From Casetext: Smarter Legal Research

Flamm v. Noble

Court of Appeals of the State of New York
Apr 17, 1947
296 N.Y. 262 (N.Y. 1947)

Summary

holding that "plaintiff is in either event," whether labelled a case of "duress rather than one for fraud," "entitled as matter of law to a recovery of the interest now demanded by him" under New York law

Summary of this case from Dukes Bridge, LLC v. Sec. Life of Denver Ins. Co.

Opinion

Argued January 14, 1947

Decided April 17, 1947

Appeal from the Supreme Court, Appellate Division, First Department, COHALAN, J.

Philip Handelman, Colin C. Ives, S.S. Goldsmith and Leon Wagman for appellant.

Ralph M. Carson, Clarence Fried and Franklin S. Wood for respondent.



By leave of the Appellate Division, the plaintiff brings here for decision the following question certified: "Upon the facts presented herein, where the plaintiff was awarded a verdict in the sum of $350,000.00 in an action for fraud and duress, should the Trial Court have granted plaintiff's motion for an order directing that the sum of $107,508.33 be added as interest to the said verdict herein from January 17, 1941, the date of the wrong, to the date of the rendition of the verdict?" We are to say whether the plaintiff is entitled to such interest as matter of law. The answer of both courts below was in the negative.

The Trial Term Judge took his stand upon Faber v. City of New York ( 222 N.Y. 255). In that case, the question was whether interest should be allowed upon a claim of damages for extra work done in performance of a contract. This court there said: "The question of the allowance of interest on unliquidated damages has been a difficult one. The rule on this subject has been in evolution. Today, however, it may be said that if a claim for damages represents a pecuniary loss, which may be ascertained with reasonable certainty as of a fixed day, then interest is allowed from that day. The test is not whether the demand is liquidated. Was the plaintiff entitled to a certain sum? Should the defendant have paid it? Could the latter have determined what was due, either by computations alone or by computation in connection with established market values, or other generally recognized standards?" (P. 262.) In the Faber case, the plaintiff sued for $159,180. The verdict was for $79,590. Because of that discrepancy and because the plaintiff's extra work had no established market value, a recovery of interest was denied. In the present case, the defendant made misstatements and threats and as the result thereof the plaintiff parted with certain corporate stock for less than its true value. The loss thereby inflicted upon the plaintiff was found by the jury to be $350,000. Since the stock was closely held and was not dealt in on any exchange or in any market, the value thereof was not ascertainable with reasonable certainty as of a fixed day either by computation alone or by computation in connection with generally recognized standards. "The value of this stock [said the Trial Judge] was a straight question of fact presented to the jury on widely divergent testimony." In that state of the record, the plaintiff's motion for an order adding interest to the verdict was rightly denied, if our decision in the Faber case was here applicable.

The Faber case was decided in 1918. The rule thereby declared was a procedural limitation of liability for interest on contract claims of uncertain amount. In 1927 (L. 1927, ch. 623), section 480 of the Civil Practice Act was amended by the incorporation therein of a provision which now reads as follows: "In every action wherein any sum of money shall be awarded by verdict, report or decision upon a cause of action for the enforcement of or based upon breach of performance of a contract, express or implied, interest shall be recovered upon the principal sum whether theretofore liquidated or unliquidated and shall be added to and be a part of the total sum awarded." As thus amended, section 480 means that interest must be paid on a pecuniary loss caused by breach of contract even in a case where the defendant could not determine on any fixed date what was due. ( Preston Co. v. Funkhouser, 261 N.Y. 140, 145, affd. 290 U.S. 163.) The reasons for that statutory innovation are reasons of policy and justice. "The party not performing should not deprive the party not in fault of the use of his money without paying therefor." ( Preston Co. v. Funkhouser, supra, at p. 145.) Consequently, the rule of the Faber case no longer stands in the way of a full recovery of interest as an incident of liability arising from the violation of a contractual obligation.

The plaintiff tries to bring himself within the above amendment of section 480 of the Civil Practice Act by describing the present action as one for breach of a contract implied in law. We cannot adopt that characterization. There is of course authority for saying that restitution of a benefit obtained by fraud may be compelled in an action of assumpsit. But such a theory of action is here excluded by the plaintiff's complaint and by the position he took at the trial, as well as by the question certified to us by the Appellate Division, all of which stamp the present action as a prosecution for fraud or duress. The above amendment of section 480 provides for the addition of interest to a principal sum awarded by verdict, report or decision for breach of contract, and that amendment, therefore, has no bearing upon tort actions of the kind here maintained by this plaintiff. Nor is there any warrant for his assumption that a contrary viewpoint was taken in Weprin Glass Building Corp. v. Rosoff Subway Constr. Co. ( 269 N.Y. 672) and Sciaky v. Rodgers Hagerty, Inc. ( 277 N.Y. 483). To be sure, the tort in both of those cases was trespass to real property; still the recovery in each case was had upon a covenant whereby the obligor had contracted to indemnify the property owner against such a wrong; hence in each case interest was necessarily added to the verdict in compliance with the command of section 480.

