).
See Texas Dep't of Pub. Safety v. Alford, 209 S.W.3d 101, 103 (Tex. 2006) (per curiam).
See Slay v. Texas Comm'n on Envtl. Quality, 351 S.W.3d 532, 549 (Tex. App.—Austin 2011, pet. denied).
To the extent that the issues presented here turn on the construction of the Unit Agreement, the interpretation of an unambiguous contract is a question of law that we review de novo. As such, we are not bound by the Commission's interpretation of an unambiguous contract. When construing a written contract, we "ascertain the intent of the parties as expressed in the instrument," giving the language in the agreement "its plain, ordinary, and generally accepted meaning," unless doing so "would defeat the parties' intent." If a contract is ambiguous, its interpretation is a matter for the fact finder. Such findings of fact would be reviewed in the same manner as other agency fact findings, that is for support by substantial evidence.
See, e.g., Coker v. Coker, 650 S.W.2d 391, 393 (Tex. 1983) (if contract is unambiguous, court will construe contract as question of law).
See Texas Workers' Comp. Ins. Facility v. State Bd. of Ins., 894 S.W.2d 49, 52 (Tex. App.—Austin 1995, no writ).
See Coker, 650 S.W.2d at 393.
See DeWitt Cnty. Elec. Coop., Inc. v. Parks, 1 S.W.3d 96, 101 (Tex. 1999).
See Coker, 650 S.W.2d at 394.
See Tex. Gov't Code § 2001.174; Charter Med.-Dallas, 665 S.W.2d at 452-53.
Commission's decision
The Commission's decision to deny Roland's plugging extension for failure to demonstrate "a good faith claim to a continuing right to operate" the Lease was based principally on its underlying findings of fact that (1) Roland produced no hydrocarbons from the Unit and conducted no Unit Operations on the Unit from May 2005 through July 2006 (a period of 15 consecutive months), and (2) the Unit Agreement provides that it terminates if there is a cessation in the production of hydrocarbons or Unit Operations of more than 90 days. In reaching its ultimate conclusion, the Commission also necessarily rejected Roland's argument that the Unit Agreement's force majeure provision excused the gap in hydrocarbon production. That rejection was based on the Commission's legal conclusion that force majeure provisions apply only when the force majeure event relied on is beyond the reasonable control of the operator and, in turn, on its related finding of fact that the Commission issued the severance order in this case due to long-overdue testing on six inactive wells, but that it had been within the reasonable control of Roland to stay current on that regulatorily-required testing. The Commission also necessarily rejected Roland's argument that the repairs and testing it performed on the Lease's inactive wells during the gap in production constituted Unit Operations such that there was no cessation in those operations to trigger termination of the Unit Agreement. The Commission, concluding that "operations" requires work directed at actually producing oil or gas, found that the work Roland performed on inactive wells during the 15-month gap did not contribute to the production of hydrocarbons.
Force majeure
In its first issue, Roland challenges the Commission's general legal conclusion that force majeure provisions apply only where the force majeure event being relied upon is beyond the reasonable control of the party invoking the provision. Roland counters that, despite the Commission's apparent conclusion to the contrary, there is no general rule regarding the applicability of force majeure clauses; instead, their scope and application, like every contract provision, depend on the specific language used in the contract. The language used in the Unit agreement, Roland urges, provides that its obligations are excused if a "rule, regulation, or order of a governmental agency" prevents compliance. Thus, Roland concludes, because there is no question that the Commission's 2005 order of severance was an "order of a governmental agency" that required Roland to stop production, the cessation in production that might otherwise serve to default the lease was excused. In sum, Roland contends that the Commission abused its discretion by improperly construing and interpreting the force majeure provision of the Unit agreement.
Roland cites to Sun Operating Ltd. P'ship v. Holt, 984 S.W.2d 277, 282-83 (Tex. App.—Amarillo 1998, pet. denied) ("Force majeure[] is now little more than a descriptive phrase without much inherent substance. Indeed, its scope and application, for the most part, is utterly dependent upon the terms of the contract in which it appears.") and Hydrocarbon Mgmt., Inc. v. Tracker Exploration, Inc., 861 S.W.2d 427, 436 (Tex. App.—Amarillo 1993, no writ) ("We note initially that the lease terms are controlling regarding force majeure, and common law rules merely fill in gaps left by the lease.") to support this assertion.
