From Casetext: Smarter Legal Research

Pac. Coast Fed'n of Fishermen's Associations v. U.S. Dep't of the Interior

UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT
Mar 28, 2016
No. 14-15514 (9th Cir. Mar. 28, 2016)

Opinion

No. 14-15514

03-28-2016

PACIFIC COAST FEDERATION OF FISHERMEN'S ASSOCIATIONS; et al., Plaintiffs - Appellants, v. UNITED STATES DEPARTMENT OF THE INTERIOR; et al., Defendants - Appellees, and WESTLANDS WATER DISTRICT; et al., Intervenor-Defendants - Appellees.


NOT FOR PUBLICATION

D.C. No. 1:12-cv-01303-LJO-MJS MEMORANDUM Appeal from the United States District Court for the Eastern District of California
Lawrence J. O'Neill, District Judge, Presiding Argued and Submitted February 9, 2016 San Francisco, California Submission Withdrawn February 9, 2016 Resubmitted March 28, 2016 Before: SILVERMAN, FISHER, and TALLMAN, Circuit Judges.

This disposition is not appropriate for publication and is not precedent except as provided by 9th Cir. R. 36-3.

This case is resubmitted the date the memorandum is filed. --------

Pacific Coast Federation of Fishermen's Associations, Inc., and San Francisco Crab Boat Owners Association, Inc. ("plaintiffs") appeal the district court's partial dismissal and partial summary judgment of their action under the National Environmental Policy Act ("NEPA") against the United States Department of the Interior and the United States Bureau of Reclamation. We have jurisdiction under 28 U.S.C. § 1291. We affirm in part, reverse in part, and remand.

Prior to approving eight interim two-year contracts for the delivery of water from the Central Valley Project to California water districts, Reclamation issued an environmental assessment ("EA") and a finding of no significant impact ("FONSI"). Plaintiffs seek declaratory and injunctive relief on the basis of alleged violations of NEPA in (1) an inadequate EA and FONSI and (2) failure to prepare an environmental impact statement ("EIS") for the interim contracts. The district court dismissed plaintiffs' claims that an EIS was required and that the EA's "no action" alternative was deficient, and it granted summary judgment in favor of defendants on the remaining challenges to the EA.

Even though the two-year contracts expired on February 28, 2014, this appeal is not moot. The short duration and serial nature of Reclamation's interim water contracts place plaintiffs' claims within the mootness exception for disputes capable of repetition yet evading review. See A.D. ex rel. L.D. v. Haw. Dep't of Educ., 727 F.3d 911, 914 (9th Cir. 2013).

We review de novo a dismissal for failure to state a claim under Fed. R. Civ. P. 12(b)(6). Chubb Custom Ins. Co. v. Space Sys./Loral, Inc., 710 F.3d 946, 956 (9th Cir. 2013). We also review de novo the district court's ruling on summary judgment. San Luis & Delta-Mendota Water Auth. v. Jewell, 747 F.3d 581, 601 (9th Cir. 2014), cert. denied, 134 S. Ct. 948 & 950 (2015). Claims under NEPA are reviewed under the standards of the Administrative Procedure Act, which provides that an agency action must be upheld unless it is "'arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.'" Id. (quoting 5 U.S.C. § 706(2)(A)).

I. "No Action" Alternative

The EA's "no action" alternative complied with NEPA even though it assumed continued interim contract renewal. A "no action" alternative is "meaningless" if it assumes the existence of the very plan being proposed. Friends of Yosemite Valley v. Kempthorne, 520 F.3d 1024, 1038 (9th Cir. 2008). Nonetheless, when an agency action is mandatory, the "no action" alternative is properly defined as the carrying out of that action. Dep't of Transp. v. Pub. Citizen, 541 U.S. 752, 769 (2004) (holding that Federal Motor Carrier Safety Administration was not required to produce an EIS due to the environmental impact of an action it could not refuse to perform); Am. Rivers v. Fed. Energy Reg. Comm'n, 201 F.3d 1186, 1199-1201 (9th Cir. 1999) (holding that EIS for the Federal Energy Regulatory Commission's reissuance of licenses for continued operation of two hydroelectric power facilities properly identified the "no action" alternative as continued operation under the terms of the expired original licenses, as required by the Federal Power Act). The "no action" alternative may also be defined as the status quo; that is, no change from a current management direction, or the continuation of a historical practice or use. Ass'n of Pub. Agency Customers, Inc. v. Bonneville Power Admin., 126 F.3d 1158, 1188 (9th Cir. 1997) (holding that the EIS for the Bonneville Power Administration's renegotiation of long term power sales contracts properly defined the "no action" alternative as the status quo of continuing the existing contracts).