The plaintiff is right, however, in his contention that the former rule of the Faber case ( supra) was never regarded by this court as relevant where, as here, the main question was one of liability for a wrong to possession or property. Again and again, awards of interest made in such cases have been sanctioned by us without any inquiry in respect of the ability of the defendant to ascertain with reasonable certainty the extent of the loss he had caused. (See Andrews v. Durant, 18 N.Y. 496; Parrott v. Knickerbocker Ice Co., 46 N.Y. 361; McCormick v. Pennsylvania Central R.R. Co., 49 N.Y. 303; Wehle v. Haviland, 69 N.Y. 448; Wilson v. City of Troy, 135 N.Y. 96.) Indeed in the case last cited — an action for injury to property — this court took pains to declare the inapplicability of "the cases arising upon contract in which it has been held that interest is not allowable". ( Wilson v. City of Troy, supra, at p. 106.)

We come then to the question whether the plaintiff is entitled to interest as matter of law. Under a long-settled New York rule, interest is recoverable of right in actions for trespass and conversion, whereas in actions for injuries done to property through negligence the allowance of interest is left to the discretion of the jury. (See Wilson v. City of Troy, 135 N.Y. 96, supra.) Such a distinction is manifestly unsound, because interest is essential to complete indemnity in both classes of cases. But no decision of this court makes the recovery of interest a matter of discretion where, as here, damages are demanded for a money loss caused by fraud or duress. More than that, Reno v. Bull ( 226 N.Y. 546) — an action for fraud — is authority the other way. This court there said that the true measure of damage in such an action is the actual pecuniary loss sustained, with interest from the time of the wrong. (P. 553.) (See, also, Shaw v. Gilbert, 111 Wis. 165; Nichol v. Sensenbrenner, 220 Wis. 165; Vernson v. Baker, 124 Kan. 575.) The same legal measure of liability should, we think, be here enforced, though the present action may be deemed to be one for duress rather than one for fraud (Restatement, Torts, § 871, comment f); that is to say, the plaintiff is in either event entitled as matter of law to a recovery of the interest now demanded by him.

Several questions of practice remain. The complaint contained no specific demand for interest; the plaintiff made no request that his right to interest be declared by the jury; nor did he give notice of his present motion for a recovery of interest until after expiration of the term at which this case was tried. Nothing turns on any such omission in cases where, under section 480 of the Civil Practice Act, the addition of interest to a verdict is matter of right. (Cf. Greater New York Coal Iron Corp. v. Philadelphia Reading Coal Iron Co., 278 N.Y. 270; Weprin Glass Building Corp. v. Rosoff Subway Constr. Co., 269 N.Y. 672, supra; Civ. Prac. Act, § 479.) On the analogy of that practice, the plaintiff, we think, should be held to be none the worse for his failure sooner to bring forward the issue that we now decide in his favor.

The orders should be reversed, the question certified should be answered in the affirmative and the motion granted, with costs to the plaintiff in all courts.

LEWIS, CONWAY, DESMOND, THACHER, DYE and FULD, JJ., concur.

Orders reversed, etc.


Summaries of

Flamm v. Noble

Court of Appeals of the State of New York
Apr 17, 1947
296 N.Y. 262 (N.Y. 1947)

holding that "plaintiff is in either event," whether labelled a case of "duress rather than one for fraud," "entitled as matter of law to a recovery of the interest now demanded by him" under New York law

Summary of this case from Dukes Bridge, LLC v. Sec. Life of Denver Ins. Co.

In Flamm, the Court of Appeals announced in its dictum that pre-trial interest was to be granted uniformly and as a matter of right in property damage and contract cases without distinction between them.

Summary of this case from Mount Sinai Hospital v. Borg-Warner Corp.

In Flamm v. Noble (296 N.Y. 262) we were called upon to decide whether interest was allowable as of right upon a verdict in an action for fraud and duress.

Summary of this case from Purcell v. Long Is. Daily Press Pub. Co.

In Flamm v. Noble (296 N.Y. 262, 268), concerning a cause of action for fraud and duress, the court stated the following: "We come then to the question whether the plaintiff is entitled to interest as matter of law.

Summary of this case from Sandak v. Combs

In Flamm v. Noble (296 N.Y. 262, 268) the same contention was raised and rejected, the court saying: "The complaint contained no specific demand for interest; the plaintiff made no request that his right to interest be declared by the jury; nor did he give notice of his present motion for a recovery of interest until after expiration of the term at which this case was tried.

Summary of this case from Employers' Assur. Corp. v. Empire Iron

In Flamm v. Noble (296 N.Y. 262), cited by the claimant, the Court of Appeals said (p. 267): "The above amendment of section 480 provides for the addition of interest to a principal sum awarded by verdict, report or decision for breach of contract".

Summary of this case from Matter of Blumenthal
Case details for

Flamm v. Noble

Case Details

Full title:DONALD FLAMM, Appellant, v. EDWARD J. NOBLE, Respondent

Court:Court of Appeals of the State of New York

Date published: Apr 17, 1947

Citations

296 N.Y. 262 (N.Y. 1947)
72 N.E.2d 886

Citing Cases

Mount Sinai Hospital v. Borg-Warner Corp.

Since it is a matter of right, the plaintiffs' failure to demand interest in the complaint or to request…

Mallis v. Bankers Trust Co.

Plaintiffs seek prejudgment interest pursuant to § 5001(a) of New York's Civil Practice Law and Rules,…