See Tex. Gov't Code § 2001.174(F) (requiring reviewing court to reverse agency decision that is "arbitrary or capricious or characterized by abuse of discretion or clearly unwarranted exercise of discretion").
Although we agree with Roland that the scope and effect of a force majeure clause depend ultimately on the specific language used in the contract and not on any traditional definition of the term, the specific language of the Unit Agreement's force majeure provision incorporates the common-law force majeure requirement that performance become impossible or impracticable as a result of an event or effect that the parties could not have anticipated or controlled:
See Virginia Power Energy Mktg., Inc. v. Apache Corp., 297 S.W.3d 397, 402 (Tex. App.—Houston [14th Dist.] 2009, pet. denied) (citing Zurich Am. Ins. Co. v. Hunt Petroleum (AEC), Inc., 157 S.W.3d 462, 466 (Tex. App.—Houston [14th Dist.] 2004, no pet.); Perlman v. Pioneer Ltd. P'ship, 918 F.2d 1244, 1248 n. 5 (5th Cir. 1990)).
See Black's Law Dictionary 761 (10th ed. 2014) (defining "force majeure" and "force majeure clause"); 30 Samuel Williston & Richard A. Lord, A Treatise on the Law of Contracts § 77:31 (4th ed. 1990 & Supp. 2004) (specific language of clause indicates what events will excuse performance and typical clause states that party's performance is subject to "acts of God, war, government regulation, terrorism, disaster, strikes . . . civil disorder, curtailment of transportation facilities, or any other emergency beyond the parties' control").
FORCE MAJEURE
16.1 Force Majeure. All obligations imposed by this agreement on each party, except for the payment of money, shall be suspended while compliance is prevented, in whole or in part, by a strike, fire, war, civil disturbance, act of god; by federal, state, or municipal laws; by any rule, regulation, or order of a governmental agency; by inability to secure materials; or by any other cause or causes beyond reasonable
control of the party. No party shall be required against its will to adjust or settle any labor dispute. Neither this agreement nor any lease or other instrument subject hereto shall be terminated by reason of suspension of Unit Operations due to any one or more of the causes set forth in this Article.(Emphasis added.) Not only does this provision use the phrase "force majeure" twice in identifying and describing itself, it also incorporates the force majeure concept that the event be beyond control by giving a list of specific events and then including "other" of those type events that are "beyond reasonable control of the party."
Considering the Unit Agreement as a whole and taking its words in context, we conclude that the force majeure clause at issue here is subject to only one reasonable interpretation, which is that any potential triggering event of the clause must be beyond the control of the party. In so concluding, we rely on the language used in the clause itself—specifically, the adjective "other" modifying "causes or causes beyond the control of the party." In this context, "other" means "additional" or "remaining" of a group or type not already mentioned. As such, the phrase "other cause or causes beyond the control of the party" indicates the last of a group of like or similar things, with the similarity or commonality being events that are beyond a person's control. That "group" of like or similar things that are beyond a person's ability to control consists of the traditional force majeure events specifically described in the clause: "strike, fire, war, civil disturbance, act of god"; "federal, state, or municipal laws"; "any rule, regulation, or order of a governmental agency"; and "inability to secure materials."
See Coker, 650 S.W.2d at 394 (noting among other contract-interpretation considerations that we examine entire writing and an ambiguity does not exist unless the meaning is "uncertain and doubtful or it is reasonably susceptible to more than one meaning." (emphasis added)).
See Webster's Third New Int'l Dictionary 1598 (2002) (defining "other" as including "remaining," "more," and "additional").