We do not agree with the district court that the Central Valley Project Improvement Act ("CVPIA"), a part of the Reclamation Projects Authorization and Adjustment Act of 1992, required Reclamation to enter into the interim contracts. The CVPIA requires "appropriate environmental review," including the preparation of a programmatic EIS ("PEIS"), before Reclamation is authorized to renew an existing long-term water service contract. CVPIA § 3404(c)(1). After the completion of the PEIS, Reclamation "shall, upon request, renew any existing long-term repayment or water service contract for the delivery of water from the Central Valley Project for a period of twenty-five years." Id. Prior to the completion of the PEIS, Reclamation "may" renew water service contracts for interim three- or two-year periods. Id. As the district court acknowledged, normally, when "may" and "shall" are used in the same statute, the "'inference is that each is being used in its ordinary sense—the one being permissive, the other mandatory.'" Ctr. for Biological Diversity v. U.S. Fish & Wildlife Serv., 450 F.3d 930, 935 (9th Cir. 2006) (quoting Haynes v. United States, 891 F.2d 235, 239-40 (9th Cir. 1989)) (interpreting Endangered Species Act).

Nonetheless,, the status quo was the historical use of Central Valley Project water by the water districts. See Ass'n of Pub. Agency Customers, Inc., 126 F.3d at 1188. The EA's "no action" alternative therefore complied with NEPA.

II. Statement of Purpose and Need

The EA's statement of purpose and need did not unreasonably narrow Reclamation's consideration of alternatives. See Alaska Survival v. Surface Transp. Bd., 705 F.3d 1073, 1084 (9th Cir. 2013). The statement did not assume that contract quantities would remain the same, and it was not an abuse of discretion. See id.

III. Reduction in Water Quantity

Reclamation's decision not to give full and meaningful consideration to the alternative of a reduction in maximum interim contract water quantities was an abuse of discretion, and the agency did not adequately explain why it eliminated this alternative from detailed study. See Te-Moak Tribe of W. Shoshone of Nev. v. U.S. Dep't in Interior, 608 F.3d 592, 602 (9th Cir. 2010); Native Ecosys. Council v. U.S. Forest Serv., 428 F.3d 1233, 1245 (9th Cir. 2005). The four reasons set forth in the EA do not establish the non-viability of the alternative of maximum water quantity reduction. See W. Watersheds Project v. Abbey, 719 F.3d 1035, 1050 (9th Cir. 2013) (holding that existence of viable but unexamined alternative renders EA inadequate).

The first reason given by Reclamation was that the Reclamation Project Act mandates renewal of existing contract quantities when beneficially used. See 43 U.S.C. § 485h-1(1) & (4). The EA stated that the water districts had complied with contract terms, and, according to water needs assessments performed by Reclamation, each water district's needs equaled or exceeded the current total contract quantity. Plaintiffs exhausted administrative remedies as to their argument that Reclamation did not know whether existing water quantities were "beneficially used" because Reclamation did not conduct a proper water needs assessment, as contractually required, and Reclamation's 2006 assessment was inadequate because it was prepared with data from 1999 that predated a land retirement project. See Barnes v. U.S. Dep't of Transp., 655 F.3d 1124, 1132 (9th Cir. 2011) (holding that issue was exhausted when agency had independent knowledge of EA flaw); Lands Council v. McNair, 629 F.3d 1070, 1076 (9th Cir. 2010) (holding that issue is exhausted if agency is provided sufficient information to give it a chance to bring its expertise to bear to resolve the claim). As plaintiffs argue, Reclamation acted unreasonably by relying on stale water needs data. See W. Watersheds Project, 719 F.3d at 1052 (holding that "an agency errs when it relies on old data without showing that the data remain accurate").