See State v. Fidelity & Deposit Co. of Md., 223 S.W.3d 309, 311-12 (Tex. 2007) (determining "other necessary structure related to a public road" in statute defining "highway" to include "public road or part of a public road or bridge, culvert, or other necessary structure related to a public road," did not include TxDOT research and technology center because that phrase directly related to preceding "bridge" and "culvert" and thus, "likewise pertains to the physical function of the road, such as a guard rail"); Toungate v. Bastrop Indep. Sch. Dist., 842 S.W.2d 823, 828 (Tex. App.—Austin 1992, no writ) (holding that "any other order" in statute restricted meaning to same class of orders described in provision).
Roland disagrees, arguing that each of the specific list of events in this clause stand alone and is not modified or described by the phrase "by any other cause or causes beyond the reasonable control of the party." Thus, it maintains, "any rule, regulation, or order of a governmental agency," is a force majeure event regardless of the underlying circumstances. But this is not a reasonable construction of the Unit Agreement's force majeure provision. Under Roland's interpretation, a fire that was directly controlled or caused by Roland would trigger the Unit Agreement's force majeure clause. Likewise, any inability to secure materials, including Roland's refusal to pay for materials, would trigger this clause. Further, and more directly relevant here, Roland's failure to obtain any State license could conceivably be offered as a force majeure event under Roland's interpretation regardless of the reason for the failure.
See, e.g., Reilly v. Rangers Mgmt., Inc., 727 S.W.2d 527, 530 (Tex. 1987) (noting that courts should "avoid when possible and proper a construction which is unreasonable"); Coker, 650 S.W.2d at 393 (noting that "contract is ambiguous when its meaning is uncertain and doubtful or it is reasonably susceptible to more than one meaning").
Finally, as suggested above, Roland's interpretation would require ignoring the existence of "other" in this provision. If the drafters of the agreement intended to excuse the specific events listed without regard to control, as Roland urges, but also excuse any event that was beyond the reasonable control of the party, then it was unnecessary to include the word "other"—e.g., All obligations shall be suspended while compliance is prevented by a strike, fire, war, civil disturbance, act of god; by any rule, regulation, or order of a governmental agency; or by any cause or causes beyond reasonable control of the party. By including "other," the drafters expressed, we conclude, a clear intent that the force majeure cause or causes relied on be beyond the reasonable control of the party. Accordingly, although the Commission's declaration regarding the scope of force majeure clauses may go too far, its ultimate decision that the Unit Agreement's force majeure clause was not triggered by the Commission's order of severance because it was within the reasonable control of Roland was correct on the record here, and we will not reverse a right decision even in the face of a wrong legal explanation. We overrule Roland's first issue.
See Sargent v. Highlite Broad. Co., 466 S.W.2d 866, 868 (Tex. Civ. App.—Austin 1971, no writ) ("'The terms of a contract must, if possible, be construed to mean something rather than nothing at all.'" (quoting Portland Gasoline Co. v. Superior Mktg. Co., 243 S.W.2d 823, 824 (Tex. 1951), overruled on other grounds, Northern Natural Gas Co. v. Conoco, Inc., 986 S.W.2d 603, 608 (Tex.1998))).
See, e.g., Sun Operating, 984 S.W.2d at 288 ("[I]n listing circumstances beyond the lessee's control last, the parties intended that the "cause[s], occurrence[s] or circumstance[s]" enumerated before it be outside the lessee's reasonable control before they could serve as force majeure."); Atkinson Gas Co. v. Albrecht, 878 S.W.2d 236, 241 (Tex. App.—Corpus Christi 1994, writ denied) (refusing to apply force majeure clause where Commission order well shut because lessee's failure to comply with regulations was within lessee's reasonable control).
See ICON Benefit Adm'rs II, L.P. v. Abbott, 409 S.W.3d 897, 903-04 (Tex. App.—Austin 2013, pet. denied) (citing Beck v. Law Offices of Edwin J. (Ted) Terry, Jr., P.C., 284 S.W.3d 416, 442 (Tex. App.—Austin 2009, no pet.)) (noting that a trial court does not abuse its discretion if it reaches the right result for the wrong reason).