Reclamation's second reason for concluding that consideration of a reduction in interim contract water quantities was not warranted was that the Central Valley Project-wide PEIS for long-term contract renewal selected a preferred alternative of renewal "for the full contract quantities." Additionally, the PEIS took into account the balancing requirements of the CVPIA, which provides, among other things, for the weighing of fish, wildlife, and habitat restoration goals. The PEIS did not, however, address site-specific impacts of individual contracts. See W. Watersheds Project, 719 F.3d at 1050-51 (holding that when modification of grazing practices was not considered at programmatic level, it must be given hard and careful look at site-specific level). The government's position that the consideration of reduced-quantity alternatives should be required only with respect to "long-term contract renewals" is unreasonable under the circumstances presented here, involving an ongoing - and hence long-term - series of interim renewals.

Reclamation's third reason was that a shortage provision in the interim contracts provided it with a mechanism for annual adjustments in water supplies. As plaintiffs argue, however, the existence of a mechanism for adjusting water quantities after contract approval did not relieve Reclamation of its obligation to consider a reduction in quantities prior to contract approval. See id. at 1050.

Reclamation's fourth reason was that "retaining the full historic water quantities under contract provides the contractors with assurance the water would be made available in wetter years and is necessary to support investments for local storage, water conservation improvements and capital repairs." This reasoning in large part reflects a policy decision to promote the economic security of agricultural users, rather than an explanation of why reducing maximum contract quantities was so infeasible as to preclude study of its environmental impacts. See id. Moreover, given the shortage provisions in the interim contracts and recent drought conditions, the water districts have not been able to rely on delivery of consistent quantities.

We therefore reverse as to the district court's grant of summary judgment on plaintiffs' claim that the EA was inadequate because it did not give full and meaningful consideration to the alternative of a reduction in maximum water quantities. See id.

IV. Geographic Scope

Plaintiffs contend that the EA's geographic scope was improperly limited to the delivery areas and should also have considered the effects, including cumulative effects, of interim contract renewal on the California River Delta, the source of the water, and on the Delta's fish and other wildlife. See Save Our Sonoran, Inc. v. Flowers, 408 F.3d 1113, 1122 (9th Cir. 2004) (holding that agency must analyze all environmental consequences of action). This contention lacks merit because the EA was tiered off of the PEIS, which addressed Central Valley Project-wide effects of long-term contract renewal. See 40 C.F.R. § 1508.28 (describing tiering). In light of Reclamation's obligation to conduct a more comprehensive analysis in the PEIS, it would be impractical to require the agency to trace the incremental effects of each two-year water service contract on the Delta and all Central Valley Project waters. See Friends of the Wild Swan v. Weber, 767 F.3d 936, 943 (9th Cir. 2014) (stating that agency must balance need for comprehensive analysis against considerations of practicality).

V. Impacts on Listed Species and Cumulative Impacts

Plaintiffs waived their argument that the EA's analysis of the giant garter snake and the California least tern impermissibly equated a finding of no jeopardy under the Endangered Species Act with a finding of no significant impact under NEPA. See Lands Council, 629 F.3d at 1076. Impacts on salmonids and green sturgeon, as well as cumulative impacts related to drainage and selenium, were more appropriately addressed in the PEIS and the San Luis Drainage Feature Re- Evaluation Final EIS, rather than the EA for interim contract renewal. See Friends of the Wild Swan, 767 F.3d at 943.

We affirm the district court's judgment in part. We reverse in part and remand with instructions for the district court to vacate its grant of summary judgment in favor of defendants on plaintiffs' claim that the EA was inadequate because it did not give full and meaningful consideration to the alternative of a reduction in maximum water quantities. On remand, the district court shall direct Reclamation consider such an alternative in any future EA for an interim contract renewal. In satisfying this duty, Reclamation may rely upon any water needs assessment for which the data remain accurate. See W. Watersheds Project, 719 F.3d at 1052.

Each party shall bear its own costs.

AFFIRMED in part, REVERSED in part, and REMANDED.


Summaries of

Pac. Coast Fed'n of Fishermen's Associations v. U.S. Dep't of the Interior

UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT
Mar 28, 2016
No. 14-15514 (9th Cir. Mar. 28, 2016)
Case details for

Pac. Coast Fed'n of Fishermen's Associations v. U.S. Dep't of the Interior

Case Details

Full title:PACIFIC COAST FEDERATION OF FISHERMEN'S ASSOCIATIONS; et al., Plaintiffs …

Court:UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT

Date published: Mar 28, 2016

Citations

No. 14-15514 (9th Cir. Mar. 28, 2016)