"Unit operations"
In its second issue, Roland challenges the Commission's legal conclusion that "operations" means "actual work done in a good faith endeavor to cause a well to produce oil and/or gas in paying quantities" Specifically, Roland asserts that under a proper interpretation of the Unit Agreement, the work or operations that Roland performed on the Lease's inactive wells during the gap in production constitute "Unit Operations" that extended the term of the Lease, despite the gap in hydrocarbon production. In making this argument, Roland relies on two provisions of the Unit Agreement, the first of which specifies the duration of the agreement:
18.1 Term. The term of this agreement shall be for the time that Unitized Substances are produced in paying quantities and as long thereafter as Unit Operations are conducted without a cessation of more than ninety (90) consecutive days, unless sooner terminated by Working Interest Owners in the manner herein provided.(Emphasis added.) Focusing on the above-emphasized language, Roland contends that the term of the Unit Agreement is perpetuated not only by the production of oil and gas in paying quantities, but also by the continuation of "Unit Operations," which the agreement defines as follows:
1.15 Unit Operations means all operations conducted by Working Interest Owners or Unit Operator pursuant to this agreement and the Unit Operating Agreement for
or on account of the development and operation of the Unitized Formation for the production of Unitized Substances.During the gap in hydrocarbon production at issue here, Roland maintains, it conducted these "Unit Operations" by performing repairs and testing on the Lease's inactive wells as required by Commission Rule 3.14. Those repairs and tests are "Unit Operations," Roland contends, because they were, quite simply, "operations conducted by . . . the Unit Operator" pursuant to the agreement—i.e., the general work, including repairs and testing, that are performed to maintain the Lease. Therefore, Roland concludes, the term of the Lease continued under provision 18.1 because "Unit Operations [were] conducted without a cessation of more than 90 days."
The agreement defines "Unitized Substances" as "oil, gas, gaseous substances, sulphur contained in gas, condensate, distillate, and all associated and constituent liquid or liquefiable hydrocarbons."
Stated generally, the agreement defines "Unified Formation" as the specific geological formation located under the Unit from which oil, gas, etc. is drawn.
But Roland's proffered interpretation of "Unit Operations" is incomplete. Although broadly referring to "all operations conducted" by a working-interest owner or operator, the agreement's definition also requires that the operations be conducted "for or on account of the development and operation of the Unitized Formation for the production of Unitized Substances." In other words, the plain language of the agreement limits the scope of "Unit Operations" to those activities that are taken in connection with producing oil and gas. This limitation, or narrowing of the common meaning of "operations," is consistent with the specialized meaning of "operations" that has developed in oil and gas law, which is those activities conducted in a good faith effort to achieve production. Thus, for Roland's repairs and testing to be considered "Unit Operations" under the agreement, they must have been activities conducted in an effort to produce oil or gas. This closely matches the Commission's conclusion that "operations means actual work being done in a good faith endeavor to cause a well to produce oil and/or gas in paying quantities" and, as such, comports with both the Unit Agreement's definition of "Unit Operations" as wells as the technical or specialized meaning that "operations" has acquired in the oil and gas context. Accordingly, the Commission's legal conclusion regarding the meaning of "operations" was not in error.
See, e.g., Ramsey v. Grizzle, 313 S.W.3d 498, 510 (Tex. App.—Texarkana 2010, no pet.) ("Actual physical work being done on equipment in a good faith effort to place it in working order to produce oil constitutes sufficient operations to maintain the lease."); Hydrocarbon Mgmt., 861 S.W.2d at 438 (noting that "the intention of the parties was for the lessees to do something that would bring about the exploration and production of oil and gas" and that "lessee should not be allowed to maintain a lease without conducting activities that would cause the well to produce"); Cox v. Stowers, 786 S.W.2d 102, 105 (Tex. App.—Amarillo 1990, no writ) (concluding that term "reworking operations" means "good faith effort[s] to cause a well or wells to produce oil or gas in paying quantities"); Lab Oil Co. v. Bentz, 380 S.W.2d 846, 847 (Tex. Civ. App.—Corpus Christi 1964, no writ) ("The meaning of the word 'operations' in drafting the lease, unquestionably denoted to the parties the meaning of doing those things that would continue the quest for production.")
See Trinity Universal Ins. Co. v. Cowan, 945 S.W.2d 819, 823 (Tex. 1997) ("[W]hen terms are defined in a[ contract], those definitions control.").
See Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 662 (Tex. 2005) (noting acceptability of applying technical meaning to contract terms where appropriate (citing Heritage Res., Inc. v. NationsBank, 939 S.W.2d 118, 121 (Tex. 1996) (applying "well accepted meanings in oil and gas industry" to terms "royalty" and "market value at the well")).
See Tex. Gov't Code § 2001.174; Buddy Gregg Motor Homes, Inc. v. Motor Vehicle Bd., 156 S.W.3d 91, 98-99 (Tex. App.—Austin 2004, pet. denied) (noting that we review agency legal conclusions for errors of law).
In addition to challenging the Commission's interpretation of "operations," Roland suggests that the Commission's related underlying findings of fact, expressed as follows, are not supported by substantial evidence:
The relevant lease operations that Roland engaged in during the severance period between May, 2005 and August, 2006, were confined to those acts necessary to
pass Commission required H-15 and H-5 testing. The wells were inactive before the testing and inactive after the testing. They did not contribute to the development of the unitized formation for the production of oil and/or gas.We disagree.
The bulk of the "operations" evidence in the record relates to the work Roland performed in connection with efforts to comply with former Commission Rule 3.14, specifically the repairs and testing on the Lease's inactive wells in preparation for their being plugged. This evidence included specific information regarding the type of work or tests done, the inactive wells on which the work or tests were done, and when the work or tests were performed. While there is some evidence in the record of other work that Roland performed on the Lease—i.e., "constant" maintenance-oriented work, including flow-line repair, electrical repairs, pump repairs, monitoring for leaks, mowing the grass, and road inspections—that evidence does not specify when this work was done, how often it was done, or whether it was performed on any of the Lease's active wells. Regardless, under the applicable substantial-evidence standard of review, we ask only whether some reasonable basis exists in the record for the agency's action. That standard was met here.
See Charter Med., 665 S.W.2d at 453 (noting that test is whether some reasonable basis exists in the record for agency's action (citing Gerst v. Nixon, 411 S.W.2d 350, 354 (Tex. 1966)).
Roland, challenging the Commission's specific finding that its work during the gap did not contribute to the production of oil and gas, questions why it would bother to spend time and money conducting repairs and testing on inactive wells if not to eventually produce oil and gas. But for purposes of our review, the evidence in the record shows that the work in question was performed on inactive wells to comply with former Commission Rule 3.14, that it was done in preparation for plugging those inactive wells, and that those wells remained inactive after the required testing. Inactive wells do not produce oil or gas; moreover, inactive wells slated to be plugged do not and will not produce oil or gas. Accordingly, it was reasonable for the Commission to conclude that Roland's work did not actually contribute to the production of oil and gas, and thus did not constitute good-faith endeavors to produce oil and gas.
See, e.g., Tex. Nat. Res. Code § 89.002(12) (defining "inactive well" as "unplugged well that has had no reported production . . . for a period of greater than 12 months").
See, e.g., R.D. Oil Co. v. Railroad Comm'n, 849 S.W.2d 871, 872 (Tex. App.—Austin 1993, no writ) (describing plugging as pouring cement into the well casing); Railroad Comm'n, Well Plugging Primer 6-7 (200), available at http://www.rrc.state.tx.us/media/6358/plugprimer1.pdf (showing that operator plugs a well by pumping cement down it and, if done properly, seals the well, preventing water and other substances from leaking into it and gas or oil from leaking out).
See Texas Indus. Energy, 324 S.W.3d at 105; Gulf States Util., 809 S.W.2d at 211.
--------
We overrule Roland's second issue.
CONCLUSION
Having overruled Roland's issues, we affirm the district court's judgment affirming the Commission's order.
/s/_________
Jeff Rose, Chief Justice
Before Chief Justice Rose, Justices Puryear and Field Affirmed on Motion for Rehearing Filed: February 27, 2015